You are here

Projects Updates for Topic: PPA

Pages

  1. EGen008 Pursue Solar PPA recommendation - Assessment started

    The iCAP Working Group (iWG) met on May 10, 2018, to discuss and start the assessment of SWATeam recommendation, EGen008 Pursue Solar PPA. The iWG's draft comment on the recommendation was:

    "We support this recommendation. We should issue an RFP for a PPA.

    See SWATeam recommendation EGen008 Pursue Solar PPA here.

  2. EGen008 Pursue Solar PPA recommendation - Submittal

    The eGen SWATeam submitted a recommendation, to the iWG, stating, "Explore the option of a PPA with a local solar developer."

    See attached the SWATeam recommendation, EGen008 Pursue Solar PPA, complete with comments from all the eGen SWATeam members.

  3. EGEN SWATeam Meeting (4.13.17)

    The EGEN SWATeam held another bi-weekly meeting. Topics covered include:

    • Ximing Cai's [in attendance] vision for iSEE and SWATeams
    • Developing a recommendation to expand UIUC solar farm.
    • Developing a recommendation for another clean energy PPA
    • Cost savings for geothermal systems and opportunities for implementation at solar farm and new building sites
  4. EGEN SWATeam Meeting (3.30.17)

    The EGEN SWATeam held another bi-weekly meeting. Topics covered include:

    • Performing preliminary assessment for clean energy PPA
    • Fact sheet using solar farm as basis to estimate land needs and costs of additional solar farm to meet iCAP goal
    • Update on biomass boiler at energy farm
    • Identifying opportunities to purseu implementation of ground source heat pump (GSHP) technology on campus.