Tom, Suhail, and Morgan met to discuss next steps

Posted by Morgan White on August 3, 2011

We're going with electronics, lighting, faucet aerators and running toilets, and weather stripping for student tasks.

Right when I get back on campus, I'll contact you to get me started on getting set up at F&S. Then we'll finalize a plan, and start recruiting people early september. From mid september to mid October, I'll be doing a test run on a house to note how long it takes, and to familiarize myself with what needs to be done by other students. I'll spend a few days training them, and then they'll take from mid october to november to complete their jobs. In the meantime i'll meet with them weekly and give you and Dean updates. We'll have them do 1 house at a time to better track their work quality. Up to the final weeks of the semester they'll write reports and in the spring they'll do a presentation about the whole process and what not. They can earn up to $500 for good work.

~Tom