You are here

Campus Tree Inventory (In Progress)

Project History

Project Family

Description

This project will document existing trees on campus, using a GPS device and collecting tree details into the ArcGIS data layer.  The existing Tree Inventory was last updated in 2006, so it includes trees that have subsequently been removed and it is missing new trees that have been planted.  Through this project, the Tree Inventory will be updated to include all and only existing trees on campus.

Project Team

  • Project Leader:

    Brent Lewis

    Team Members:

    • Ryan Welch
    • Morgan White

Dates

  • Proposed July 1, 2016
    Proposed by Ryan Welch
    Investigated January 12, 2016
    Investigated by Ryan Welch
    Approved July 13, 2017
    Approved by Helen Coleman, Interim Executive Director of F&S
    Started June 15, 2018
    Started by Brent Lewis and Ryan Welch

Themes