  1. Provost Office approves funding for LED Exit Signs

    The Office of the Provost approved $75,000 in one-time funding for the next step in the LED Exit Sign retrofit project.  The funding of $75,000 is for LED Exit Sign lighting replacement, additions, and new building surveys.  Material and labor of $70,000 would be used to replace 343 fixtures in 20 buildings at an average rate of $204/fixture.  An additional $5,000 is proposed to survey 50 campus buildings for exit light counts.  That will provide the input necessary for the next phase, once this phase is completed.

  2. Meeting with F&S officials

    Associated Project(s): 

    Met with the university Facilities and Services officials and LED staff on Wednesday, September 21, 2016, to discuss the progress of LED Campus projects so far. The main focus of the meeting was Exit signs in the buildings. Meeting was hosted by Mogan Johnston, and attended by Ken Buenting, Brian Finet, Steven Bainbridge, and Patty Douglas.

  3. Campus approves an additional $100K for LED Exit Signs

    Associated Project(s): 

    After the successful completion of the recent LED Exit Sign upgrades, the F&S Building Maintenance division has received approval for another round of LED Exit Sign upgrades.  Ken Buenting, Sharon Ball, Ryan Wild, and Morgan Johnston met to discuss the prioritization process for identifying the next buildings to address.  Buildings will be ranked according to student/transient visitor contact hours (if this information can be obtained), results of campus code fire safety reports, and coordination with other projects or funding.

  4. updated list of LED exit sign buildings

    Associated Project(s): 

    FY07 - 13 buildings

    • 112 - MEB
    • 26 - Altgeld
    • 12 - Noyes
    • 99 - Undergrad
    • 210 - DCL
    • 15 - Engineering Hall
    • 152 - Hydrosystems
    • 67 - Loomis
    • 29 - MEL
    • 34 - MSEB
    • 24 - Newmark
    • 13 - Talbot
    • 42 - Transportation Bldg

    FY08 - 12 buildings

    • HARDING BAND BUILDING #4
    • ILLINI HALL #65
    • OPTICAL PHYSICS BUILDING #165
    • ILLINOIS PROGRAM FOR RESEARCH & HUMANITIES #221
    • ARCHITECTURE BUILDING #50
    • NOBLE HALL #90
    • ART & DESIGN #219
    • MUSIC BUILDING #39
    • FLAGG HALL #89
    • UNIVERSITY HIGH SCHOOL #61
    • ARMORY #6
    • FOELLINGER AUDITORIUM #7

    FY14 – CURRENT PROJECT

    • #324 Grainger Library
    • #174 Engineering Sciences
    • #116 Roger Adams Lab
    • #336 Animal Sciences
    • #197 Turner Hall
    • #370 South Studio #5
    • #371 South Studio #7

    OTHER PROJECTS

    • #339 Temple Buell Hall
  5. update on project progress

    Associated Project(s): 

    Ken Buenting, Sharon Ball, Eva Sweeney, Morgan Johnston, and Ryan Wild met to review progress on the LED Exit Sign work.  Ken reported great progress with four buildings complete and one in progress: Grainger, RAL, Animal Sciences Lab, and the Engineering Sciences Building.  They are in Turner Hall now.  Just over $24K has been spent so far through the contractor.  They will move on to the Main Library and the Education Building next.

    The current implementation process is as follows:

    1. Ryan Wild and Morgan Johnston work with others to identify the priority list of buildings.
    2. Eva Sweeney will review records to ascertain whether the fixtures are connected to an emergency generator or will need battery backup.
    3. Sharon Ball and team will do the initial count of fixtures.
    4. Ken Buenting will direct the hired contractor to replace the existing fixtures and provide data sheets for our records.
    5. Eva Sweeney and Ryan Wild will identify additional signage installation needs.
    6. Ken will direct the F&S electricians to install the additional signs.

    Eva had Ken remove Temple Buell Hall from the list because it is being handled through another project.  Also, through other funding, South studio five and seven were completed.

  6. Campus funding allocated for LED exit signs

    Associated Project(s): 

    The LED Campus commitment includes having all the interior wayfinding signs converted to LED by 2025.  This is primarily LED Exit Signs. We had hoped to use the Revolving Loan Fund to implement another phase of the LED Exit Sign project.  However, that funding is only applicable if there is a reasonable payback through utility savings.  LED Exit Signs have a good payback, but not through Utilities.  The savings come from reduced maintenance, which also provides a reasonable payback. Given the shortfall in maintenance funding and the Chancellor’s commitment to becoming an LED campus, Mike Andrechak agreed to provide $100,000 per year for two years toward LED Exit Signs.  This funding could be continued in future years, subject to funding approval.

  7. Revolving Loan Fund approved for $250K for LED Exit Signs

    Associated Project(s): 

    The Revolving Loan Fund is approved to fund $250K in LED Exit Sign improvements.  Here is the description of the project, as reviewed by the RLF committee:

    ======================================

    This project will replace existing exit signs with efficient LED fixtures in approximately (14) campus buildings.  As a result, energy use will be decreased, life safety systems will operate more reliably, and maintenance needs will decrease dramatically.  This is a continuation of projects funded in FY07 and FY08. We are requesting funding in the amount of $250,000, although the work is very scalable and any funding amount can be successfully applied. 

    _________________________________________________________________

    CRITERIA:

    ¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯

    08. VISIBILITY - Very visible.  Building users notice when exit signs are burned out and it may make them feel uncomfortable or unsafe.  It also creates a negative impression of the pride we take in our facilities.

    09. PAYBACK PERIOD - When replacing incandescent, the payback from energy savings alone is about 6-7 years.  Replacement of fluorescent exit signs yields a payback of 8-10 years.  However, the old signs also require maintenance up to 3 times per year.  If one includes this expense, the overall payback improves to 1-2 years.

    10. REDUCTION OF COAL - By reducing overall campus energy use, this will contribute to Abbott Power Plant s ability to reduce the number of generation units in use.  An additional benefit is the reduction in GHG emissions from maintenance vehicles traveling to replace burned out lamps.

    11. FUND SIZE IMPACT - F&S is working with the Illinois DCEO and this project would qualify for about $7,000 in grant rebates.

    12. PROJECT COORDINATION - F&S has a record of success with these projects.  We have developed a project execution method that keeps overhead to a bare minimum, avoids expensive consultant fees, purchases material at bulk prices, and achieves maximum labor efficiency.  F&S Construction Services will execute the work, and F&S Engineering will document results for the DCEO grant.

    _________________________________________________________________

    ISSUES:

    ¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯

    01. REPLACEMENT OF FACILITY SYSTEMS - Existing exit signs are typically long past their expected life, and have many maintenance problems.  The new LED exit signs will have an expected useful life of at least 15-20 years.

    03. IMPACT ON PLANNED PROJECTS - Very little impact on capital projects.  We coordinate to ensure no overlap between buildings selected for exit sign replacement and planned major renovations.

    04. WHAT IF PROJECT IS NOT FUNDED? - If this project is not funded, our campus will continue to expend many maintenance hours keeping these lights operational, and waste electricity on inefficient technology that is over 20 years outdated.

    If this project is partially funded, we will install as many LED exit signs as possible with the funds allocated.

    06. WHAT OTHER DEPARTMENTS ARE AFFECTED BY THE PROJECT? - The buildings we propose are all across campus and used by virtually every college and department.  These units will benefit from improved safety and fewer maintenance disruptions.

    07. RISK FACTORS - No known risk factors.  In fact this work will reduce the risks associated with having nonfunctioning exit signs, and improve life safety for the campus community.  We have executed this type of work in 25 buildings so far without major problems.