You are here

Projects Updates for Topic: Lot F4

  1. Water005 Rainworks Design Lot F4 recommendation - Assessment started

    The iCAP Working Group (iWG) met on May 10, 2018, to discuss and start the discussion on SWATeam recommendation, Water005 Rainworks Design Lot F4. The iWG's draft comment on the recommendation was:

    "Do a feasibility study for lot F4, incorporating the green infrastructure from the conceptualization completed by the students in the award winning rainworks challenge. Potential funding could be requested from the Student Sustainability Committee (SSC)."

    See SWATeam recommendation Water005 Rainworks Design Lot F4 here.

  2. Water005 Rainworks Design Lot F4 recommendation - Submittal

    The Water and Stormwater SWATeam submitted a recommendation, to the iWG, stating, "The appropriate campus units (Parking, Facilities and Services) should begin the process of implementing the award winning green stormwater redesign for parking Lot F4."

    See attached the SWATeam recommendation, Water005 Rainworks Design Lot F4, complete with comments from all the Water and Stormwater SWATeam members.

    Also, attached are the two supporting documents as submitted by the SWATeam.

  3. Meeting 27 September

    Topics of discussion included the planned water audit and parking lots that could be used for studies related to stormwater runoff. A student in the Sustainability minor planned to work with Rabin Bhattarai on the audit. The EPA Rainworks Project would have potential to redesign Parking Lot F4 because Burnsides Laboratory will be torn down.