Projects Updates for Topic: PPA

Pages

  1. Long-Term PPA Recommendation

    In Spring 2016, a recommendation was submitted to allow longer-term contracts for the purchase of renewable power. The institute for Sustainability, Energy, and the Environment (iSEE) is currently reviewing this request with campus legal counsel and Purchasing departments to determine feasible options and potential next steps.

  2. EGen003 PPA term recommendation - Assessment with all comments

    The iCAP Working Group (iWG) met on March 30th, 2016, to discuss the recommendation EGen003 PPA Term and started the assessment. iWG's official recommendation was:

    "We understand that the University is currently advocating for state legislative relief from a number of procurement-related restrictions, and we recommend that the University include in this effort a request to eliminate the 10-year limit on Power Purchase Agreements. If successful, this would allow (but not require) our campus and Prairieland Energy, Inc. to enter into long-term Power Purchase Agreements for renewable energy (including electricity and other renewable fuels) which may offer more favorable terms, perhaps even being less expensive than traditional energy options."

    See the attached file for the complete assessment of this recommendation with comments from all the iWG members.

    See SWATeam recommendation EGen003 PPA Term here.

  3. EGen003 PPA term recommendation - Submittal

    The eGen SWATeam submitted a recommendation to the iWG stating, "Take steps to allow a Power Purchase Agreement for electricity without any restriction on the term of the agreement."

    See attached the SWATeam recommendation EGen003 PPA term complete with comments from all the eGen SWATeam members.

    Attached Files: 
  4. Solar Farm Agreements Signed

    Associated Project(s): 

    CHAMPAIGN, IL (January 20, 2015) –  Construction of a 5.87 megawatt (MW) Solar Farm on campus will begin in Spring 2015 after university and state officials approved power purchase and land lease agreements with Phoenix Solar South Farms, LLC.

    See the attached release, fact sheet, and poster for more details.

  5. F&S response to iWG assessment

    This letter is in response to the Illinois Climate Action Plan (iCAP) Working Group (iWG) recommendation #EG001, which Facilities & Services (F&S) received on August 28.  F&S agrees that the campus should investigate the feasibility of entering into a Wind Power Purchase Agreement (PPA) to increase the use of renewable energy for campus. 

    Regarding the EG001 general statements about campus energy use, data points, and assessments of anticipated financial impacts, F&S will need more time to compile a useful response.  Regarding the three specific EG001 recommendations, I have consulted with Al Stratman, Kent Reifsteck, and Mike Larson to provide the responses below. 

    1. Recommendation: “The campus should undertake a Power Purchase Agreement for wind energy. Based on currently available information, we recommend that the amount be at least 119 million kWh per year (25% of our total electrical usage), but we should aim to purchase as much as we possibly can, given any technical, financial, and contractual constraints.”

    From this recommendation, we understand that the iWG recommends entering into a Wind PPA for at least 25% of the FY15 electrical demand.  However, the campus cannot make an informed decision about whether or not to undertake a PPA until the financial impact is fully understood.  A key component of the financial impact is the fully burdened cost of the purchased wind power, which will not be known until after the successful completion of the Request for Proposal (RFP) process.  Therefore, F&S does support pursuing a PPA so the feasibility can be evaluated, but we do not support making a final decision to undertake a PPA until completely evaluating the financial implications.

    1. Recommendation: “The effort to secure a PPA should be pursued as quickly as possible. The campus should inform PEI that this is a top priority, and that the review of RFI submittals and the issuance of the RFP should be expedited by all necessary means.”

    During this summer, F&S worked with PEI to define a schedule for issuing a Request for Information (RFI) and a subsequent Request for Proposals (RFP).  This schedule shows a completion date of April 2015, so that the PPA could commence with delivery of power on July 1, 2015, at the start of FY16.  We have informed PEI that this is a top priority, along with safety and reliability of the overall campus energy system.

    1. Recommendation: “The iCAP Working Group should be kept informed and advised during the process of pursuing the RFI, RFP, and PPA, and given the opportunity to provide recommendations before key decisions are made about the PPA, to ensure that technical and financial considerations are appropriately balanced with our campus sustainability objectives.”

    F&S values the advice and input from sustainability advocates on campus.  Therefore, we suggest developing a set of interim checkpoints for keeping the iWG informed as the process unfolds.

    To meet our Climate Commitment and achieve carbon neutrality, there is a lot of work that needs to be done.  I look forward to working with the iWG and the SWATeams as this recommendation is pursued.

    Sincerely,

    Morgan B. Johnston

    Associate Director of Sustainability, F&S

  6. Updated RFP schedule from PEI

    Associated Project(s): 

    I am providing an updated schedule for the RFP related to a wind-power PPA for UIUC.  The change reflects a request by one vendor to extend the response period by one week.  Because of that, we have made other slight modifications to target dates for some of the milestones, but the original completion date of April 30, 2015 is maintained.

    If you have any question, please let me know.  Dan Mortland