  1. Water005 Rainworks Design Lot F4 recommendation - Assessment started

    The iCAP Working Group (iWG) met on May 10, 2018, to discuss and start the discussion on SWATeam recommendation, Water005 Rainworks Design Lot F4. The iWG's draft comment on the recommendation was:

    "Do a feasibility study for lot F4, incorporating the green infrastructure from the conceptualization completed by the students in the award winning rainworks challenge. Potential funding could be requested from the Student Sustainability Committee (SSC)."

    See SWATeam recommendation Water005 Rainworks Design Lot F4 here.

  2. Water005 Rainworks Design Lot F4 recommendation - Submittal

    The Water and Stormwater SWATeam submitted a recommendation, to the iWG, stating, "The appropriate campus units (Parking, Facilities and Services) should begin the process of implementing the award winning green stormwater redesign for parking Lot F4."

    See attached the SWATeam recommendation, Water005 Rainworks Design Lot F4, complete with comments from all the Water and Stormwater SWATeam members.

    Also, attached are the two supporting documents as submitted by the SWATeam.

  3. RainWorks Challenge

    Tawab Hlimi is serving as faculty advisor for the 2014 EPA Campus Rainworks Challenge. The team is composed of graduate students from Landscape Architecture, Architecture, Civil Engineering, Environmental Economics, and Ecology. They have begun a green stormwater infrastructure study for the UIUC campus and have selected the channelized extent of Boneyard Creek as site for a demonstration project.