  1. Conservation Budget Recommendation (ECONS003) - Submittal

    The ECBS SWATeam submitted a recommendation to the iWG stating, "We recommend continuing to fund critical projects that are key to energy conservation efforts at UIUC. Given the budgetary constraints of the University of Illinois, the team has developed a prioritized list to guide decision makers about funding priorities. Please see noted references for additional rationale for our recommendations.

    Priority 1 (Top—Most important): RESTORE funding for energy conservation work to FY 15 levels (total of ~$2M) to allow the recommission teams to continue their work. Specifically:

    • Restore $610K in Systems & Controls / Energy Conservation FY 16 cuts (includes $250K Quick Payback.)

    • Provide funding to maintain the $1.15M needed for the 3 existing Recommissioning teams.

    • Protect this initiative from FY 17 budget cuts (including another $ 250K proposed cut in Quick Payback.)

    Priority 2: INCREASE the Recommissioning and Preventive Maintenance (PM) teams. IMPLEMENT systematic upgrades of building control systems.

    • Increase Recommissioning teams from 3 to 4 for FY2017 (increase of $ 350K for FY 17).

    • Provide funding for systematic building control upgrades at $1M/year to allow further conservation.

    Priority 3: MAINTAIN the State Utilities Budget (currently ~$65M/year). This will allow campus to reinvest energy savings in more conservation work while maintaining the ability to cover possible future fuel and power price increases. Future Energy Performance Contracts with ESCOs could be supported by this reinvestment, as well as providing funding support for debt service payments on borrows. We anticipate that another ~$100M will need to be spent on future ESCO/deferred maintenance projects.

    Priority 4: COORDINATE with the Campus Master Plan to retire campus space and reduce overall campus square footage. New capital projects must be optimized for energy conservation. Coordinate campus deferred maintenance estimated at (~$750M) with deferred maintenance projects, campus energy conservation efforts, and campus master plan efforts."

    See attached the SWATeam recommendation ECONS003 Conservation Budget complete with comments from all the ECBS SWATeam members.

    See Supplanted ECONS001 Conservation Budget

  2. Trans007 Campus fleet analysis and Planning recommendation - Submittal

    The Transportation SWATeam submitted a recommendation to the iWG stating,

    "Campus fleet analysis and planning. The campus fleet includes department-owned vehicles, the car and truck pool vehicles, and the heavy equipment pool (mainly diesel-fueled large construction equipment). It is proposed that a feasibility study be performed on campus that:
    1. Reviews the campus sustainability goals in the context of the University fleet;
    2. Analyzes existing fleet data (i.e., fleet composition, ownership, usage/mileage profile) and future demand;
    3. Evaluates current vehicle technology, fleet size, fuel types and availability;
    4. Proposes collection of additional data (if needed);
    5. Identifies various plans and anticipated cost/benefit results. Some of the options include: converting regular fuels to compressed natural gas, electricity, or biodiesel, increasing the portion of low-emission hybrid vehicles.
    "

    See attached the SWATeam recommendation, Trans007 Campus Fleet Analysis and Planning, complete with comments from all the Transportation SWATeam members.

    See the supplanted SWATeam recommendation Trans004 Fleet Study here.

     

  3. Trans001 TEM_DMI recommendation - Supplanted

    The OBFS department sent their response to the iCAP Working Group (iWG) on September 23, 2015, which was then forwarded to the Transportation SWATeam in October. The Transportation SWATeam supplanted the Trans001 TEM_DMI recommendation with the new Trans005 Travel Demand Analysis recommendation.

    See the new SWATeam recommendation Trans005 Travel Demand Analysis here.

    See Transmittal of SWAteam recommendation of Trans001 TEM_DMI here.

    See iWG assessment of Trans001 TEM_DMI here.

    See SWATeam recommendation Trans001 TEM_DMI here.