You are here

Projects Updates for Wind Turbine Generator(s) on South Farms

Search tips:
  • This form will search for words in the title OR the description. If you would like to search for the same term(s) across both the title and description, enter the same search term(s) in both fields.
  • This form will search for any of the words you enter in a field, not the exact phrase you enter. If you would like to search for an exact phrase, put double quotes (") around the phrase. For example, if you search for Bike Path you will get results containing either the word Bike OR the word Path, but if you search for "Bike Path" you will get results containing the exact phrase Bike Path.

Pages

  1. SSC funding award letter

    In October 2010, the Student Sustainability Committee (SSC) wrote a letter to the Office of Sustainability at the U of I recommending that the wind turbine project receive $500,000 in funding with following conditions:

    1) That all funds provided by the SSC be returned in full if the project is postponed, cancelled or placed on hold.

    2) That all funds provided by the SSC for be expended by December 31 st, 2011 and that a final report of all work completed and accounting of funds spent be provided to us by that date as well.

    Attached Files: 
  2. News article about guaranteed return on sustainability investment

    In last week of August 2010, The Daily Illini published an article focusing on the return from sustainability investment -- "Sustainability investment guarantees returns" -- https://web.archive.org/web/20101206070431/http://www.dailyillini.com/op...

  3. iCAP completed

    In May 2010, iCAP was completed with the following goals (for the wind project):

    • Goal is to eventually make the U of I carbon neutral by 2050
    • Describes a path toward the fulfillment of the commitment of the American College & University Presidents’ Climate Commitment (signed by University in 2008)
    • Among the commitment the University is making in order to achieve carbon neutrality goal is renewable energy
    • Target: “Strive to meet the requirements for renewable energy generation in the ILRPS both on campus (priority) and off campus (if necessary) as follows:
      • 5 percent of total campus energy from renewable sources by fiscal year 2015
      • 17.5 percent of total campus energy from renewable sources by fiscal year 2020
      • 25 percent of total campus energy from renewable sources by fiscal year 2025
      • End coal usage at Abbott Power Plant by 2017”
    • Among the 5 strategies to do this: “Install at least three utility-scale wind turbines on the south campus, with a minimum of one to be installed by 2011”
    Attached Files: 
  4. Students' letter to the Governor

    In late January 2009, students wrote a letter to the Governor, Pat Quinn, requesting him for support and assistance in the campus wind farm project. This letter addressed the need of wind generation capacity on campus and requesting the governor to persuade the Chancellor to bring the wind power to the campus.

    Attached Files: 
  5. SSC and SECS letter writing campaign

    In January 2009, the Student Sustainability Committee (SSC) and Students for Environmental Concerns (SECS) wrote letters to the university administration (trustees, Chancellor and Provost’s offices, deans and assistant deans, department heads, faculty and senate faculty) asking for support for the campus wind farm project.

  6. Complaint letter from SSC and SECS

    Following the cancellation of the wind turbine project on South farms, the Student Sustainability Committee (SSC) and Students for Environmental Concerns (SECS) wrote a complaint letter to the Chancellor Richard Herman. SSC and SECS expressed their disappointment about the decision as well as the timing of the decision. They were also upset because the university didn't discuss or consult with the student stakeholders in this decision.

  7. Student protest

    Following cancellation of the wind project, the students were angry about autocratic and secretive behaviour of the university administration regarding cancellation. They were disheartened and upset with the timing of the decision because the decision came during the finals week when the students were pre-occupied and under stress with exams. Students felt that university's choice of cancelling the project during the finals week was to avoid any response or protest from the students.

    However, following the finals week, students protested the decision of cancelling the wind turbine project.

Pages