ICECF 2009 Lighting Retrofit (Completed)

Project History

  • 4/15/2011

    As part of the ICECF 2009 Lighting Retrofit, 177 T-12 fixtures in the Abbott Power Plant were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 27,909 hours.

  • 4/15/2011

    As part of the ICECF 2009 Lighting Retrofit, 115 T-12 fixtures in the Vet Med Chiller Plant were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 28,742 hours.

Description

The ICECF 2009 Lighting Retrofit was the second round of the T-12 to T-8 Lighting Retrofit Project. A total of 33,192 T-12 fixtures were replaced with thinner, more energy effiecient T-8 fixtures. This will incur a total Annual KWh  Savings of 5,335,909 hours. Thirty university buildings were involved in this round of the project. The total Simple Payback is estimated to be 1.17.

Project Team

  • Primary Contact:

    Morgan Johnston

    Project Leader:

    Eva Sweeney

Themes

Project Location(s)

View larger location(s) map