  • 4/13/2017

    The Wind PPA vendor has provided the Feb 2017 Buyer's Share report to Prairieland Energy Inc.

  • 4/12/2017

    The Wind PPA vendor has provided the March 2017 Buyer's Share report to Prairieland Energy Inc. (PEI).  This represents the actual wind power purchased, received, and used on the Urbana campus through the agreement with EDP Renewables (EDPR).

Description

From November 2016 through October 2026, the Urbana campus will receive a percentage-based portion of the wind-generated electricity and associated environmental attributes from the Rail Splitter Wind Farm located north of Lincoln, Illinois. The power purchase agreement (PPA) specifies that 8.6% of the total wind generation from the farm will be sold to the university, which is expected to be an annual amount of more than 25,000 megawatt-hours (MWh).

The 10-year PPA between Prairieland Energy, Inc., a wholly-owned subsidiary of the University of Illinois, and Rail Splitter Wind Farm LLC, a subsidiary of EDP Renewables (EDPR) North America LLC, will significantly increase the amount of renewable energy used by the University of Illinois at Urbana-Champaign. Actual purchased wind power is shared monthly in project updates.

Wind Power Purchased by Month (kWh) (Tracked by Month)

Project Team

  • Primary Contact:

    Morgan Johnston

    Project Leader:

    Kent Reifsteck

    Team Members:

    • Mike Marquissee
    • Mark Krueger
    • Dan Mortland
    • Tony Spurlock
    • Jason Sweet
    • Ben McCall

Dates

  • Proposed April 20, 2014
    Proposed by Kent Reifsteck
    Investigated July 1, 2014
    Investigated by Dan Mortland (PEI)
    Started March 9, 2015
    Started by Mark Krueger (PEI)
    Completed November 1, 2016
    Completed by Praireland Energy, Inc.