Borehole sealed

Posted by Morgan White on December 20, 2018

Hi Everyone, We successfully installed the geothermal loop and fiber optic cable today. The borehole is now grouted closed. My appreciation goes out to the group of colleagues and staff from the ISGS that assisted the drill crew to insert the 400-feet of tubing in the ground.

The drill crew will be back in the morning to clean up the site and move equipment offsite. We still need to install a drop box to store the fiber-optic cable and access the geothermal loop. The box has been ordered and if it arrives in the morning, we may be able to get it installed before the holidays. In about a month we will start measuring the ground temperature and run a DTRT test once the grout cures.

Happy Holidays!!

Andrew