  • This form will search for any of the words you enter in a field, not the exact phrase you enter. If you would like to search for an exact phrase, put double quotes (") around the phrase. For example, if you search for Bike Path you will get results containing either the word Bike OR the word Path, but if you search for "Bike Path" you will get results containing the exact phrase Bike Path.
  1. Water007 SeeClickFix - Successful

    Dr. Mohamad Attalla, Executive Director at F&S, responded to Dr. Ximing Cai, iWG Chair, on August 27, 2019, stating, "We will schedule a meeting with the Land and Water SWATeam to discuss options for achieving the recommendation."

    For further information, please see Green Infrastructure.

    See the transmittal of Water007 SeeClickFix recommendation.

  2. Water006 Lot F23 Monitoring - Returned

    Following the completion of iWG assessment for Water006 Lot F23 Monitoring, the recommendation was returned back to the Water SWATeam so that a proposal for funding this project may be submitted to the Student Sustainability Committee.

    See iWG assessment of Water006 Lot F23 Monitoring attached.

    See SWATeam Recommendation Water006 Lot F23 Monitoring here.

  3. Water004 GSI Standards Parking Lots recommendation - Successful

    Executive Director of Facilities & Services, Mohammed Atalla, responded over email to Ximing Cai (iSEE Associate Director for Campus Sustainability) in support of the recommendation:

    "Facilities & Services will proceed with incorporating Green Stormwater Infrastructure in to the Facility Standards. Brent Lewis is the point person for this effort, and he will add GSI information to each of the relevant standards. This includes but is not limited to the sections on parking lots, transportation, sustainability, and stormwater.

  4. Water005 Rainworks Design Lot F4 recommendation - Successful

    Director of Parking at the University of Illinois, Marty Paulins, responded over email to Ximing Cai (iSEE Associate Director for Campus Sustainability) in support of the recommendation:

    "Parking supports the recommendation to do a feasibility study for Lot F4, incorporating the green infrastructure from the conceptualization completed by the students in the award winning rainworks challenge."

    For future updates on this project, please visit EPA RainWorks Challenge.

  5. Water005 Rainworks Design Lot F4 recommendation - Assessment started

    The iCAP Working Group (iWG) met on May 10, 2018, to discuss and start the discussion on SWATeam recommendation, Water005 Rainworks Design Lot F4. The iWG's draft comment on the recommendation was:

    "Do a feasibility study for lot F4, incorporating the green infrastructure from the conceptualization completed by the students in the award winning rainworks challenge. Potential funding could be requested from the Student Sustainability Committee (SSC)."

  6. Water004 GSI Standards Parking Lots recommendation - Assessment started

    The iCAP Working Group (iWG) met on May 10, 2018, to discuss and start the assessment of Water004 GSI Standards Parking Lots recommendation. The iWG's draft assessment was:

    "F&S should include the minimum requirements of Green Stormwater Infrastructure (GSI) in the Facilities Standards, as described in the Campus Master Plan."

  7. Water005 Rainworks Design Lot F4 recommendation - Submittal

    The Water and Stormwater SWATeam submitted a recommendation, to the iWG, stating, "The appropriate campus units (Parking, Facilities and Services) should begin the process of implementing the award winning green stormwater redesign for parking Lot F4."

    See attached the SWATeam recommendation, Water005 Rainworks Design Lot F4, complete with comments from all the Water and Stormwater SWATeam members.

    Also, attached are the two supporting documents as submitted by the SWATeam.

  8. Water004 GSI Standards Parking Lots recommendation - Submittal

    The Water and Stormwater SWATeam submitted a recommendation to the iWG, stating, "The Facilities and Services Standards for Parking and for Stormwater Systems should be revised to include a greater emphasis on sustainable design Green Stormwater Infrastructure (GSI) for stormwater management. This revision will align these standards with the newly adopted 2017 Campus Master Plan."

    See attached the SWATeam recommendation, Water004 GSI Standards Parking Lots, complete with comments from all the Water and Stormwater SWATeam members.

  9. Water005 Rainworks Design Lot F4 recommendation - Transmittal

    The iCAP Working Group transmitted the Water SWATeam recommendation to do a feasibility study for implementing the award winning RainWorks Challenge student design in parking lot F4 on campus.

    See attached iWG assessment.

    See SWATeam recommendation Water005 Rainworks Design Lot F4 here.

  10. Water001 BIF Greywater Meter recommendation - Transmittal

    Following the completion of iWG assessment of Water001 BIF Greywater Meter, the recommendation was transmitted to the Facilities & Services (F&S) department on July 12, 2017.

    See iWG assessment of Water001 BIF Greywater Meter here. 

    See SWATeam recommendation Water001 BIF Greywater Meter here.

  11. Water001 BIF Greywater Meter recommendation - Assessment with comments

    The iCAP Working Group (iWG) met on December 20, 2016, to discuss and start the assessment of SWATeam recommendation, Water001 BIF Greywater Meter. The iWG's official comment on the recommendation was:

    "A permanent real-time water meter should be installed on the greywater piping system in BIF, and the collected data should be made available in the Energy Billing System and through an online dashboard."

    See attached the iWG assessment of Water001 BIF Greywater Meter complete with official comments from all the iWG members.

  12. Water003 Design Center Greywater Piping recommendation - Denied

    The iCAP Working Group (iWG) met on December 20, 2016, to discuss the SWATeam recommendation, Water003 Design Center Greywater Piping. After some discussion, the iWG rejected this recommendation.

    See SWATeam recommendation Water003 Design Center Greywater Piping here.

  13. Water002 Cooling Tower Increase COC recommendation - Submittal

    The Water and Stormwater SWATeam submitted a recommendation to the iWG stating,

    "We recommend that a small tonnage (< 700 tons cooling capacity) stand-alone cooling tower on campus operating at a water concentration cycle of less than 2.5 be operated using softened water under high pH/high silica conditions to demonstrate near zero blowdown operation."

    See attached the SWATeam recommendation, Water002 Cooling Tower Increase COC, complete with comments from all the Water and Stormwater SWATeam members.

  14. Water001 BIF Greywater Meter recommendation - Submittal

    The Water and Stormwater SWATeam submitted a recommendation to the iWG stating, 

    "Monitoring the water usage in the Business Instructional Facility (BIF). Specifically, both the total water use and the amount of water used by the raw water system should be measured and the data made available to the campus community.