You are here

Projects Updates for eGen Recommendations Summary

Search tips:
  • This form will search for words in the title OR the description. If you would like to search for the same term(s) across both the title and description, enter the same search term(s) in both fields.
  • This form will search for any of the words you enter in a field, not the exact phrase you enter. If you would like to search for an exact phrase, put double quotes (") around the phrase. For example, if you search for Bike Path you will get results containing either the word Bike OR the word Path, but if you search for "Bike Path" you will get results containing the exact phrase Bike Path.

Pages

  1. eGen010 Geothermal Feasibility Study - Returned

    Andy Stumpf provided the following response for eGEN010, "Yes. The summary will be compiled as part of a 'Living Labs' project proposed by the Illinois Water Resources Center."

     

    See the iWG Assessment of eGen010 Geothermal Feasibility Study here.

    See the SWATeam recommendation eGen010 Geothermal Feasibility Study here

  2. eGen009 Campus Geothermal Policy - Successful

    Dr. Mohamed Attalla, Executive Director at F&S, responded to Dr. Ximing Cai, iWG Chair, on August 27, 2019 stating, "We will review options for incorporating geothermal into existing campus documents, and share our thoughts with the iWG before proceeding."

    For further information about this project, please see Geothermal on Campus

  3. eGen009 Campus Geothermal Policy - Transmitted

    Following the completion of iWG assessment for EGEN009 Campus Geothermal Policy, the recommendation was transmitted to Dr. Mohamed Attalla, Director of Facilities & Services.

    See iWG assessment of EGEN009 Campus Geothermal Policy attached.

    See SWATeam Recommendation EGEN009 Campus Geothermal Policy here.

  4. eGen010 Geothermal Feasibility Study - Returned

    Following the completion of iWG assessment for EGEN010 Geothermal Feasibility Study, the recommendation was transmitted back to the Energy SWATeam to conduct additional analysis and investigation of current campus geothermal efforts.

    See iWG assessment of EGEN010 Geothermal Feasibility Study attached.

    See SWATeam Recommendation EGEN010 Geothermal Feasibility Study here.

  5. eGen010 Geothermal Feasibility Study - Submittal

    The eGen SWATeam submitted a recommendation to the iWG, proposing that the university "Enter into a contract with an engineering firm to evaluate
    the feasibility of implementing geothermal energy technologies in future new construction and retrocomissioning of buildings on the UIUC campus."

    See attached the SWATeam recommendation eGen010 Geothermal Feasibility Study complete with comments from eGen SWATeam members.

    An iCAP Working Group assessment of this recommendation began on June 7, 2019.

  6. eGen009 Campus Geothermal Policy - Submittal

    The eGen SWATeam submitted a recommendation to the iWG, proposing the development of "a policy for the consideration of geothermal energy systems in all new or retro-commissioned buildings on UIUC campus."

    See attached the SWATeam recommendation eGen009 Campus Geothermal Policy complete with comments from eGen SWATeam members.

    An iCAP Working Group assessment of this recommendation began on June 7, 2019.

  7. EGen008 Pursue Solar PPA recommendation - Assessment started

    The iCAP Working Group (iWG) met on May 10, 2018, to discuss and start the assessment of SWATeam recommendation, EGen008 Pursue Solar PPA. The iWG's draft comment on the recommendation was:

    "We support this recommendation. We should issue an RFP for a PPA.

    See SWATeam recommendation EGen008 Pursue Solar PPA here.

  8. EGen008 Pursue Solar PPA recommendation - Submittal

    The eGen SWATeam submitted a recommendation, to the iWG, stating, "Explore the option of a PPA with a local solar developer."

    See attached the SWATeam recommendation, EGen008 Pursue Solar PPA, complete with comments from all the eGen SWATeam members.

  9. EGen007 Solar Farm 2.0 recommendation - Assessment with all comments

    The iCAP Working Group (iWG) met on October 27th, 2017, to discuss and start the assessment of the SWATeam recommendation EGen007 Solar Farm 2.0. The iWG's final recommendation was:

    "The iWG agrees that this is the most cost-effective method for meeting the iCAP objective of 25,000 MWh/year of on-campus solar generation by FY25.  To meet that goal, the Solar Farm 2.0 project needs to begin soon, under F&S direction."

    See attached the iWG assessment complete with official comments from all the iWG members.

  10. EGen007 Solar Farm 2.0 recommendation - Transmittal

    The SWATeam recommendation, eGen007 Solar Farm 2.0, was transmitted to the Sustainability Council and was presented during their meeting on December 7, 2017.

    For future updates, please refer to Solar Farm 2.0.

    See iWG assessment of EGen007 Solar Farm 2.0 here.

  11. EGen006 Petascale Offsets recommendation - Transmittal

    Following the completion of iWG assessment, this recommendation was transmitted to the Vice Chancellor for Research (VCR).

    For future updates, please refer to PPA for National Petascale Computing Facility.

    See iWG assessment of EGen006 Petascale Offsets here.

  12. March 2017 Sustainability Council Recommendations Approved

    Interim Provost Wilkin, on behalf of Chancellor Jones, approved moving forward with the recommendations discussed at the March 2017 Sustainability Council meeting. See attached file.

    See iWG follow-up on the March 2017 Sustainability Council meeting here.

  13. EGen003 PPA term recommendation - Successful

    Following the completion of the iWG Assessment, the EGen003 PPA Term recommendation was discussed at the Sustainability Council meeting in March 2017.  In June 2017, Provost Wilkins said, "On behalf of the Chancellor, I'm writing to convey approval of the recommendations. Please do begin encouraging action on the items mentioned. Thank you and the rest of the Council for the diligent and forward-looking thinking on these items."

  14. EGen007 Solar Farm 2.0 recommendation - Submittal

    The eGen SWATeam submitted a recommendation to the iWG stating, "Start a project to expand the existing Solar farm, or install a new large scale solar installation in a new location."

    See attached the SWATeam recommendation EGen007 Solar Farm 2.0 complete with comments from all the eGen SWATeam members.

  15. March 2017 Sustainability Council Recommendations & Next Steps

    Director of iSEE, Evan DeLucia, summarized three recommendations presented at the March 2017 Sustainability Council meeting: EGen005 Rooftop Solar Standard, EGen003 Power Purchase Agreement (PPA) Timeline, and ECons003 Conservation Budget, as well as the next steps, for Chancellor Jones’ approval.

  16. EGen005 Rooftop Solar Standards recommendation - Transmittal

    Following the completion of iWG assessment, the SWATeam recommendation EGen005 Rooftop Solar Standards was transmitted to the Sustainability Council on March 6, 2017.

    See iWG Assessment for SWATeam recommendation EGen005 Rooftop Solar Standard here.

  17. EGen003 PPA term recommendation - Transmittal

    Following the completion of the iWG Assessment, the EGen003 PPA Term recommendation was transmitted to the Sustainability Council.

    See iWG Assessment of EGen003 PPA Term here.

    See SWATeam recommendation EGen003 PPA Term here.

  18. EGen006 Petascale Offsets recommendation - Assessment with all comments

    The iCAP Working Group (iWG) met on February 23rd, 2017, to discuss and start the assessment on the SWATeam recommendation EGen006 Petascale Offsets. The iWG's official recommendation was:

    "This has been an open issue since the 2010 iCAP and the 2015 iCAP.  This should be addressed with the current discussions about supercomputing on campus."

    See attached the iWG assessment complete with official comments from all the iWG members.

  19. EGen006 Petascale Offsets recommendation - Submittal

    The eGen SWATeam submitted a recommendation to the iWG stating, "Continue and/or start discussions with the Vice Chancellor for Research and/or NCSA regarding the development of a plan and budget to procure the offset for all emissions from the National Petascale computing facility as outlined in the 2015 iCAP."

    See attached the SWATeam recommendation EGen006 Pertascale Offsets complete with comments from all the eGen SWATeam members.

Pages