October 2020 construction progress

Posted by Morgan White on October 23, 2020

For this month's progress, the fence has been installed and the statistics are as follows:

 

191 rows with motors and partial torque tubes.

103 with all torque tubes and ready for panels.

79 rows of panels.

 

These numbers are included in each other, i.e., the 103 is included in the 191 and the 79 is included in the 103.

Thank you,

 

Sushanth Girini

Management Engineer,

Facilities & Services,
UES-Utility Distribution, UIUC