You are here

Solar Farm 2.0 construction update from Sushanth Girini at F&S

Posted by Morgan White on September 24, 2020

The Solar Farm 2.0 construction is on schedule to be in service by 1/28/2021. Currently the project is installing approximately 4,400 posts in ground for the panel foundations. One of key objectives is to complete the Golden Row* by end of this month. Once the golden row is completed, inspected, and approved, the construction will be in full force to reach completion. The university is scheduled to perform routine inspections and capture all the underground equipment GPS points for reference. A recycling plan is in place, and the project is coordinating with F&S Transportation to collect the recyclable waste. The installation of a utility switch on the east side of the farm is complete.

Procurement: We have received all the racking equipment and about 80% of the solar panel on site. Transformers and inverters are scheduled to be delivered by end of Oct 2020.

~by Sushanth Girini, management engineer at F&S Utilities and Energy Services

 

Golden Row - is a single row of solar panel constructed by the construction crew. Once the project make sure all the connections are good and row is as per design, it gets approved. It's like a start of what's coming. Like a movie trailer!