First in house 3-Bins delivered
These 2 units were delivered to Noyes 1st floor north and south entry ways 11/12/2024.
These 2 units were delivered to Noyes 1st floor north and south entry ways 11/12/2024.
Fabricated through our own mill shop. Cost to make two of these bins is attached.
Members of the Zero Waste Team analyzed the main buildings in each of the three central quads. Locations of current 3-bins were noted as well as areas where more were needed. The plan is to transition away from single flow trash and recycling bins towards a system where only 3-bins are used in main hallways. This will ensure that there are well marked bins in highly visible areas and will condense the many bins that need to be serviced by university workers into fewer overall bins. Overall this initiative will lead to improved waste management efficiency and increased recycling rates across the campus.
P10H08575 placed in Waste Transfer Station break room
P10H08574 placed in the Materials Research Laboratory
P10H08580 placed on the first floor- East
P10H08581 placed on the first floor- West
P10H08585 placed on basement level
P1H08584 placed on first floor
P10H08583 placed on second floor
P10H08582 placed on third floor
P10H08419 placed on Lower Level C0220 near stairs, P10H08418 placed on second floor C2220 against north brick wall, P10H08117 placed on third floor C3200 east wall/elevator landing, P10H08416 placed on fourth floor C4200 east wall/evelator landing.
P10H08422 placed on the second floor south side, P10H08421 placed on the third floor north side, and P10H08420 placed on the third floor south side.
P10G96450 placed in the cafe, 613, on the south wall near the TV monitor.
P10G96448 placed in the vestibule outside the bottom of the stairwell, C0192.
P10G96449 placed at C100A.
P10H08415 on first floor outside 137, near lecture hall.
P10H08424 outside of room 62 in the basement and P10H0843 in 163C area where the old cafe space used to be.
P10G96447 lower lobby against the west wall.
P10G96446 C108 hallway by stairs.
P10G96445 on first floor near Pennsylvania Ave entrance.
P10G96444 placed near Room 364.
P10G96441 placed on ground floor, P10G96443 placed on second floor, P10G96442 placed on third floor.
Brent, Morgan,
I am working with CSL on a small project for some solar panels near their satellite office in the North Campus Parking Garage. CSL mentioned that Canadian Solar is one of the approved suppliers to the campus.
You probably know that Canadian Solar, in spite of its name, is mostly a Chinese supplier, although they have a more modest plant in Canada. The largest Chinese supplier is Jinko Solar, which in my experience is a bit better in quality.
I am hoping we can spin up a higher-quality U.S. supplier, such as Sunpower, as an alternative to the various foreign providers.
Philip T. Krein, Ph.D., P.E.
----------------------------------
Hi Sush and Brian,
I am working on this research project at the North Campus Parking Deck to put solar panels on the canopy on the outside of the south side of the building. They will be feeding them into a research space to power servers. They actually want to have the panels directly power a battery and then power the servers from the battery. I provided the cutsheets of the panels we used at the President’s Shed. These fit the weight and size dimension requirements. As we have used them before, they are therefore “pre-approved.” One of the researchers, Philip, is asking about using something different in the email below. Can you please assist in a response?
Also, as far as I knew, we hadn’t done any large battery systems on campus. Possibly that is incorrect, but in asking recently I came up with nothing. Please take a look at the cutsheet for the enphase and see if we would be ok with this one. If not, please provide some additional direction.
Thanks!
Brent.
----------------------------
Brent,
I’m not aware that we have approved “vendors” for solar panels nor for inverters and such equipment. Also, I not aware of where we would have a PV system using storage, the few I’m familiar with are grid tie systems.
How big of a system are they looking at?
Brian Curtis Finet, PE
---------------------------
Brian,
We will still tie this to the grid as a back up, back up power supply. They would have 18 panels total along that canopy. I know we don’t have any officially “approved” vendors, but since we used the ones at the President’s House, we had approved them through construction. Originally the researchers picked out what they wanted, but the manufacturer didn’t want to deal with us, so I threw out using the ones we’ve already installed here at least once.
I am not 100% certain if this is to power 3 new servers with 3 new batteries, or 3 new servers, with only one battery. Based on the last email, it appeared we would only be looking at one battery for the backup. I can put you in touch with the MEP if you would rather talk directly.
Thanks,
Brent.
---------------------
Brent,
Apart from Brian’s comments, here some things I would consider if the owner has concerns and this is how I would plan on choosing a panel vendor.
My final thoughts - Sunpower has a better rating, reliability and warranty compared to Canadian solar (last I checked its been a year or so) but it also comes at higher $$.
Thanks,
Sushanth Girini