  1. 28 bin order arrived

    Associated Project(s): 

    On Friday, February 17, the bin order from MAX-R arrived at the Waste Transfer Station. 20 26-gallon bins (standard size) and 8 18-gallon (slim) bins arrived.

  2. Undergraduate Library rehomes 6 3-bins to other facilities on campus

    Associated Project(s): 

    The Undergraduate Library rehomed 6 3-bins at the onset of redevelopment:

    • Armory took 4 (P10E62260 second floor east side right out of the elevator, P10E62264 third floor southside center outside restroom, P10E62261 third floor northside center outside of restroom, P10E62265 in landing area in front of Room 232 under glassed bulletin board).
    • Mechanical Engineering Laboratory took 2 (P10E62262 and P10E62263 on first and second floors).
  3. update on indoor bin count

    Associated Project(s): 

    Just wanted to provide a wonderful update on Indoor bins for the iCAP portal: The campus has 180 out of 200 available multi stream bins deployed in 56 different campus buildings. According to the iCAP metric, we are 1/3 of the way to our FY24 goal. ~Sydney Trimble