  1. Vet Med Chiller Plant

    As part of the ICECF 2009 Lighting Retrofit, 115 T-12 fixtures in the Vet Med Chiller Plant were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 28,742 hours. The simple payback for this project is -0.2 years.

  2. Illinois State Water Survey

    As part of the ICECF 2009 Lighting Retrofit, 1,154 T-12 fixtures in nine buildings belonging to the Illinois State Water Survey were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 181,017 hours. The simple payback for this project is -2.45 years.

  3. Roger Adams Laboratory (completed)

    A portion of the T-12 fixtures in the Roger Adams Laboratory were retrofitted in the 2008 leg of the ICECF Lighting Retrofit. The remaining 2,064 fixtures were replaced in the 2009 Retrofit, however, allowing an additional Annual kWh Savings of 157,759 hours. The Simple Payback for the replacing these fixtures in the remaining portion of the building is 3.34 years.

  4. Undergraduate Library

    As part of the ICECF 2009 Lighting Retrofit, 2,294 T-12 fixtures in the Undergraduate Library were replaced with the more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 508,525 hours. The simple payback for this project is -0.17 years.

  5. Wohlers Hall

    As part of the ICECF 2009 Lighting Retrofit, 1,071 T-12 fixtures in the Wohlers Hall were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 168,358 hours. The simple payback for this project is 0.83 years.

  6. LED Exit Signs Phase 2

    Associated Project(s): 

    Phase 2 of the LED Exit Sign project to replace incandescent exit signage with LED fixtures started on June 30, 2008. This phase of the project will replace fixtures in the Armory, Foellinger Auditorium, Harding Band Building, Illini Hall, the Optical Physics Building, the Illinois Program for Research & Humanities, the Architecture Building, Noble Hall, the Art & Design Building, the Music Building, Flagg Hall, and University High School.

  7. LED Exit Signs Phase 1

    Associated Project(s): 

    Phase 1 of the LED Exit Sign project will replace incandescent exit signage with LED fixtures in facilities used for the Engineering Open House. The building involved are the Material Sciences and Engineering Building,  the Mechanical Engineering Building, the Transportation Building, Altgeld Hall, Morrill Hall, Burrill Hall, Noyes Laboratory, and the Undergraduate Library.