  1. Noyes Laboratory

    Associated Project(s): 

    A total of 1,574 lighting fixtures in the Noyes Laboratory were changed from T-12 fixtures to T-8 fixtures as part of the ICECF Lighting Retrofit. This will allow an Annual kWh Savings of 276,264 hours. The Simple Payback for changing the fixtures in the Noyes Laboratory is 0.94 years.

  2. Davenport Hall

    Associated Project(s): 

    A total of 2,030 lighting fixtures in Davenport Hall were changed from T-12 fixtures to T-8 fixtures as part of the ICECF Lighting Retrofit. This will allow an Annual kWh Savings of 363,141 hours. The Simple Payback for changing the fixtures in Davenport Hall is 1.36 years.

  3. Freer Hall

    Associated Project(s): 

    A total of 629 lighting fixtures in Freer Hall were changed from T-12 fixtures to T-8 fixtures as part of the ICECF Lighting Retrofit. This will allow an Annual kWh Savings of 100,595 hours. The Simple Payback for changing the fixtures in Freer Hall is 2.49 years.

  4. Natural History Building

    Associated Project(s): 

    A total of 2,153 lighting fixtures in the Natural History Building were changed from T-12 fixtures to T-8 fixtures as part of the ICECF Lighting Retrofit. This will allow an Annual kWh Savings of 345,994 hours. The Simple Payback for changing the fixtures in the Natural History Building is 2.37 years.

  5. Main Library (6th Stack)

    Associated Project(s): 

    A total of 379 lighting fixtures in the Main Library (6th Stack) were changed from T-12 fixtures to T-8 fixtures as part of the ICECF Lighting Retrofit. This will allow an Annual kWh Savings of 55,547 hours. The Simple Payback for changing the fixtures in the Main Library (6th Stack) is 6.66 years.

  6. Turner Student Services Building

    Associated Project(s): 

    As part of the ICECF 2009 Lighting Retrofit, 628 T-12 fixtures in the Turner Student Services Building were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 99,474 hours. The simple payback for this project is 2 years.

  7. Wohlers Hall

    Associated Project(s): 

    As part of the ICECF 2009 Lighting Retrofit, 1,071 T-12 fixtures in the Wohlers Hall were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 168,358 hours. The simple payback for this project is 0.83 years.

  8. Foreign Language Building

    Associated Project(s): 

    A total of 2,694 lighting fixtures in the Foreign Language Building were changed from T-12 fixtures to T-8 fixtures as part of the ICECF Lighting Retrofit. This will allow an Annual kWh Savings of 424,790 hours. The Simple Payback for changing the fixtures in the Foreign Language Building is 3.06 years. Occupancy sensors were also installed in this facility for further energy savings.

  9. Krannert Center for the Performing Arts

    Associated Project(s): 

    A total of 1,090 lighting fixtures in the Krannert Center for the Performing Arts were changed from T-12 fixtures to T-8 fixtures as part of the ICECF Lighting Retrofit. This will allow an Annual kWh Savings of 171,871 hours. The Simple Payback for changing the fixtures in the Krannert Center is 2.26  years.

  10. Everitt Electrical Building

    Associated Project(s): 

    A total of 2,059 lighting fixtures in the Everitt Electrical Building were changed from T-12 fixtures to T-8 fixtures as part of the ICECF 2008 Lighting Retrofit. This will allow an Annual kWh Savings of 336,327 hours. The Simple Payback for changing the fixtures in the Everitt Electrical Building is 2.25 years.

  11. Agriculture Engineering Sciences Building

    Associated Project(s): 

    A total of 1,236 lighting fixtures in the Agriculture Engineering Sciences Building were changed from T-12 fixtures to T-8 fixtures as part of the ICECF Lighting Retrofit. This will allow an Annual kWh Savings of 193,605 hours. The Simple Payback for changing the fixtures in the Agriculture Engineering Sciences Building is 2.36 years.

  12. Henry Administration Building

    Associated Project(s): 

    A total of2,135 lighting fixtures in the Henry Administration Building were changed from T-12 fixtures to T-8 fixtures as part of the ICECF Lighting Retrofit. This will allow an Annual kWh Savings of 358,223 hours. The Simple Payback for changing the fixtures in the Henry Administration Building is 1.75 years.

  13. Armory

    Associated Project(s): 

    A total of 2,046 lighting fixtures in the Armory were changed from T-12 fixtures to T-8 fixtures as part of the ICECF Lighting Retrofit. This will allow an Annual kWh Savings of 312,561 hours. The Simple Payback for changing the fixtures in the Armory is 2.56 years. Occupancy sensors were also installed in this facility for further energy savings.

  14. Mumford Hall

    Associated Project(s): 

    A total of 1,508 lighting fixtures in Mumford Hall were changed from T-12 fixtures to T-8 fixtures as part of the ICECF Lighting Retrofit. This will allow an Annual kWh Savings of 240,593 hours. The Simple Payback for changing the fixtures in Mumford Hall is 1.96 years.

  15. Plant Sciences Laboratory

    Associated Project(s): 

    A total of 1,009 lighting fixtures in the Plant Science Laboratory were changed from T-12 fixtures to T-8 fixtures as part of the ICECF Lighting Retrofit. This will allow an Annual kWh Savings of 159,182 hours. The Simple Payback for changing the fixtures in the Plant Sciences Laboratory is 3.25 years.

  16. Madigan Laboratory

    Associated Project(s): 

    A total of 2,587 lighting fixtures in Madigan Laboratory were changed from T-12 fixtures to T-8 fixtures as part of the ICECF Lighting Retrofit. This will allow an Annual kWh Savings of 401,383 hours. The Simple Payback for changing the fixtures in Madigan Laboratory is 2.35 years.

  17. Loomis Laboratory

    Associated Project(s): 

    A total of 2,001 lighting fixtures in Loomis Laboratory were changed from T-12 fixtures to T-8 fixtures as part of the ICECF Lighting Retrofit. This will allow an Annual kWh Savings of 316,267 hours. The Simple Payback for changing the fixtures in Loomis Laboratory is 2.61 years.

  18. Materials Research Laboratory

    Associated Project(s): 

    A total of 2,253 lighting fixtures in the Materials Research Laboratory were changed from T-12 fixtures to T-8 fixtures as part of the ICECF Lighting Retrofit. This will allow an Annual kWh Savings of 360,623 hours. The Simple Payback for changing the fixtures in the Materials Research Laboratory is 1.63 years.

  19. Materials Science Engineering Building

    Associated Project(s): 

    A total of 893 lighting fixtures in the Materials Science Engineering Building were changed from T-12 fixtures to T-8 fixtures as part of the ICECF 2008 Lighting Retrofit. This will allow an Annual kWh Savings of 154,715 hours. The Simple Payback for changing the fixtures in MSEB is 3.99 years.

  20. Mechanical Engineering Laboratory

    Associated Project(s): 

    A total of 1,395 lighting fixtures in the Mechanical Engineering Building were changed from T-12 fixtures to T-8 fixtures as part of the ICECF Lighting Retrofit. This will allow an Annual kWh Savings of 245,845 hours. The Simple Payback for changing the fixtures in the Mechanical Engineering Building is 1.77 years.