  1. Memorial Stadium

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 821T-12 fixtures in Memorial Stadium were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 173,934 hours. The simple payback for this project is 2.41 years.

  2. Central Receiving Building

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 573 T-12 fixtures in the Admin Tech Info Building were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 107,680 hours. The simple payback for this project is 1.8 years.

  3. Atkins Tennis Center

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 185 T-12 fixtures in Atkins Tennis Center were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 3,886 hours. The simple payback for this project is 2.96 years.

  4. FSI Classroom/ Office Building

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 248 T-12 fixtures in the FSI Classroom/ Office Building were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 40,839 hours. The simple payback for this project is 1.08 years.

  5. FSI Fire Station

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 127 T-12 fixtures in the FSI Fire Station were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 20,183 hours. The simple payback for this project is 1.51 years.

  6. FSI Firemanship Training Facility

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 51 T-12 fixtures in the FSI Firemanship Training Facility were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 8,576 hours. The simple payback for this project is 3.28 years.

  7. FSI South Storage Building

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 10 T-12 fixtures in the FSI South Storage Building were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 1,139 hours. The simple payback for this project is 12.71 years.

  8. FSI Storage Building

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 26 T-12 fixtures in the Admin Tech Info Building were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 3,048 hours. The simple payback for this project is 18.86 years.

  9. FSI Hazmat Storage Building

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 20 T-12 fixtures in the FSI Hazmat Storage Building were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 2,278 hours. The simple payback for this project is 6.64 years.

  10. Main Library (Remainder)

    Associated Project(s): 

    As part of the Lighting Retrofit #5, the remaining 5,646 T-12 fixtures in the Main Library were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 849,998 hours. The simple payback for this project is 3.11 years.

  11. Natural Resources Building

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 2,711 T-12 fixtures in the Natural Resources Building were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 424,466 hours. The simple payback for this project is 2.2 years.

  12. LED Exit Signs Phase 2

    Associated Project(s): 

    Phase 2 of the LED Exit Sign project to replace incandescent exit signage with LED fixtures started on June 30, 2008. This phase of the project will replace fixtures in the Armory, Foellinger Auditorium, Harding Band Building, Illini Hall, the Optical Physics Building, the Illinois Program for Research & Humanities, the Architecture Building, Noble Hall, the Art & Design Building, the Music Building, Flagg Hall, and University High School.

  13. LED Exit Signs Phase 1

    Associated Project(s): 

    Phase 1 of the LED Exit Sign project will replace incandescent exit signage with LED fixtures in facilities used for the Engineering Open House. The building involved are the Material Sciences and Engineering Building,  the Mechanical Engineering Building, the Transportation Building, Altgeld Hall, Morrill Hall, Burrill Hall, Noyes Laboratory, and the Undergraduate Library.