  • This form will search for any of the words you enter in a field, not the exact phrase you enter. If you would like to search for an exact phrase, put double quotes (") around the phrase. For example, if you search for Bike Path you will get results containing either the word Bike OR the word Path, but if you search for "Bike Path" you will get results containing the exact phrase Bike Path.
  1. SAIC Report in the iCAP: Lighting

    Associated Project(s): 

    The campus is in the process of retrofitting older T12 fluorescent lighting fixtures by replacing them with more energy-efficient T8 (or T5) fixtures and electronic ballasts. The lighting retrofit proposed in the SAIC report would reduce campus energy consumption by ~1.6 percent; a very small amount of this is due to the use of occupancy sensors and day lighting controls. Extending this retrofit  to smaller campus buildings, replacing other lighting fixtures (besides T-12s), and a wide deployment of both occupancy and daylight sensors (which can reduce  lighting use by 20 percent to 80 percent depending on location) should be able to  provide significantly more energy savings than predicted in the SAIC...Expand »

  2. SAIC Report in the iCAP: Envelope

    Associated Project(s): 

    The SAIC report derives most of its envelope-related savings from window replacement and roof insulation, assuming that only 1 percent of campus energy can be saved by weatherization. The report did not consider changes such as entry-way retrofits to reduce heat loss during entry and exit or improvements in insulation in areas besides roofs. Additionally, the report made no estimation of chilled water savings due to either weatherization or wall insulation, or any potential savings from decreasing heat gain through roofs due to improved reflectivity or vegetative roofs. Improvements to building envelope, weatherization, improving insulation levels in roofs and other areas, and tightening building infiltration&...Expand »

  3. SAIC Report in the iCAP: Building (Retro) Commissioning

    Associated Project(s): 

    Commissioning for existing buildings (sometimes referred to as retro-commissioning or RCx) is a systematic process for investigating, analyzing, and optimizing the performance of building systems by improving their operation and maintenance to ensure their continued performance over time. This process helps make the building systems perform interactively to meet current facility requirements. The campus RCx teams have found a 29 percent average reduction in energy use and emissions for the 14 existing buildings (2,347,170 sq. ft.) they have examined. This success rate shows that there is enormous potential for this reduction strategy. Campus RCx activities have included: repairing and recalibrating...Expand »

  4. SAIC Report in the iCAP: Fume Hoods

    Associated Project(s): 

    The campus is estimated to have between 1,700 and 1,800 fume hoods in operation at the present time. The majority of these are constant air volume (CAV) hoods without heat recovery that operate continuously. Several hundred variable air volume (VAV) hoods also exist, which are in operation only when the hood sash is raised. These hoods, however, are often operated continuously. Based on a Trane TRACE energy model for a typical fume hood on campus, the cost of conditioning air to replace the air vented by a CAV fume hood over the course of a year is estimated to be approximately $5,500 per year. The energy model also predicts an energy usage for VAV hoods, CAV hoods using heat recovery, and VAV hoods using...Expand »

  5. SAIC Report in the iCAP: Information Technology (IT) and Electrical Equipment

    Associated Project(s): 

    The SAIC report assumes very little potential for savings from the purchase of ENERGY STAR® equipment such as computers and printers. Thin client computers being deployed on campus today offer the potential for a 90 percent reduction in energy use compared to desktop computers. A broad deployment of low-energy computing equipment, server virtualization, consolidation of IT facilities (web servers, file servers, terminal servers) and reduction in the total number of server instances can all yield significant savings on both costs, equipment purchase expenses, and campus IT costs. Use of standards more aggressive than ENERGY STAR® for all equipment purchases (i.e. washers and dryers in residence halls, etc.)...Expand »

  6. SAIC Report in the iCAP: Behavioral Changes and Incentives

    Associated Project(s): 

    Although the SAIC report describes the potential energy savings from behavioral changes in its section on metering, it does not include it in its analysis. The University believes a well designed incentive and education program can reduce campus energy consumption by at least 5 percent. Such a program should seek to ensure that cost savings from energy conservation measures benefit building users (e.g. “energy rebates” to students in high-performing departments, or energy-driven reductions in overhead rates for faculty). In addition, adding real-time energy displays in campus buildings and via electronic media can help promote awareness and incentive for improvement. Many buildings have limited or no...Expand »

  7. SAIC Report in the iCAP: Other HVAC

    Associated Project(s): 

    This category includes conversion from constant air volume reheat to variable air volume, eliminating summer steam usage (reheat), heat recovery, variable speed drives for fans and pumps, and steam system maintenance (including trap replacement and pipe insulation). The target for other HVAC is 12.5 percent.

  8. SAIC Report in the iCAP: Hot Water

    Associated Project(s): 

    This category includes using instantaneous and semi-instantaneous hot water heaters, increasing insulation on hot water tanks, utilizing recovered heat from chiller condensers and other sources, and temperature setbacks. The target for hot water is 4.5 percent.