Michael McKelvey and Sarthak Prasad met to continue discussing how to handle projects with large numbers of metrics in the iCAP Portal.
Discussion/Decisions
- Option #1: continue showing metrics in accordion on project page
- Pros:
- No new effort needed
- Cons:
- Lots of metrics on a single page - kind of overwhelming
- Page load could get slow
- Pros:
- Option #2: parent project for all pedestrian & bicycle counts with a sub-project for each counter, similar to how Solar Power on Campus is set up
- Pros:
- Only 1 metric per page
- Simple solution
- Easy to find each counter in hierarchy
- Cons:
- 30+ new projects - hierarchy bloat?
- Don't see all the metrics together; have to visit each project to see its metric
- Pros:
- Option #3: show all metrics on a single graph
- Pros:
- See everything in one place
- No new projects needed
- Cons:
- New feature requires additional work to implement
- Graphing dozens of items makes it hard to differentiate them - too much data
- Pros:
- Things to consider:
- What information do we want people to get from the data? Comparison of pedestrian vs bicycle? Comparison of various locations?
- Discuss graphing long-term metrics
TODOs:
- Bring options to larger group
- Sarthak will investigate whether Eco Counters website could allow embedding of their visualizations