You are here

Projects Updates for place: Campus Instructional Facility

  1. Outfitting main quads with 3-bins

    Associated Project(s): 

    Members of the Zero Waste Team analyzed the main buildings in each of the three central quads. Locations of current 3-bins were noted as well as areas where more were needed. The plan is to transition away from single flow trash and recycling bins towards a system where only 3-bins are used in main hallways. This will ensure that there are well marked bins in highly visible areas and will condense the many bins that need to be serviced by university workers into fewer overall bins. Overall this initiative will lead to improved waste management efficiency and increased recycling rates across the campus.

    Attached Files: 
  2. Recycling Bin Update 04/01/24

    Associated Project(s): 

    Hi Todd & Mark,

    I hope this message finds you well. I wanted to reach out & reconnect on the topic of the black, metal outdoor bins. I believe we have 18 identified locations approved by Brent Lewis ready to be installed as soon as the shops are able (locations attached) – these all require concrete poured. We then have  ~56 more stored primarily in the Buenting Barn that we have not yet identified locations for, but will very shortly. Some of them will require concrete and others will not. We have WO# 10814481 for this project.  Pete is hoping to have the whole process wrapped up by June 30, 2024. I just wanted to put this back up on the radar and get a sense of whether we will be able to get these all installed by summer?...Expand »

  3. Outdoor Bins Follow Up

    Associated Project(s): 

    Hi all,

     

    We have completed all outdoor bin location proposals. With all the photos it is a large document, so I have placed it on a shared Box. Please let me know if any of these locations need further clarification

    In response to your question below of completion by June 30 that is not possible.  Also, without knowing all of the locations it is difficult to give you an answer as to what the completion timeframe would be.  Below are the two scenarios depending on the proposed locations of the bins.

    Installing the bins on existing concrete:

     1.   Ironworkers can go to the site with the bins/post with two guys and install the anchors and the bins in 2-3 crew hours (4-6 hours total with two guys).

    Installing...Expand »

  4. Greywater System in the CIF Feasability Study Paper

    Good afternoon Mr. Sims,

     

    My name is Juliette Deley and my team, Team 9, recently presented to you as part of our final project for CEE 190, Project Based Introduction to Civil & Environmental Engineering. Attached to this email is the paper to our feasibility study on implementing a greywater system in the Campus Instructional Facility.

     

    Again, thank you for taking the time to hear our presentation earlier today,

     

    Best,

    Juliette D. 

    --------------------

    Morgan, Jeremy, Katie and Mike,

     

    I attended freshman level Civil Engineering class project presentations last week. One of the presentations was their study regarding greywater system at CIF. They sent me their report.

     

    I...Expand »

    Attached Files: 
  5. Brent Lewis approves 17 more dual bin locations

    Associated Project(s): 

    On July 18th, Brent Lewis approved 16 more sites for installation, and the site on Champaign property was approved on July 6. On September 6th, these 17 sites plus the 7 additional sites sent to earlier this summer on June 7th (the eighth site at Siebel Center for Computer Science was installed on August 1st, so it was omitted from this spreadsheet), were sent to the iron workers for a total of 24 sites.

     

    55 dual bins remain in storage and need site proposals from the zero waste team and approval from Brent Lewis.

  6. 1 outdoor dual bin installed at Siebel Center for Computer Science

    Associated Project(s): 

    79 outdoor dual bins remain in storage.

     

    From: Hawkins, Todd B <hawkns@illinois.edu>
    Sent: Tuesday, August 1, 2023 8:03 AM
    To: Hulse, Daphne Lauren <dlhulse2@illinois.edu>
    Cc: Mininger, Timothy R <mininger@illinois.edu>
    Subject: FW: Siebel recycle bins

     

    Good morning. The recycle bins for site A8 SW. corner of Siebel were installed yesterday afternoon.

    Thank you.

     

     

     

     

    Todd Hawkins

    Foreperson

    University of Illinois

    F&S Ironworkers

    Office   217-244-5451

    Mobile 217-493-9814

    1501 S. Oak St

    Champaign Il, 61820

     

     

    Attached Files: 
  7. City of Champaign approves new bin location at Psychology Building

    Associated Project(s): 

    From: Marchello Graddy <marchello.graddy@champaignil.gov>
    Sent: Thursday, July 06, 2023 12:49 PM
    To: DeLorenzo, Stacey <sdeloren@illinois.edu>; Harman Jordan <Harman.Jordan@champaignil.gov>
    Cc: White, Morgan <mbwhite@illinois.edu>
    Subject: RE: [Needs approval] outdoor dual bin installation at Psychology Building

     

    Stacey,

    I’ve looked into this and there is no issue with you replacing the existing concrete can.  Please just minimize its encroachment into the walking path.

     

    Thanks,

    Marchello

     

    From: Hulse, Daphne Lauren
    Sent: Friday, June 23, 2023 10:31 AM
    To: White, Morgan <mbwhite@illinois.edu>
    Subject: [Needs approval] outdoor dual bin installation at Psychology Building

     

    Hi...Expand »

Pages