Projects Updates for place: Ceramics Kiln House

  1. Ceramics Building

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 531 T-12 fixtures in the Admin Tech Info Building were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 96,045 hours. The simple payback for this project is 2.96 years.

  2. Geological Survey Laboratory

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 225 T-12 fixtures in the Geological Survey Laboratory were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 44,856 hours. The simple payback for this project is 2.59 years.

  3. Garage/ Car Pool

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 445 T-12 fixtures in the Admin Tech Info Building were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 70,200 hours. The simple payback for this project is 2.79 years.

  4. Mailing Center

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 218 T-12 fixtures in the Mailing Center were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 33,971 hours. The simple payback for this project is 2.4 years.

  5. Children's Research Center

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 725 T-12 fixtures in the Children's Research Center were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 115,133 hours. The simple payback for this project is 3.53 years.

  6. Police Training Institute

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 604 T-12 fixtures in the Police Training Institute were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 90,436 hours. The simple payback for this project is 3.73 years.

  7. Memorial Stadium

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 821T-12 fixtures in Memorial Stadium were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 173,934 hours. The simple payback for this project is 2.41 years.

  8. Central Receiving Building

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 573 T-12 fixtures in the Admin Tech Info Building were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 107,680 hours. The simple payback for this project is 1.8 years.

  9. Atkins Tennis Center

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 185 T-12 fixtures in Atkins Tennis Center were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 3,886 hours. The simple payback for this project is 2.96 years.

  10. FSI Classroom/ Office Building

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 248 T-12 fixtures in the FSI Classroom/ Office Building were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 40,839 hours. The simple payback for this project is 1.08 years.

  11. FSI Fire Station

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 127 T-12 fixtures in the FSI Fire Station were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 20,183 hours. The simple payback for this project is 1.51 years.

  12. FSI Firemanship Training Facility

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 51 T-12 fixtures in the FSI Firemanship Training Facility were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 8,576 hours. The simple payback for this project is 3.28 years.

  13. FSI South Storage Building

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 10 T-12 fixtures in the FSI South Storage Building were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 1,139 hours. The simple payback for this project is 12.71 years.

  14. FSI Storage Building

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 26 T-12 fixtures in the Admin Tech Info Building were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 3,048 hours. The simple payback for this project is 18.86 years.

  15. FSI Hazmat Storage Building

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 20 T-12 fixtures in the FSI Hazmat Storage Building were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 2,278 hours. The simple payback for this project is 6.64 years.

  16. Main Library (Remainder)

    Associated Project(s): 

    As part of the Lighting Retrofit #5, the remaining 5,646 T-12 fixtures in the Main Library were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 849,998 hours. The simple payback for this project is 3.11 years.

  17. Natural Resources Building

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 2,711 T-12 fixtures in the Natural Resources Building were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 424,466 hours. The simple payback for this project is 2.2 years.