  • This form will search for any of the words you enter in a field, not the exact phrase you enter. If you would like to search for an exact phrase, put double quotes (") around the phrase. For example, if you search for Bike Path you will get results containing either the word Bike OR the word Path, but if you search for "Bike Path" you will get results containing the exact phrase Bike Path.
  1. UIUC Micro Nano

    Associated Project(s): 

    Mario,

     

    EMS Controls (David Hardin’s group) is working on a controls upgrade at Micro Nano. I am trying to connect Ayush (cc’d) with someone who can discuss the engineering on the ESCO project and potential ECM’s that were evaluated but ultimately not included in the project. Are you a good contact for this or should I reach out to GBA (Mike/Tim)?

     

    Thanks,

     

    Amber Perfetti

    -------------------------

    Amber,

     

    I think Mike would be best.  I don’t have access to any of the work we did with ESG.  Maybe Jim C can help as well ?

     

    Mario Zotta P.E.

    ---------------------

    Hey Amber,

     

    Thanks for getting this conversation started. Can you share Mike and Jim’s email ID’s? I can try contacting them.

     

    Thank you,

    Ayush

    -----------------------

    Dear Jim and Mike,

     

    EMS Controls (David Hardin’s group) is working on a controls upgrade project at Micro Nano. Is there someone with whom we can discuss the potential ECM’s that were evaluated but ultimately not included in the ESCO project?

     

    Thank you,

    Ayush Gupta

    -----------------------

    Ayush: 

     

    Jim and I will circle our wagons next week and get together with you by the  weeks end.

    Michael J. McDermott

    ----------------------

    Thank you, sir. That would be great.

     

    Regards,

    Ayush

    ---------------------

    Ayush:

     

    I was able to reach out to Deon Collins and review the 2014 ESG Unfunded list, 2011 VFA Deferred maintenance back log and 2012 Cannon MEP Condition Assessment.    We were able to start a preliminary list of energy conservation measures/deferred maintenance items for consideration:

     

    1. Add DDC control for three (3) existing humidifiers - $30,000
    2. DDC upgrade for AHU-18, 19 and 20 - $225,000
    3. Replace AHU-15 (16,000 cfm ) & 16 (21,600 cfm) (Alternate 3) - $700,000
    4. Replace AHU-13 (16,000 cfm) and AHU-14 and add Heat Recovery (Alternate 4) – $2.9 million
    5. Main building steam valve replacement (ECM-8)- $200,000
    6. Pipe Insulation (ECM-10)- 125,000
    7. Active Media Filtration (ECM-15)- $800,000
    8. Main Building Chilled Water Valve Replacement - $60,000
    9. New Building DDC upgrade
    10. New Building southwest section Lab Upgrade and VAV conversion
    11. E-17A & B (25,600 cfm each) – Replace exhaust fan and move to roof - $1,200,000
    12. E-18A&B (10,600 cfm each) – Replace exhaust fan and move to roof - $600,000
    13. High Efficiency Fume hood and VAV conversion upgrade
    14. Heat recovery Chiller
    15. Acid, Solvent and Special Gas Scrubber Replacement – $700,000
    16. Replace chilled water system - $221,000
    17. Replace steam and Condensate - $108,700
    18. Replace AHU-9(22,000 cfm) , AHU-10 (22,000 cfm), AHU-11 (5,200 CFM) , AHU-12(8,000 cfm) , and AHU-17(34,000 cfm) - $1,600,000
    19. Replace ventilation systems for AHU-11 and AHU-17 - $720,000
    20. Replace AHU-1,2 3,4 &5 - $1,500,000
    21. Replace general exhaust EF-5 - $20,000
    22. Domestic hot water heater-$200,000
    23. Acid waste system – $325,000
    24. Process water system - $300,000
    25. Vacuum system - $220,000
    26. Emergency power system- $300,000
    27. Exit lighting – $25,000
    28. Lighting control systems - $250,000
    29. Exterior Lighting- $20,000

     

     

    Call if you have any questions.  

    ----------------------------------

    Hey David,

     

    Below is the list of unfunded ECMs and deferred maintenance items that were considered but not acted upon by ESCO.

     

    Thank you,

    Ayush

    ------------------------------------------

    Ayush,

     

    This is useful information and provides a starting point.

     

    Thanks

     

    Hey everyone,

     

    Here is some info from Mike McDermott from their ESCO review.

     

    Thanks

  2. Provost Office approves funding for LED Exit Signs

    The Office of the Provost approved $75,000 in one-time funding for the next step in the LED Exit Sign retrofit project.  The funding of $75,000 is for LED Exit Sign lighting replacement, additions, and new building surveys.  Material and labor of $70,000 would be used to replace 343 fixtures in 20 buildings at an average rate of $204/fixture.  An additional $5,000 is proposed to survey 50 campus buildings for exit light counts.  That will provide the input necessary for the next phase, once this phase is completed.