You are here
- Home
- Recommendations
- ECONS006 Energy Conservation Funding 2017
ECONS006 Energy Conservation Funding 2017
Original Recommendation
We recommend the following actions and funds to implement critical projects key to energy conservation efforts at UIUC. Total funds needed: $3.55M
- RESTORE funding of ~ $1.5M in FY19, compensating for loss of DCEO grants (Department of Commerce and Economic Opportunity), to continue the Retro-commissioning (RCx) work. Retro-commissioning = Identifying and implementing operational and maintenance improvements to existing buildings (first pass) to ensure continued optimal performance over time.
- INCREASE the Recommissioning (REx) and Preventive Maintenance (PM) teams. Re-commissioning = Building operating and maintenance systems are examined, parts may be fixed or replaced, and systems reset as if they were being installed new. REx is usually performed about 5 years after RCx has passed thru a building and reoccurs about every 5 years going forward. Preventive Maintenance = actions to preserve life of equipment and prevent breakdowns (cleaning of coils, review of air handling unit systems, review of hydronic systems.) Occurs before recommissioning. The PM group reports to the maintenance side of the organization whereas the RCx and REx teams report to Utilities and Energy Services. In terms of priority:
- Change the 5th recommissioning team that is temporary for FY18 to make it permanent in FY19 ($350K/year)
- Increase Building Maintenance and Preventive Maintenance teams from 1 to 2 for FY19. ($ 350K for 2nd team)
- Implement systematic building control upgrades to enhance further energy conservation and/or replace outdated equipment (IT audit item) ($1M/year).
- Increase Recommissioning teams from 5 to 6 for FY2019 ($350K for 6th team).
Recommendation Updates
Date | Status | Update |
---|---|---|
5/11/2018 | Successful | ECONS006 approved by matthew Tomaszewski |
4/10/2018 | Transmitted | ECON006 transmitted to Provost Andreas Cangellaris |
3/28/2018 | Assessment Completed | iWG met to discuss and assess ECONS006 |
11/27/2017 | Submitted | ECBS SWATeam submitted ECONS006 |
No description has been provided yet.
Current Status
Successful