You are here

18F Semesterly Report - BIF Rooftop Solar

Posted by Cathy Liebowitz on December 17, 2018

 

The BIF project was initially scheduled to begin in January 2018, but was on hold until F&S and the College received word from the state regarding the general contractor award.  The kickoff meeting took place in March 2018 and a planning meeting followed in April. 

 

On Monday, May 21st, construction kicked off and is expected to be complete summer 2019.  Thus far, the following work has been completed (64% complete):  removal of rooftop garden; insallation of steel, metal, and concrete decking; roof membrane installed; installation of roof drain lines; installation of exterior and interior walls;  window and ductwork installation; HVAC updates/upgrades; above ceiling mechanicals and sprinkler lines installed; GWB taping and sanding with painting underway.