The BIF project was initially scheduled to begin in January 2018, but was on hold until F&S and the College received word from the state regarding the general contractor award. The kickoff meeting took place in March 2018 and a planning meeting followed in April.
On Monday, May 21st, construction kicked off and is expected to be complete summer 2019. Thus far, the following work has been completed (64% complete): removal of rooftop garden; insallation of steel, metal, and concrete decking; roof membrane installed; installation of roof drain lines; installation of exterior and interior walls; window and ductwork installation; HVAC updates/upgrades; above ceiling mechanicals and sprinkler lines installed; GWB taping and sanding with painting underway.