  1. Work order for MSEB occ sensor work

    Associated Project(s): 

    Work Request 141288 converted to Work Order 10288695

    Work Order: 10288695

    Building: 0034 - MATERIALS SCIENCE AND ENG BLDG

    Room:

    Department Reference:

    Customer Description:

    Please provide engineering design services to install lighting occupancy sensors and HVAC occupancy sensors in the Materials Science and Engineering Building (MSEB).  Charge CFOP 1-762417-862004-xxxxxx-198000.

    Phases:

    Phase: 001 DESIGN SERVICES

  2. Spurlock ECIP project

    Mike,

    As we discussed on the phone, our Electricians have visited with the folks at Spurlock and secured a preliminary scope of work (see attached). Because of the complex existing lighting system in the building our Electricians will require some assistance from our In-House Engineering staff. I understand that Spurlock has been allotted $22K for this work. I am going to ask Robert to give us an estimate of the Engineering charges and if they exceed 10% of the budget we will discuss scaling back some of the scope with the folks at Spurlock. The AiM project is 2693 and the Engineering estimate work order is 10282137.

    Thanks,

    Thomas Doud

    Construction Superintendent

    Construction Services Division

    University of Illinois, Facilities and Services

    217-244-3686

    Attached Files: 
  3. News about Christopher Hall winning

    Saving energy pays off for Christopher Hall

    Clayton Glazik 3/5/2014

    Since we were little our parents have told us to turn off the lights after we leave a room. That is just what the Christopher Hall residents at the University of Illinois did in 2013. By shutting the lights off in rooms not in use, switching their lights to compact fluorescent light (CFL) bulbs, as well as other sustainable practices, the building was able to cut back its energy usage by 30.6% from the previous year.

    The campus Facilities & Services (F&S) hosted a reception at Christopher Hall on February 14 to celebrate the building’s accomplishment in the F&S Energy Conservation Incentive Program (ECIP). A campus-wide sustainability effort, ECIP provides building upgrades to facilities that produce top energy conservation results in energy advancement and occupant action categories. ECIP calculates how much money the buildings are saving in energy reduction and gives it back to the building to pay for upgrades.

    Christopher Hall, which houses the Family Resiliency Center (FRC), the Autism Program (TAP), several classrooms, faculty and staff offices, and a family research home, saved nearly $22,000. According to FRC Director Barbara Fiese, a building committee recommended investing the funds in a bike rack since so many people cycle to work, as well as other items that can further reduce energy usage.

    In 2010, the University of Illinois published a climate action plan that set aggressive timeliness for reducing energy consumption on campus. Currently, there are more than 300 such active projects, which can be tracked at http://icap.sustainability.illinois.edu/projects.

    “At the end of the day, if we really want to meet ICAP goals, we have to do more,” says Al Stratman, F&S executive director. “That is why we came up with ECIP, which mirrors the campus goals.”

    At the award ceremony, faculty and students pledged to continue reducing energy in their lifestyles by taking public transportation, using natural light in their offices rather than electricity, and shopping more at local food markets instead of commercial grocery stores. With their current sustainable practices and these recent pledges, Christopher Hall will continue slashing their energy consumption, making the Illinois campus a greener place.

    (from Family Resiliency Center news http://illinois.edu/lb/article/3493/82438)

  4. News about Library winning

    Libraries Win Energy Awards

    Jan 23, 2014

    The Energy Conservation Incentive Program (ECIP) at Illinois awards building upgrades on campus in facilities which have produced top energy conservation results. Each year eight campus buildings receive ECIP awards in two separate categories. Those selected have demonstrated the greatest percentage of energy conservation over a one-year period.

    In 2013, three of eight awards went to Urbana campus libraries. The Undergraduate Library won 1st Place in the Occupant Action category; in the Energy Advancement category, the Main Library took 3rd Place while the Grainger Engineering Library took 4th Place. These libraries will work with the Utilities & Energy Services Division within Facilities & Services at the University to implement upgrades to their appearance or functionality.

    The Energy Advancement category is for campus buildings whose energy reduction is the result of central funding from a significant energy conservation project. The Occupant Action category is for those buildings which have not benefited from such projects in the last fiscal year.

    To learn more about the ECIP, please visit go.illinois.edu/ecip.

    (from Library News at http://www.library.illinois.edu/news/ECIP2013.html)

  5. FY13 ECIP Award Winners Announced

    Energy Advancement Category

    1. Atmospheric Sciences Building            53.3%
    2. Spurlock Museum                                      44.5%
    3. Main Library                                                 43.1%
    4. Grainger Engineering Libra                    41.3%

    Occupant Action Category

    1. Undergraduate Library                            35.2%
    2. Law Building                                                  35.1%
    3. Christopher Hall                                          30.6%
    4. Henry Administration Building             28.4%
  6. Explanation of calculations

    We take total energy usage by building (electricity, Steam, Nat Gas and Chilled Water) convert all of those to one common unit, MMBTU (million British Thermal Units) and after adjusting for the weather differences between years, compare each building's annual usage with the year before.  We then convert the change into a percentage and then rank all eligible buildings by percentage saved.  The top four in each category win first through fourth.     Having won in FY13 does not disqualify you from winning in the future.  The goal is to encourage individual contributions to saving energy.   Mike Marquissee

  7. Letter to SSC

    Associated Project(s): 

    Dear Student Sustainability Committee,   As the new Transportation Demand Management (TDM) Coordinator in Facilities & Services, I am writing to introduce myself to the Committee and provide you with an update on the Bicycle Parking Upgrade project, which I have taken over as part of my new role. We have been transitioning the role of TDM Coordinator from Morgan Johnston to me since June, and she has been working to bring me up to speed on the large number of transportation infrastructure projects happening across campus, including bicycle parking upgrades. While we have made progress toward the completion of this project, we are requesting an additional extension to finish the work.   In addition to the delay from the staff transition period, we have taken some time to evaluate our various options to ensure that the upgraded racks provide the long-term solution that was intended by SSC’s funding award. One of the primary challenges with this project is that many of the bike parking locations selected for this project are in need of concrete or pavement upgrades; however, funding is not in the TDM budget to pay for these upgrades. One location, the Art & Design Building, has been completed so far with financial support from the Art & Design Department to re-lay new concrete at that site.  For the majority of the other locations, however, there is no funding available from the departments to repair or replace the cracked and degraded concrete.  This has made us hesitant to install new bicycle racks onto pavement that will need to be replaced in a matter of years.   As a more permanent solution, we are looking at a few alternative configurations of bike racks.  All those we are considering are moveable and can easily be relocated – whether to upgrade the pavement beneath them, to accommodate a construction project, or to permanently relocate a building’s bicycle parking to a more optimal location over time.  We are looking at rack units which can be purchased and also a rack where 5 U-loops would be installed on rails, rather than directly cemented into the ground. While the initial cost of constructing the loops on rails is higher, it is a much more sustainable approach to bike parking given the challenges at these locations, and it is more affordable than replacing the pavement at each location. A rack unit can also be placed on permeable pavement, or even in a gravel/grass location temporarily as needed.  The lifespan of a bike rack unit is significantly higher, and offers much greater flexibility for placement and upkeep of the racks and surrounding landscape. Due to a potential increased initial cost of the racks on rails configuration (if this is what is determined to be the approved configuration), I may be requesting approval to change the scope of the project.  A change of scope is necessary because fewer total bike parking loops may be possible when on racks. Once we have identified a configuration that meets the best need of the users, we will be ready to proceed with the project and do not expect any further delays, but getting to this point has taken longer than originally expected. We anticipate being finished with the installation of these racks before the beginning of the fall semester 2014. Please let me know whether this change in the scope of the project is acceptable to the SSC.  I will keep you informed on the status and look forward to working with you on the best solution for our campus. Facilities & Services is incredibly grateful to the SSC for your ongoing support for sustainable transportation initiatives on campus, and we look forward to continuing to work with you to make the campus more bike-able, walkable, and transit-friendly. If you would like more detail, please contact me.   Thank you,   Stacey DeLorenzo Design Review Coordinator Transportation Demand Management Coordinator University of Illinois Urbana-Champaign Facilities Services Office: 217-300-1750 Cell: 217-722-4992        

  8. bike parking review meeting

    Associated Project(s): 

    Stacey DeLorenzo, Amelia Neptune, Morgan Johnston, and Noel Grove met to review the bike parking estimates for this project.  There are a few locations where the pavement is in terrible condition, so we discussed options for handling those locations.  The racks could be installed on rails, or the pavement could be replaced.  There were also a few locations where there are conflicting major projects occuring in the near future.  Stacey will talk to the project managers for those sites to work through the solutions for the bike parking installation.

    Additionally, this project includes the installation of one bike fix-it station at Allen Hall.  Amelia began this work and Stacey will take it over now.  Stacey and Amelia will meet with Sean Sullivan in the SSC to provide him with an update.  Noel Grove will provide cost break downs with the pavement work separate from the bike rack installation work.  He will also contact the Iron Workers to discuss options for racks on rails built in-house.

  9. 2009 Classroom Occupancy Sensor Installation

    Associated Project(s): 

    In 2009, the Student Sustainability Committee awarded $50,000 to Facilities & Services for installation of occupancy sensors to control lights in ten campus buildings: Animal Sciences Laboratory, Architecture Building, Bevier Hall, Chemistry Annex, Huff Hall, Materials Science and Engineering Building, Mumford Hall, Music Building, Noyes Laboratory and Transportation Building. The funds were used to install a total of 230 occupancy sensors in 223 rooms in these ten buildings.

  10. 2008 Classroom Occupancy Sensor Installation

    Associated Project(s): 

    In 2008, the Student Sustainability Committee awarded $20,000 to Facilities & Services for installation of occupancy sensors to control lights in three campus buildings: Loomis Laboratory, Foreign Languages Building, and Armory. Later, the budget was increased to $50,000 and the scope expanded to include seven additional buildings: Davenport Hall, Everitt Electrical Building, English Building, Henry Administration Building, Psychology Laboratory, Mechanical Engineering Building, and Wohlers Hall. The funds were used to install a total of 332 occupancy sensors in 272 rooms in these ten buildings.

  11. Bike fix-it station update

    Associated Project(s): 

    From: Neptune, Amelia
    Sent: Tuesday, May 14, 2013 12:27 PM
    To: Ortiz, Benita Vonne
    Cc: Johnston, Morgan B
    Subject: Bicycle Repair Station outside of Allen Hall

    Hi Vonne,

    As you may recall, earlier in the school year we had discussed that there is some funding for a new bicycle repair station near Allen Hall/CRCE. The original location we proposed near Gregory Drive in front of CRCE was rejected by the Architecture Review Committee, and they have proposed a better location near the bike parking area in front of Allen Hall. I would like to get your OK on this location before we move forward.

    The first attached PDF shows the location proposed by the Architecture Review Committee. As you’ll see in the photos on pages 2 and 3, it is on existing pavement, close to the bike parking, but not blocking a walkway, which I think is ideal.

    The second PDF shows the specifications of the newly designed repair stations so you know what it would look like. The new design is much smaller and (in my opinion) more attractive than the existing repair stations we have elsewhere on campus. The blue color of the existing stations is no longer available, so our plan is to match the color of the adjacent bike parking, in this case black.

    Please let me know if Housing has any objections to this location, or would like to meet there in person to discuss it further. Once I have your approval, we’ll move forward placing the order and installing this summer.  Please let me know if there are any questions.

    Thank you,

    Amelia  

    =========================================

    Amelia Neptune

    Campus Bicycle Coordinator

    University of Illinois at Urbana-Champaign

    1501 S. Oak, Champaign, IL 61820

    aneptune@illinois.edu

    217-300-1316

  12. Art and Design bike racks funded

    Associated Project(s): 

    To Davie Akins, Please proceed with the bike parking upgrade on the west side of Art and Design, per the previous discussions we have had.  The SSC funding will contribute $11,849.50 from CFOP: 1-629514-814006-xxxxxx-191200-814BIK. - from Morgan Johnston

  13. Racquetball Court Energy Reduction Project

    Associated Project(s): 

    Twelve racquetball and three squash courts at the Activities and Recreation Center (ARC) were retrofit with 193 fluorescent and 96 mercury vapor light fixtures. The project was funded by the Student Sustainability Committee through an interest-free loan of $75,000.

    Once the lighting retrofits were completed, occupancy sensors were installed in all 15 courts.

    The overall cost of the project ended up at $61,203.69 -- $13,796.31 less than the original quote. Campus Recreation requested that the remaining balance stay with the division and be used to further fund energy reduction projects within their facilities.

    The total average reduction in power consumption is 129,226 kWh. This is a 75.7 percent decrease in consumption, which translates to an annual savings of $9,020. The simple payback for this project is 6.78 years.

  14. RLF Occupancy Sensors FY12

    Associated Project(s): 

    Ten buildings on the University of Illinois at Urbana-Champaign campus were selected to receive RLF funding for occupancy sensors in FY12. In order from top priority to lowest priority, the buildings that received funding are Gregory Hall, the Foreign Languages Building, the Agriculture Engineering Sciences Building, Newmark Laboratory, the Rehabilitation Education Center, the Education Building, the Law Building, the Water Survey Buildings, Noyes Laboratory, and Freer Hall. The University will now proceed to implementation of occupancy sensors in all of the above buildings.

    Gregory Hall, the Foreign Languages Building, Newmark Laboratory, the Rehabilitation Education Center, Noyes Laboratory, and Freer Hall have also been selected to receive HVAC occupancy sensors.

  15. Cost estimates requested for first 5 locations

    Associated Project(s): 

    Transportation staff submitted work order requests to have cost estimates for time and materials for the first five locations to be upgraded from donut hole bike parking to U-rack bike parking.  The remaining nine locations need to have CAD drawings produced and apprroved before costs can be estimated.  

  16. Campus Bike Parking Overhaul Phase 1_Funding Award and Acceptance