- This form will search for any of the words you enter in a field, not the exact phrase you enter. If you would like to search for an exact phrase, put double quotes (") around the phrase. For example, if you search for Bike Path you will get results containing either the word Bike OR the word Path, but if you search for "Bike Path" you will get results containing the exact phrase Bike Path.
Pages
Student solar efforts renewing for fall 2016
Associated Project(s):Niharika Kishore, masters in Urban Planning (MUP) student, and Corey Weil, sophomore in Electrical and Computer Engineering, are working with Morgan Johnston on the iSEE objective for on-campus solar. Niharika will continue her efforts for promoting rooftop solar to meet the iCAP objective for 12,500 MWh/year of on-campus solar energy generation as part of a MUP capstone project this year. Corey will volunteer in various efforts to support the development of solar solutions for campus, from the Net Zero Energy ECE efforts to advocating for solar energy funding.
Possibility for rooftop solar on Mechanical Engineering Building
Associated Project(s):After the August 5th presentation by Niharika Kishore to College of Engineering facilities contact Greg Larson, Greg spoke with Mechanical Engineering facilities contact Damon McFall about roofotp solar for the Mechanical Engineering Building (MEB). Morgan Johnston explained that MEB had been left off the list Niharika worked on because of the upcoming Capital Programs project in that facility. Greg indicated that they are interested in pursuing rooftop solar for MEB. Potentially the design could be included in the Capital Project design effort, and the installation would need to be funded separately. This roof could hold approximately 130 kW array.
Niharika Kishore sending email to potential facilities
Associated Project(s):Niharika Kishore will send an email to potential facilities for adding rooftop solar, in support of the 2015 iCAP objective. The draft email is attached and the list of potential facilities is as follows:
Building Estimated Yearly Output (kWh/yr) Physical Plant Services Building 791,522 Activities and Recreation Center 725,562 Law Building 395,761 Ikenberry Dining Hall 382,569 Abbott Power Plant 263,841 Digital Computer Library 263,841 Plant Sciences Laboratory 164,900 Timothy J. Nugent Hall 164,900 Institute of Genomic Biology 158,304 Richard T. Ubben Basketball Complex 151,708 Oak Street Library 151,708 Bousfield Hall 145,112 Garage and Carpool 125,324 Attached Files:Niharika Kishore is working on developing a rooftop solar RFP for design
Associated Project(s):Today, Morgan Johnston met with Niharika Kishore to discuss the rooftop solar iCAP objective. Niharika is going to review the work already done, in the iSEE solar box folder, and draft a proposal for getting the engineering design work done for a set of building. She will be working towards meeting the FY20 on campus generation goal of 12,500 MWh/year, and possibly additional installations for FY25.
Art and Design Building solar design
Associated Project(s):A group of seniors completed the attached report for the Art and Design Building, for rooftop solar. They recommended a flexible solar material, with micro-inverters. The Art and Design department is interested in working with a student in the fall to seek funding for the rooftop solar from the Student Sustainability Committee.
Attached Files:Rooftop Solar Student Project
Associated Project(s):Brendan McDonnell is working with F&S to identify the best buildings on campus for rooftop solar. Brendan is a MechSE graduate student working toward an MS in ME with a certificate in Energy Systems Engineering, and this is his summer capstone project. Professor Elif Ertekin is his advisor for the project, and Morgan Johnston is his supervisor at F&S. The files Brendan is collecting are stored in the iSEE Solar box folder at https://uofi.app.box.com/files/0/f/2802975201/iSEE_-_Solar_Working_Group....