The geothermal heat pump is now installed at the Gable Home, at the Energy Farm.
You are here
Geothermal at Gable Home (Completed)
Recent Project Updates
-
1/15/2021
-
1/7/2021
The supplier of the heat pump, Connor Company, has received it from the factory and will deliver it to campus on Friday, January 8, 2020. Lanz Inc. will then work to install the system.
Project Family
-
Geothermal on Campus
- Geothermal Battery at Energy Farm
- Geothermal Monitoring Well on Bardeen Quad
- Geothermal Test Well at Energy Farm
- Geothermal at Allerton Park
- Geothermal at Gable Home
- Geothermal at President's House
- Geothermal at WPP
- Geothermal at the Campus Instructional Facility (CIF)
- Geothermal at the Energy Farm
- Geothermal at the Fruit Farm Admin Building
- Hydro-Systems Lab Energy Foundations
- ISTC Geothermal Loop
- RIPE Greenhouse with Geothermal at Research Park
Description
Project Team
-
Primary Contact:
Tim MiesTeam Members:
- Mark Taylor
- Wes Ifft, Lanz Inc.
- Andy Stumpf
- Jeff Hurst, Connor Company
- Tim Stark
- Maryam Ghadiri
- Abedalqader Idries
- Yu-Feng Lin
- Yun Yi
Dates
-
Started November 9, 2020Started by Tim MiesCompleted January 14, 2022Completed by Lanz Inc.
Themes
-
Primary Theme:
Other Themes:
Project Location(s)
This map is interactive! Click (or touch) and drag to pan; scroll (or pinch) to zoom.