- This form will search for any of the words you enter in a field, not the exact phrase you enter. If you would like to search for an exact phrase, put double quotes (") around the phrase. For example, if you search for Bike Path you will get results containing either the word Bike OR the word Path, but if you search for "Bike Path" you will get results containing the exact phrase Bike Path.
- Associated Project(s):Attached Files:
Feasibility Study approved by SSC and CCRC
Associated Project(s):SSC confirmed funding of $15,000 for composting feasibility study 5/9/11. Study approved 5/12/11 by Chancellor’s Capital Review Committee (CCRC) with Fall 2011 completion target. Proposal requested from Retainer A/E Foth Engineering, which was also the A/E on the previous composting project before it was cancelled.
Funding request submitted to SSC for FY12
Associated Project(s):In Fall 2010, The Bike Project requested $7,500 in funding from SSC for 50% of a half-time shop manager. The SSC approved this request.
Composting project discussions continue
Associated Project(s):Meeting with SSC and F&S to confirm details of composting feasibility study scope. Kevin, Matt, and Morgan worked on completing the project request form. Kevin, Carl, and Tracy worked on detailing the transportation charges budget. Kevin also met with Dawn Aubrey about the food waste supply.
Quick payback projects
Associated Project(s):At some point in the past, perhaps FY 09, Terry Ruprecht and the Provost’s office worked out an agreement to provide a funding source for “quick payback projects.” This meant that the payback was expected to be quick, typically in the 1-3 year range. This was a onetime funding source. A variety of projects (10-15) have been brought forward and funded at a value of approximately 1 million dollars. These projects have included lighting retrofits, fume hood removals, chiller control upgrades, adding variable frequency drives (VFDs) to HVAC equipment, temperature control upgrades, and hot water control valve replacements.
UIUC Campus Bike Plan Presentation 2011
Associated Project(s):Presentation on bike counts, along with proposed bike facilities, costs, and updates.
Attached Files:Matt Edmonson assigned as Capital Planner for study
Associated Project(s):Planning Division brought into discussion, so the project can get implemented. Matt Edmonson assigned as capital planner for the Food Waste Composting Feasibility Study.
Energy presentation at CSL
Associated Project(s):Energy details on display at Coordinated Science Lab.
James Hoffer, student intern, created building list file
Associated Project(s):James provided the attached list of buildings audited by student teams in FY11. Unfortunately, these audits were rushed and incomplete. There were many follow up discussions about paying the student teams as originally intended, and in the end the teams were not paid. This decision was coordinated by Mckenzie Beverage, the SSC Program Advisor, during FY12 and FY13.
Attached Files:Conservation Plan
Associated Project(s):In March 2011, John Dempsey, then Executive Director of Facilities and Services, signed the conservation plan for the State Threatened Franklin's ground squirrel at the South Farms location (for wind turbine installation).
Attached Files:Site location (modified)
Associated Project(s):A modified version of the site location for the wind turbine was proposed.
Attached Files:Wind turbine: History and status
Associated Project(s):In March 2011, the university provided the history and the current status update regarding the wind turbine project at the South Farms location.
Attached Files:Energy presentation at Altgeld
Associated Project(s):Energy details on display at Altgeld.
Kevin Wolz discusses composting with various F&S representatives
Associated Project(s):Series of emails from Kevin Wolz with various F&S staff. Tracy was involved in discussions with Kevin about the waste container and truck options. Ryan Welch was involved in discussions with Kevin about the possibilities of using the Grounds landscape compost site and equipment.
Energy presentation at IGB
Associated Project(s):Energy details on display at the Institute of Genomic Biology.
Site Selection Committee formed
Associated Project(s):A Site Selection committee was formed to evaluate potential locations for the Solar Farm.
Letter from the Mayor of Urbana
Associated Project(s):In February 2011, the Mayor of Urbana wrote a letter to Morgan Johnston regarding wind turbine project on South Farms location. She asked the university to conduct research on the issues mentioned in the letter before the start of the wind turbine project.
Attached Files:Public comments #2
Associated Project(s):Following the meeting on January 31, 2011, the university received comment cards from the public.
Attached Files:Public meeting #2
Associated Project(s):In January 2011, the university held a second meeting with the public. Morgan Johnston presented a seminar on South Farm Wind Turbine Project, and received comments and questions from the public.
Attached Files:Kevin Wolz meets with F&S representatives
Associated Project(s):Kevin Wolz met with Carl Wegel & Tracy Osby to discuss compost pick-up & transportation