  1. Imported Swine Research Laboratory

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 323 T-12 fixtures in the Imported Swine Research Laboratory were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 50,918 hours. The simple payback for this project is 3.56 years.

  2. Labor & Employment Relations

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 179 T-12 fixtures in the Admin Tech Info Building were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 29,829 hours. The simple payback for this project is 3.48 years.

  3. Atmospheric Sciences Building

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 221 T-12 fixtures in the Atmospheric Sciences Building were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 34,365 hours. The simple payback for this project is 3.83 years.

  4. Meat Sciences Laboratory

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 367 T-12 fixtures in the Meat Sciences Laboratory were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 66,103 hours. The simple payback for this project is 2.91 years.

  5. Horticulture Field Laboratory

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 256 T-12 fixtures in the Horticulture Field Lab were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 40,187 hours. The simple payback for this project is 3.58 years.

  6. Admin Info Tech Building

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 687 T-12 fixtures in the Admin Tech Info Building were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 112,316 hours. The simple payback for this project is 3.42 years.

  7. Art and Design Building

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 1,250 T-12 fixtures in the Art and Design Building were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 202,172 hours. The simple payback for this project is 3.47 years.

  8. Cost estimates requested for first 5 locations

    Associated Project(s): 

    Transportation staff submitted work order requests to have cost estimates for time and materials for the first five locations to be upgraded from donut hole bike parking to U-rack bike parking.  The remaining nine locations need to have CAD drawings produced and apprroved before costs can be estimated.  

  9. Art East Annex- Studio 1

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 703 T-12 fixtures in the Art East Annex (Studio 1) were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 112,892 hours. The simple payback for this project is 3.47 years.

  10. Ceramics Building

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 531 T-12 fixtures in the Admin Tech Info Building were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 96,045 hours. The simple payback for this project is 2.96 years.

  11. Geological Survey Laboratory

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 225 T-12 fixtures in the Geological Survey Laboratory were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 44,856 hours. The simple payback for this project is 2.59 years.

  12. Garage/ Car Pool

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 445 T-12 fixtures in the Admin Tech Info Building were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 70,200 hours. The simple payback for this project is 2.79 years.

  13. Mailing Center

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 218 T-12 fixtures in the Mailing Center were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 33,971 hours. The simple payback for this project is 2.4 years.

  14. Children's Research Center

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 725 T-12 fixtures in the Children's Research Center were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 115,133 hours. The simple payback for this project is 3.53 years.

  15. Police Training Institute

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 604 T-12 fixtures in the Police Training Institute were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 90,436 hours. The simple payback for this project is 3.73 years.

  16. Memorial Stadium

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 821T-12 fixtures in Memorial Stadium were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 173,934 hours. The simple payback for this project is 2.41 years.

  17. Central Receiving Building

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 573 T-12 fixtures in the Admin Tech Info Building were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 107,680 hours. The simple payback for this project is 1.8 years.

  18. Campus Bike Parking Overhaul Phase 1_Funding Award and Acceptance