  1. Gregory Hall

    As part of the ICECF 2009 Lighting Retrofit, 426 T-12 fixtures in Gregory Hall were replaced with the more energy-effiecient T-8 fixtures. This switch will incur an Annual kWh Savings of 68,862 hours. The simple payback for this project is -4.1 years. There are 777 T-12 fixtures in Gregory Hall remaining to be switched.

  2. David Kinley Hall

    As part of the ICECF 2009 Lighting Retrofit, 858 T-12 fixtures in the David Kinley Hall were replaced with the more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 84,223 hours. The simple payback for this project is -5.36 years. There are 54 fixtures that remain to be done in David Kinley Hall.

  3. Morrill Hall

    As part of the ICECF 2009 Lighting Retrofit, 195 T-12 fixtures in Morrill Hall were replaced with the more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 25,781 hours. The simple payback for this project is -4.45 years. There are 2,594 T-12 fixtures in Morrill Hall that remain to be switched.

  4. Lincoln Hall

    As part of the ICECF 2009 Lighting Retrofit, 1,728 T-12 fixtures in Lincoln Hall were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 99,886 hours. The simple payback for this project is -8.03 years.

  5. Vet Med Chiller Plant

    As part of the ICECF 2009 Lighting Retrofit, 115 T-12 fixtures in the Vet Med Chiller Plant were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 28,742 hours. The simple payback for this project is -0.2 years.

  6. Quick payback projects

    Associated Project(s): 

    At some point in the past, perhaps FY 09, Terry Ruprecht and the Provost’s office worked out an agreement to provide a funding source for “quick payback projects.” This meant that the payback was expected to be quick, typically in the 1-3 year range. This was a onetime funding source.  A variety of projects (10-15) have been brought forward and funded at a value of approximately 1 million dollars. These projects have included lighting retrofits, fume hood removals, chiller control upgrades, adding variable frequency drives (VFDs) to HVAC equipment,  temperature control  upgrades, and hot water control valve replacements. 

  7. Illinois State Water Survey

    As part of the ICECF 2009 Lighting Retrofit, 1,154 T-12 fixtures in nine buildings belonging to the Illinois State Water Survey were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 181,017 hours. The simple payback for this project is -2.45 years.