Projects Updates for place: Temple Hoyne Buell Hall

  1. Planning meeting to implement project

    Associated Project(s): 

    Teresa Tousignant, Paul Foote, Morgan Johnston, and Eva Sweeney met to discuss the implementation steps for this project.  Eva will obtain the CFOP from Gaines or Mckenzie.  Morgan will submit an engineering work order for the daylighting and occ sensors.  Teresa will set up a kickoff meeting for about three weeks from now.  Eva will initiate engineering design.  Later, a work order for inhouse implementation of the daylighting will come from the SSC account and a work order for occ sensors will come from the RLF account.

    overview of discussion:

    Gaines Hall received the award letter, and Teresa is going to oversee the implementation as the "customer."  Teresa will get the CFOP, then Morgan will submit the work order for Engineering Design.  Eva and Teresa discussed holding a kickoff meeting.  It will include Gaines, David Chasko, Teresa, Eva, Robert, the facility manager, Paul, and any anyone else needed.

    Eva needs a copy of all the documents, and Teresa will set up a meeting for about three weeks from now.

    Perhaps the SSC will want to include a representative.   Eva mentioned that in some cases the SSC rep can add tangential conversations, and Teresa said that she believes the rep would most likely be an observer, getting trained.

    One work order now for engineering.  Later, do work orders for occ sensors and daylighting implementation later.  The budget was reviewed.  It included Eva's rough estimates for the cost of the project, engineering costs, and contingencies for unknowns.   The potential for connecting the HVAC occ sensors as well needs to be explored, so Eva will touch base with Karl Helmink.  The RLF funding could cover the HVAC connection, if that is the best use of the RLF funds.

    The proposal includes "publicity plaques" engraved and mounted on the wall in studio spaces near the light switches.  These were signed off on by Gaines with the acceptance of the funding.  Teresa can get the school or a class to do a design competition for the plaques.  This could be anything that fits the design standards for the campus, and has Dr. Chasko's approval.  The sign shop can most likely produce and install these signs, based on a second phase for the construction work order with the daylighting.

    Eva anticipates a single review submittal for this project.  We would like to get the design done during the summer and the construction done during the fall.  The funding is only available until next summer.  A lot of this work can probably be done while school is in session, as long as they work around the classroom and event schedules. 

     

     

  2. Teresa Tousignant requests meeting

    Associated Project(s): 

    Here are the proposal and supporting documents for the TBH lighting project.   The account number has been set up so the project now has access to the funds.   I’d like to get this project into the lighting design and electrical engineering pipeline as soon as we can.  I’d also like to call a project kickoff meeting so we can sit down with Prof. Hall, Director Chasco, and Eva Sweeney and make sure everyone is on the same page.

    Teresa Tousignant
    Student Sustainability Committee

    Energy Working Group Co-Chair

  3. Animal Sciences A/C Center

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 50 T-12 fixtures in the Animal Sciences A/C Center were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 7,884  hours. The simple payback for this project is 3.56 years.

  4. University Press

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 488 T-12 fixtures in the University Press Building were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 76,948 hours. The simple payback for this project is 3.64 years.

  5. Transportation Building

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 547 T-12 fixtures in the Transportation Building were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 86,251 hours. The simple payback for this project is 3.56 years.

  6. Temple Hoyne Buell Hall

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 471 T-12 fixtures in Temple Hoyne Buell Hall were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 74,267 hours. The simple payback for this project is 3.56 years.

  7. Speech and Hearing Clinic

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 47- T-12 fixtures in the Speech and Hearing Clinic were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 74,110 hours. The simple payback for this project is 3.08 years.

  8. Shelford Vivarium Greenhouse

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 335 T-12 fixtures in the Shelford Vivarium Greenhouse were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 52,823 hours. The simple payback for this project is 3.53 years.

  9. Personnel Services Building

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 433 T-12 fixtures in the Personnel Services Building were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 68,275 hours. The simple payback for this project is 3.2 years.

  10. Nuclear Physics Lab

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 415 T-12 fixtures in the Nuclear Physics Lab were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 65,437 hours. The simple payback for this project is 3.56 years.

  11. Natural Resources Studies Annex

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 1,200 T-12 fixtures in the Natural Resources Studies Annex were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 189,216 hours. The simple payback for this project is 3.56 years.

  12. Levis Faculty Center

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 189 T-12 fixtures in the Levis Faculty Center were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 29,802 hours. The simple payback for this project is 3.56 years.

  13. International Studies Building

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 571 T-12 fixtures in the International Studies Building were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 90,035 hours. The simple payback for this project is 3.56 years.

  14. Illini Hall

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 610 T-12 fixtures in Illini Hall were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 96,185 hours. The simple payback for this project is 3.56 years.

  15. Huff Hall

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 426 T-12 fixtures in Huff Hall were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 67,172 hours. The simple payback for this project is 3.56 years.

  16. Harker Hall

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 485 T-12 fixtures in Harker Hall were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 76,475 hours. The simple payback for this project is 3.56 years.

  17. Harding Band Building

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 304 T-12 fixtures in the Harding Band Building were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 47,935 hours. The simple payback for this project is 3.81 years.

  18. Colonel Wolfe School

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 298 T-12 fixtures in the Colonel Wolfe School were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 46,989 hours. The simple payback for this project is 3.55 years.

  19. Ceramics Kiln House

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 687 T-12 fixtures in the Admin Tech Info Building were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 112,316 hours. The simple payback for this project is 3.42 years.