  • This form will search for any of the words you enter in a field, not the exact phrase you enter. If you would like to search for an exact phrase, put double quotes (") around the phrase. For example, if you search for Bike Path you will get results containing either the word Bike OR the word Path, but if you search for "Bike Path" you will get results containing the exact phrase Bike Path.
  1. Provost Office approves funding for LED Exit Signs

    The Office of the Provost approved $75,000 in one-time funding for the next step in the LED Exit Sign retrofit project.  The funding of $75,000 is for LED Exit Sign lighting replacement, additions, and new building surveys.  Material and labor of $70,000 would be used to replace 343 fixtures in 20 buildings at an average rate of $204/fixture.  An additional $5,000 is proposed to survey 50 campus buildings for exit light counts.  That will provide the input necessary for the next phase, once this phase is completed.

  2. Meeting with F&S officials

    Associated Project(s): 

    Met with the university Facilities and Services officials and LED staff on Wednesday, September 21, 2016, to discuss the progress of LED Campus projects so far. The main focus of the meeting was Exit signs in the buildings. Meeting was hosted by Mogan Johnston, and attended by Ken Buenting, Brian Finet, Steven Bainbridge, and Patty Douglas.

  3. Campus approves an additional $100K for LED Exit Signs

    Associated Project(s): 

    After the successful completion of the recent LED Exit Sign upgrades, the F&S Building Maintenance division has received approval for another round of LED Exit Sign upgrades.  Ken Buenting, Sharon Ball, Ryan Wild, and Morgan Johnston met to discuss the prioritization process for identifying the next buildings to address.  Buildings will be ranked according to student/transient visitor contact hours (if this information can be obtained), results of campus code fire safety reports, and coordination with other projects or funding.

  4. LED Exit Sign projects completed

    Associated Project(s): 

    In support of the Chancellor's commitment to making the University of Illinois an LED Campus, 531 LED way-finding signs have been installed in eight campus buildings: Grainger Library, Animal Science, Roger Adams Lab, Engineering Science Building, Turner Hall, Main Library, Education Building, and the Chem. Life Sciences Lab.

  5. update on project progress

    Associated Project(s): 

    Ken Buenting, Sharon Ball, Eva Sweeney, Morgan Johnston, and Ryan Wild met to review progress on the LED Exit Sign work.  Ken reported great progress with four buildings complete and one in progress: Grainger, RAL, Animal Sciences Lab, and the Engineering Sciences Building.  They are in Turner Hall now.  Just over $24K has been spent so far through the contractor.  They will move on to the Main Library and the Education Building next.

    The current implementation process is as follows:

  6. Campus funding allocated for LED exit signs

    Associated Project(s): 

    The LED Campus commitment includes having all the interior wayfinding signs converted to LED by 2025.  This is primarily LED Exit Signs.   We had hoped to use the Revolving Loan Fund to implement another phase of the LED Exit Sign project.  However, that funding is only applicable if there is a reasonable payback through utility savings.  LED Exit Signs have a good payback, but not through Utilities.  The savings come from reduced maintenance, which also provides a reasonable payback.  

  7. Code Complance and Fire Safety Funding Meeting

    Associated Project(s): 

    Ryan Wild, in Code Compliance and Fire Safety, met with Morgan Johnston to review the funding parameters for this project, and identify next steps.  Morgan asked Teresa Tousignant and Nishant Makhijani, from the Student Sustainability Committee, about potential student volunteers to help locate the existing incandescent exit signs.  Ryan will work on the building surveys for the smaller buildings, and we will hold KCPA, Main Library, Beckman, Roger Adams Lab, and Chem Life Sciences Lab for potential student assistance.

  8. LED Exit Signs Phase 2

    Associated Project(s): 

    Phase 2 of the LED Exit Sign project to replace incandescent exit signage with LED fixtures started on June 30, 2008. This phase of the project will replace fixtures in the Armory, Foellinger Auditorium, Harding Band Building, Illini Hall, the Optical Physics Building, the Illinois Program for Research & Humanities, the Architecture Building, Noble Hall, the Art & Design Building, the Music Building, Flagg Hall, and University High School.

  9. LED Exit Signs Phase 1

    Associated Project(s): 

    Phase 1 of the LED Exit Sign project will replace incandescent exit signage with LED fixtures in facilities used for the Engineering Open House. The building involved are the Material Sciences and Engineering Building,  the Mechanical Engineering Building, the Transportation Building, Altgeld Hall, Morrill Hall, Burrill Hall, Noyes Laboratory, and the Undergraduate Library.