Green Roof on Literatures, Cultures and Linguistics Building (formerly called Foreign Language Building) (Completed)

Recent Project Updates

  • 10/5/2025
    Morgan White reviewed the F&S and SSC records, and completed this final project report for the FLB greenroof.
  • 10/11/2023
    Note - The Foreign Language Building (FLB) has been renamed to Literatures, Cultures and Linguistics Building (LCLB).Green roof trees are scheduled to be installed in the spring of 2024. 

Description

The LCLB basement roof is a plaza at ground level. It was built to accommodate greenery on the roof and did so from 2012 to 2014. The planters were filled with porous rock for ease of maintenance. The area still helps with rainwater runoff, however, plants could be added to the planters again to provide more benefits around the ground level of the building. Plants were added on 6/18/24 thanks to funding from the Student Sustainability Committee

No description has been provided yet.

Project Team

  • Primary Contact:

    Erin Joyce Miller

    Project Leader:

    Joey Kreiling

    Team Members:

    • Brent Lewis

Dates

  • Completed June 18, 2024
    Completed by F&S Grounds