  1. Code Complance and Fire Safety Funding Meeting

    Associated Project(s): 

    Ryan Wild, in Code Compliance and Fire Safety, met with Morgan Johnston to review the funding parameters for this project, and identify next steps.  Morgan asked Teresa Tousignant and Nishant Makhijani, from the Student Sustainability Committee, about potential student volunteers to help locate the existing incandescent exit signs.  Ryan will work on the building surveys for the smaller buildings, and we will hold KCPA, Main Library, Beckman, Roger Adams Lab, and Chem Life Sciences Lab for potential student assistance.

  2. LED Exit Signage FY12

    Associated Project(s): 

    Twenty University buildings have been allocated RLF funding for LED exit signage in FY12. The buildings, in order of priority, are Krannert Center for the Performing Arts, Foellinger Auditorium, the Beckman Institute, the Main Library, Davenport Hall, Temple Hoyne Buell Hall, the Education Building, the Law Building, the Animal Sciences Laboratory, Freer Hall, the Henry Administration Building, Grainger Engineering Library, the Agricultural Engineering Sciences Building, Turner Hall, the Illini Union Bookstore, the Stock Pavilion, the Engineering Sciences Building, Kenney Gymnasium, the Roger Adams Laboratory, and the Chemical and Life Science Laboratory.

    Implementation of LED exit signage has already started for four of these buildings; 75 percent of Krannert Center for the Performing Arts, 80 percent of Foellinger Auditorium, 10 percent of Freer Hall, and 30 of the Henry Administration Building has been completed. Implementation in the remainder of the buildings is now set to begin.

  3. Revolving Loan Fund approved for $250K for LED Exit Signs

    Associated Project(s): 

    The Revolving Loan Fund is approved to fund $250K in LED Exit Sign improvements.  Here is the description of the project, as reviewed by the RLF committee:

    ======================================

    This project will replace existing exit signs with efficient LED fixtures in approximately (14) campus buildings.  As a result, energy use will be decreased, life safety systems will operate more reliably, and maintenance needs will decrease dramatically.  This is a continuation of projects funded in FY07 and FY08. We are requesting funding in the amount of $250,000, although the work is very scalable and any funding amount can be successfully applied. 

    _________________________________________________________________

    CRITERIA:

    ¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯

    08. VISIBILITY - Very visible.  Building users notice when exit signs are burned out and it may make them feel uncomfortable or unsafe.  It also creates a negative impression of the pride we take in our facilities.

    09. PAYBACK PERIOD - When replacing incandescent, the payback from energy savings alone is about 6-7 years.  Replacement of fluorescent exit signs yields a payback of 8-10 years.  However, the old signs also require maintenance up to 3 times per year.  If one includes this expense, the overall payback improves to 1-2 years.

    10. REDUCTION OF COAL - By reducing overall campus energy use, this will contribute to Abbott Power Plant s ability to reduce the number of generation units in use.  An additional benefit is the reduction in GHG emissions from maintenance vehicles traveling to replace burned out lamps.

    11. FUND SIZE IMPACT - F&S is working with the Illinois DCEO and this project would qualify for about $7,000 in grant rebates.

    12. PROJECT COORDINATION - F&S has a record of success with these projects.  We have developed a project execution method that keeps overhead to a bare minimum, avoids expensive consultant fees, purchases material at bulk prices, and achieves maximum labor efficiency.  F&S Construction Services will execute the work, and F&S Engineering will document results for the DCEO grant.

    _________________________________________________________________

    ISSUES:

    ¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯

    01. REPLACEMENT OF FACILITY SYSTEMS - Existing exit signs are typically long past their expected life, and have many maintenance problems.  The new LED exit signs will have an expected useful life of at least 15-20 years.

    03. IMPACT ON PLANNED PROJECTS - Very little impact on capital projects.  We coordinate to ensure no overlap between buildings selected for exit sign replacement and planned major renovations.

    04. WHAT IF PROJECT IS NOT FUNDED? - If this project is not funded, our campus will continue to expend many maintenance hours keeping these lights operational, and waste electricity on inefficient technology that is over 20 years outdated.

    If this project is partially funded, we will install as many LED exit signs as possible with the funds allocated.

    06. WHAT OTHER DEPARTMENTS ARE AFFECTED BY THE PROJECT? - The buildings we propose are all across campus and used by virtually every college and department.  These units will benefit from improved safety and fewer maintenance disruptions.

    07. RISK FACTORS - No known risk factors.  In fact this work will reduce the risks associated with having nonfunctioning exit signs, and improve life safety for the campus community.  We have executed this type of work in 25 buildings so far without major problems.

  4. Gregory Hall

    Associated Project(s): 

    As part of the ICECF 2009 Lighting Retrofit, 426 T-12 fixtures in Gregory Hall were replaced with the more energy-effiecient T-8 fixtures. This switch will incur an Annual kWh Savings of 68,862 hours. The simple payback for this project is -4.1 years. There are 777 T-12 fixtures in Gregory Hall remaining to be switched.

  5. David Kinley Hall

    Associated Project(s): 

    As part of the ICECF 2009 Lighting Retrofit, 858 T-12 fixtures in the David Kinley Hall were replaced with the more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 84,223 hours. The simple payback for this project is -5.36 years. There are 54 fixtures that remain to be done in David Kinley Hall.

  6. Morrill Hall

    Associated Project(s): 

    As part of the ICECF 2009 Lighting Retrofit, 195 T-12 fixtures in Morrill Hall were replaced with the more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 25,781 hours. The simple payback for this project is -4.45 years. There are 2,594 T-12 fixtures in Morrill Hall that remain to be switched.

  7. Lincoln Hall

    Associated Project(s): 

    As part of the ICECF 2009 Lighting Retrofit, 1,728 T-12 fixtures in Lincoln Hall were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 99,886 hours. The simple payback for this project is -8.03 years.

  8. Vet Med Basic Sciences Building

    Associated Project(s): 

    As part of the ICECF 2009 Lighting Retrofit, 4,248 T-12 fixtures in the Vet Med Basic Sciences Building were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 796,429 hours. The simple payback for this project is 0.11 years.

  9. Vet Med Large Animal Clinic

    Associated Project(s): 

    As part of the ICECF 2009 Lighting Retrofit, 1,990 T-12 fixtures in the Vet Med Large Animal Clinic were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 320,117 hours. The simple payback for this project is 0.23 years.

  10. Vet Med Small Animal Clinic

    Associated Project(s): 

    As part of the ICECF 2009 Lighting Retrofit, 1,928 T-12 fixtures in the Vet Med Small Animal Clinic were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 67,145 hours. The simple payback for this project is 0.83 years.

  11. Vet Med Chiller Plant

    Associated Project(s): 

    As part of the ICECF 2009 Lighting Retrofit, 115 T-12 fixtures in the Vet Med Chiller Plant were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 28,742 hours. The simple payback for this project is -0.2 years.

  12. Abbott Power Plant (partial)

    Associated Project(s): 

    As part of the ICECF 2009 Lighting Retrofit, 177 T-12 fixtures in the Abbott Power Plant were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 27,909 hours. The simple payback for this project is 0.74 years.

  13. Digital Computer Laboratory

    Associated Project(s): 

    As part of the ICECF 2009 Lighting Retrofit, 2,793 T-12 fixtures in the Digital Computer Laboratory were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 422,793 hours. The simple payback for this project is 0.23 years.

  14. Coordinated Sciences Laboratory

    Associated Project(s): 

    As part of the ICECF 2009 Lighting Retrofit, 1,903 T-12 fixtures in the Coordinated Sciences Laboratory were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 295,922 hours. The simple payback for this project is 0.78 years.

  15. Illinois State Water Survey

    Associated Project(s): 

    As part of the ICECF 2009 Lighting Retrofit, 1,154 T-12 fixtures in nine buildings belonging to the Illinois State Water Survey were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 181,017 hours. The simple payback for this project is -2.45 years.