  1. Campus funding allocated for LED exit signs

    Associated Project(s): 

    The LED Campus commitment includes having all the interior wayfinding signs converted to LED by 2025.  This is primarily LED Exit Signs.   We had hoped to use the Revolving Loan Fund to implement another phase of the LED Exit Sign project.  However, that funding is only applicable if there is a reasonable payback through utility savings.  LED Exit Signs have a good payback, but not through Utilities.  The savings come from reduced maintenance, which also provides a reasonable payback.   Given the shortfall in maintenance funding and the Chancellor’s commitment to becoming an LED campus, Mike Andrechak agreed to provide $100,000 per year for two years toward LED Exit Signs.  This funding could be continued in future years, subject to funding approval.

  2. FY13 ECIP Award Winners Announced

    Energy Advancement Category

    1. Atmospheric Sciences Building            53.3%
    2. Spurlock Museum                                      44.5%
    3. Main Library                                                 43.1%
    4. Grainger Engineering Libra                    41.3%

    Occupant Action Category

    1. Undergraduate Library                            35.2%
    2. Law Building                                                  35.1%
    3. Christopher Hall                                          30.6%
    4. Henry Administration Building             28.4%
  3. Explanation of calculations

    We take total energy usage by building (electricity, Steam, Nat Gas and Chilled Water) convert all of those to one common unit, MMBTU (million British Thermal Units) and after adjusting for the weather differences between years, compare each building's annual usage with the year before.  We then convert the change into a percentage and then rank all eligible buildings by percentage saved.  The top four in each category win first through fourth.     Having won in FY13 does not disqualify you from winning in the future.  The goal is to encourage individual contributions to saving energy.   Mike Marquissee

  4. Report by Anna Hochlater

    Associated Project(s): 

    "The Burrill/ Morrill Hall corridor offers a unique opportunity to explore methods of sustainable design through conventional practices of rain garden design as well as hardscaping improvements, lighting installations and additional non-plant strategies.  A moderate strategy is advised. In this conversation moderate is understood to mean more than a creating only rain garden while leaving the existing vegetation, but less than a full redesign which would completely reshape the hardscaping.  A moderate strategy addresses the creation of the rain garden, all the landscape beds while leaving the mature canopy trees in place, and makes some alterations to the existing hardscape.  Perhaps the most difficult challenges of the corridor will be to unify the character of the corridor landscape beds and to design a solu-tion suitable for the harsh conditions of very little sun, significant wind, and heavy pedestrian use."

  5. Anna hired to complete this work

    Associated Project(s): 

    Eliana Brown provided the following update.

    • Anna Hochhalter was hired by F&S for the summer to complete a revised design of the Burrill/Morrill walkway rain garden / native plants improvements.  She reviewed the entire walkway from Mathews to Goodwin.  Her report is expected August 15th.
    • The space should be multifunctional, use native plants, accommodate the stormwater run off with green infrastructure.  It could include new lighting and artworks.
    • This project will use the existing SSC funding, as well as other funding sources.  The other funding sources may include Champaign County Soil and Water Conservation District, and/or F&S.
    • Eliana will take the project scope change request to SSC this fall, for approval.
    • Matt Edmonson has been involved with this project and will inform Eliana about any additional campus approvals that may be needed.
  6. Code Complance and Fire Safety Funding Meeting

    Associated Project(s): 

    Ryan Wild, in Code Compliance and Fire Safety, met with Morgan Johnston to review the funding parameters for this project, and identify next steps.  Morgan asked Teresa Tousignant and Nishant Makhijani, from the Student Sustainability Committee, about potential student volunteers to help locate the existing incandescent exit signs.  Ryan will work on the building surveys for the smaller buildings, and we will hold KCPA, Main Library, Beckman, Roger Adams Lab, and Chem Life Sciences Lab for potential student assistance.

  7. LED Exit Signage FY12

    Associated Project(s): 

    Twenty University buildings have been allocated RLF funding for LED exit signage in FY12. The buildings, in order of priority, are Krannert Center for the Performing Arts, Foellinger Auditorium, the Beckman Institute, the Main Library, Davenport Hall, Temple Hoyne Buell Hall, the Education Building, the Law Building, the Animal Sciences Laboratory, Freer Hall, the Henry Administration Building, Grainger Engineering Library, the Agricultural Engineering Sciences Building, Turner Hall, the Illini Union Bookstore, the Stock Pavilion, the Engineering Sciences Building, Kenney Gymnasium, the Roger Adams Laboratory, and the Chemical and Life Science Laboratory.

    Implementation of LED exit signage has already started for four of these buildings; 75 percent of Krannert Center for the Performing Arts, 80 percent of Foellinger Auditorium, 10 percent of Freer Hall, and 30 of the Henry Administration Building has been completed. Implementation in the remainder of the buildings is now set to begin.

  8. Revolving Loan Fund approved for $250K for LED Exit Signs

    Associated Project(s): 

    The Revolving Loan Fund is approved to fund $250K in LED Exit Sign improvements.  Here is the description of the project, as reviewed by the RLF committee:

    ======================================

    This project will replace existing exit signs with efficient LED fixtures in approximately (14) campus buildings.  As a result, energy use will be decreased, life safety systems will operate more reliably, and maintenance needs will decrease dramatically.  This is a continuation of projects funded in FY07 and FY08. We are requesting funding in the amount of $250,000, although the work is very scalable and any funding amount can be successfully applied. 

    _________________________________________________________________

    CRITERIA:

    ¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯

    08. VISIBILITY - Very visible.  Building users notice when exit signs are burned out and it may make them feel uncomfortable or unsafe.  It also creates a negative impression of the pride we take in our facilities.

    09. PAYBACK PERIOD - When replacing incandescent, the payback from energy savings alone is about 6-7 years.  Replacement of fluorescent exit signs yields a payback of 8-10 years.  However, the old signs also require maintenance up to 3 times per year.  If one includes this expense, the overall payback improves to 1-2 years.

    10. REDUCTION OF COAL - By reducing overall campus energy use, this will contribute to Abbott Power Plant s ability to reduce the number of generation units in use.  An additional benefit is the reduction in GHG emissions from maintenance vehicles traveling to replace burned out lamps.

    11. FUND SIZE IMPACT - F&S is working with the Illinois DCEO and this project would qualify for about $7,000 in grant rebates.

    12. PROJECT COORDINATION - F&S has a record of success with these projects.  We have developed a project execution method that keeps overhead to a bare minimum, avoids expensive consultant fees, purchases material at bulk prices, and achieves maximum labor efficiency.  F&S Construction Services will execute the work, and F&S Engineering will document results for the DCEO grant.

    _________________________________________________________________

    ISSUES:

    ¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯¯

    01. REPLACEMENT OF FACILITY SYSTEMS - Existing exit signs are typically long past their expected life, and have many maintenance problems.  The new LED exit signs will have an expected useful life of at least 15-20 years.

    03. IMPACT ON PLANNED PROJECTS - Very little impact on capital projects.  We coordinate to ensure no overlap between buildings selected for exit sign replacement and planned major renovations.

    04. WHAT IF PROJECT IS NOT FUNDED? - If this project is not funded, our campus will continue to expend many maintenance hours keeping these lights operational, and waste electricity on inefficient technology that is over 20 years outdated.

    If this project is partially funded, we will install as many LED exit signs as possible with the funds allocated.

    06. WHAT OTHER DEPARTMENTS ARE AFFECTED BY THE PROJECT? - The buildings we propose are all across campus and used by virtually every college and department.  These units will benefit from improved safety and fewer maintenance disruptions.

    07. RISK FACTORS - No known risk factors.  In fact this work will reduce the risks associated with having nonfunctioning exit signs, and improve life safety for the campus community.  We have executed this type of work in 25 buildings so far without major problems.

  9. Burrill and Morrill Rain Garden Spring 2012 Funding Award and Acceptance

  10. LED Exit Signs Phase 2

    Associated Project(s): 

    Phase 2 of the LED Exit Sign project to replace incandescent exit signage with LED fixtures started on June 30, 2008. This phase of the project will replace fixtures in the Armory, Foellinger Auditorium, Harding Band Building, Illini Hall, the Optical Physics Building, the Illinois Program for Research & Humanities, the Architecture Building, Noble Hall, the Art & Design Building, the Music Building, Flagg Hall, and University High School.

  11. LED Exit Signs Phase 1

    Associated Project(s): 

    Phase 1 of the LED Exit Sign project will replace incandescent exit signage with LED fixtures in facilities used for the Engineering Open House. The building involved are the Material Sciences and Engineering Building,  the Mechanical Engineering Building, the Transportation Building, Altgeld Hall, Morrill Hall, Burrill Hall, Noyes Laboratory, and the Undergraduate Library.