You are here
Project Updates search results
Search tips:
- This form will search for words in the title OR the description. If you would like to search for the same term(s) across both the title and description, enter the same search term(s) in both fields.
- This form will search for any of the words you enter in a field, not the exact phrase you enter. If you would like to search for an exact phrase, put double quotes (") around the phrase. For example, if you search for Bike Path you will get results containing either the word Bike OR the word Path, but if you search for "Bike Path" you will get results containing the exact phrase Bike Path.
- Associated Project(s):
Evans Hall
Associated Project(s):As part of the Housing Lighting Retrofit, 500 T-12 fixtures in Evans Residence Hall were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 78,840 hours. The simple payback for this project is 2.81 years.
Busey Hall
Associated Project(s):As part of the Housing Lighting Retrofit, 391 T-12 fixtures in Busey Residence Hall were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 61,653 hours. The simple payback for this project is 2.81 years.
Taft Hall
Associated Project(s):As part of the Housing Lighting Retrofit, 111 T-12 fixtures in Taft Residence Hall were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 17,502 hours. The simple payback for this project is 2.81 years.
Van Doren Hall
Associated Project(s):As part of the Housing Lighting Retrofit, 41 T-12 fixtures in Van Doren Residence Hall were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 6,465 hours. The simple payback for this project is 2.81 years.
Barton Hall
Associated Project(s):As part of the Housing Lighting Retrofit, 53 T-12 fixtures in Barton Residence Hall were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 8,357 hours. The simple payback for this project is 2.81 years.
Clark Hall
Associated Project(s):As part of the Housing Lighting Retrofit, 110 T-12 fixtures in Clark Residence Hall Administration Building were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 17,345 hours. The simple payback for this project is 2.81 years.
Lundgren Hall
Associated Project(s):As part of the Housing Lighting Retrofit, 59 T-12 fixtures in Lundgren Residence Hall were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 9,303 hours. The simple payback for this project is 2.81 years.
Hopkins Hall
Associated Project(s):As part of the Housing Lighting Retrofit, 153 T-12 fixtures in Hopkins Residence Hall were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 24,125 hours. The simple payback for this project is 2.81 years.
Forbes Hall
Associated Project(s):As part of the Housing Lighting Retrofit, 638 T-12 fixtures in Forbes Residence Hall were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 100,600 hours. The simple payback for this project is 2.81 years.
Weston Hall
Associated Project(s):As part of the Housing Lighting Retrofit, 141 T-12 fixtures in Weston Residence Hall were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 22,233 hours. The simple payback for this project is 2.81 years.
Scott Hall
Associated Project(s):As part of the Housing Lighting Retrofit, 170 T-12 fixtures in Scott Hall were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 26,806 hours. The simple payback for this project is 2.81 years.
Snyder Hall
Associated Project(s):As part of the Housing Retrofit, 161 T-12 fixtures in Snyder Residence Hall were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 25,386 hours. The simple payback for this project is 2.81 years.
University Press
Associated Project(s):As part of the Lighting Retrofit #5, 488 T-12 fixtures in the University Press Building were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 76,948 hours. The simple payback for this project is 3.64 years.
Transportation Building
Associated Project(s):As part of the Lighting Retrofit #5, 547 T-12 fixtures in the Transportation Building were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 86,251 hours. The simple payback for this project is 3.56 years.
Temple Hoyne Buell Hall
Associated Project(s):As part of the Lighting Retrofit #5, 471 T-12 fixtures in Temple Hoyne Buell Hall were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 74,267 hours. The simple payback for this project is 3.56 years.
Speech and Hearing Clinic
Associated Project(s):As part of the Lighting Retrofit #5, 47- T-12 fixtures in the Speech and Hearing Clinic were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 74,110 hours. The simple payback for this project is 3.08 years.
Shelford Vivarium Greenhouse
Associated Project(s):As part of the Lighting Retrofit #5, 335 T-12 fixtures in the Shelford Vivarium Greenhouse were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 52,823 hours. The simple payback for this project is 3.53 years.
Personnel Services Building
Associated Project(s):As part of the Lighting Retrofit #5, 433 T-12 fixtures in the Personnel Services Building were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 68,275 hours. The simple payback for this project is 3.2 years.
Nuclear Physics Lab
Associated Project(s):As part of the Lighting Retrofit #5, 415 T-12 fixtures in the Nuclear Physics Lab were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 65,437 hours. The simple payback for this project is 3.56 years.