  • This form will search for any of the words you enter in a field, not the exact phrase you enter. If you would like to search for an exact phrase, put double quotes (") around the phrase. For example, if you search for Bike Path you will get results containing either the word Bike OR the word Path, but if you search for "Bike Path" you will get results containing the exact phrase Bike Path.
  1. Eco-Counter set installed and activated at Green and Goodwin

    A set of Eco-Counters were installed at the intersection of Green St and Goodwin Ave by Loomis Laboratory on Monday, May 9, 2022. This was a new set of counters with no groundbox, purchased in October 2021. This set of Eco-Counter was purchased using the SSC funding. These counters were activated on May 10, 2022, and they are now collecting and transmitting data. See attached the pictures of these counters.

  2. Eco-Counter set installed and activated at Armory and Sixth

    A set of Eco-Counters were installed at the intersection of Armory Ave and Sixth St on Tuesday, April 26, 2022. This is the last set of old counters that were purchased in 2019. These counters were activated on April 27, 2022, and they are now collecting and transmitting data. See attached to see the pictures of these counters.

  3. Campus Transportation Advisory Committee (CTAC) spring 2022

    Please see attached the final presentation for the CTAC spring 2022. We also talked about abandoned bicycles and Campus Landscape Master Plan during this meeting. Also watch the meeting recording and read the chat from during the meeting: https://uofi.box.com/s/lv1xbqlcevdp6f2dfmiep2fpx3cq2zde

  4. Scope Change requested: Bike and Ped Counters

    Sarthak Prasad requested a scope change for the Bicycle Registration and RFID Tracking Program project on July 23, 2021. This scope change request includes changes to the following:

    1. Project name change
    2. Primary contact for the project
    3. Change in Project description
    4. Timeline extension
    5. Plan for the remaining fund – purchase and install another Eco-Counter. Overage will be covered by TDM

    Please see attached the scope change document from 2020 as well as 2021.

  5. Archived description

    Associated Project(s): 

    The MCORE project requires the CUUATS partners to monitor the pedestrian and bicycle counts following the completion of the project. This requirement is to understand the increased waking and bicycling activities at the twelve predetermined corridors. CCRPC collected pedestian and cycling counts at these locations before the MCORE project. These twelve corridors are listed in this project update.

    The University has identified other locations on campus to add pedestrian/bicycle counters as well, other than these twelve MCORE corridors. In March 2020, the first Eco-Counter pedestrian/bicycle counter was installed at the Illini Union location on Green Street. The University is also working with Obama Energy to get IntelliStreet light poles for pedestrian/bicycle count collection.

  6. Funding Letter - Bike Registration RFID

    This project funds an opt-in bike tracking system for all registered campus bikes working toward two goals: 1) Collecting useful data on where cyclists are biking on campus for more accurate and timely information than the perennial bike census; and 2) Providing incentives for people who bike to campus, in the form of points toward or drawings for gift certificates for local dining options near campus. When students and faculty of the University register their bikes, they will each receive a tag for their bike with a personal ID number. With the data collected about their individual biking habits, students and faculty will be able to track how often they bike and earn rewards through an online interface and incentive system. The interface will show the number of times biked, the rewards an individual can earn, and offer the ability to submit reports since bikers often see needed improvements before planners and engineers. This system is being developed entirely in-house by a team of women engineers. This proposal directly funds: 1) Supplies for creating the system 2) Two interns to assist with logistics 3) Mounting equipment and RFID tags.