Armory Bike Path Restoration
In the attached file is the Armory Bike Path Restoration plans.
Search tips:
In the attached file is the Armory Bike Path Restoration plans.
The Transportation SWATeam met on Wednesday, February 2021 at 10AM to discuss the following:
The Transportation SWATeam met on Wednesday, February 2021 at 10AM to discuss the following:
The Campus Bike Network will be implemented in the short-term with incremental steps that are available within previously funded projects.
Please see attached the progress report for 2014 Campus Bicycle Plan. This report reflects the progress made by the University towards the implementation of the bike plan in the last five years. The Bike Plan was also updated to reflect the changes mentioned in this progress report.
Here is the initial rough estimate for the Armory Avenue bike path for the section by Gregory Hall:
The cost of landscaping is not included in this estimate. We will be using the SSC funds available + the bike fee money for this bike path section.
Final Project Deliverables for Spring 2020
There were 7 projects completed by the WIE-GFX Abroad Scholars in the Spring 2020 semester of ENG 177
The construction on the path began in summer 2020 and was completed by the time students returned to campus. The old bike paths, along with hedges, overgrown evergreens, and decorative urns were removed from the area. A new 6 foot wide path was constructed and plans have been made to restore the landscape as needed. The Armory Avenue bike path is now open to use!
This project tied in with the renovation of the entire Armory Ave bike path that connects the bike lane on Armory Ave to the bike lane on Goodwin Ave. This bike path goes through the Gregory Hall, Foellinger Auditorium, Smith Hall, IGB, and Bevier Hall.
Please see attached the final report for this project.
See the previous update for this project.
The SSC awarded $50,000 for the "Bike Path Renovation: Armory Avenue Path South of Gregory Hall". This award will expire on May, 2022. Please see attached the Funding agreement.
Please see attached.
Please see attached the initial idea for the Lock Your Bike Right (LYBR) contest.
Letters of Support for an ITEP grant for a bikeway along First Street from Windsor Road to Curtis Road.
Hello Transportation SWATeam members,
Thank you again for your willingness to help our campus achieve the Climate Leadership Commitments. There is great value provided by the bi-weekly meetings of student, faculty, and staff representatives evaluating our progress and recommending additional actions campus units could take.
The following is a list of current activities I am aware of, and suggestions I have about useful next steps. I am happy to follow up with you on any of these, as needed.
Thank you very much,
~Morgan
9/09/16
Summary: This meeting was our inaugural meeting for the year. On the agenda today was the creation of a team description, a review of ongoing projects, and planning for future meetings.
In attendance:
Josh Feldman
Claire Dondival
Ankit Singhai
Yangfeng Ouyang
Pete Varney
Lily Wilcox - Active Transportation Coordinator
Olivia Webb - Sustainability Programs Coordinator
Topics Covered:
Team Description
We collectively crafted our team description for the iCAP portal, which can be found at: https://icap.sustainability.illinois.edu/project/transportation-swateam.
Project Slides
Renewable Fleet Study:
Claire and Petehelped foster a discussion about the current types of alternative fuels for campus fleet vehicles. Currently, natural gas is the only type of fuel seriously looked at. One concern was that the gas CNG, while possible to implement, would be somewhat costly and have little payback unless driven many miles. Electric vehicles were brought up, but are currently not part of the market. Biodiesel was also mentioned, but its performance in cold weather is a concern.
Staff Mode Shift:
Lily discussed the ways that this project will reduce single occupancy vehicles. One idea looked at was bike sharing, which has been tried by Purdue but does not have much payback economically. Lily also discussed “It’s your MTD too”, which features social bus-riding trips which introduce MTD to campus employees.
Bike Plan:
This was a summary of effort to make campus more bike-friendly. This would include having more, and better, bike parking. UIUC was recently recognized as a bronze-level Bike Friendly University by the League of American Bicyclists.
Future Meetings
We decided that every other Friday at 1pm is a good time to hold meetings. We will be holding meetings in the National Soybean Research Laboratory. Our clerk Josh will send out reminders.
From Pennsylvania Ave and Goodwin to the Ag Engineering Building, patches covered some of the largest potholes along the bike path.
While the plan implementation is not done yet, the Armory Avenue path has seen concrete repair and improvement this summer. Sections between Lincoln and Goodwin have been repaired after recent construction has made the existing poor conditions worse.
The Foundation gift fund you have requested has been created:
338548 Campus Bicycle Plan Implementation and Mission Fund
When your unit is transmitting gifts to the Foundation for processing use this fund name and number on the gift transmittal.
Happy Bike Month Everybody,
We have lots of bike-related events going on in May. And as the use of bikes and the local bike community grows, we will have more and more bike events. This is all good. Champaign County Bikes will try to share local bike information and keep everyone informed. (A growing task for us, and one of the reasons we need to grow and add capacity!) For now, during Bike Month - our Bike Month calendar and resources are at www.CUBike.org A more complete and ongoing bike event calendar that draws from many of our local bike groups is at our CCB website, www.champaigncountybikes.org.
I just want to quick highlight a new event, one I just received some information on tonight. I believe it’s good that all of us who share leadership roles in our bicycle community are well informed, given that that we might be asked about any bike-related event in town, including this new event. Scott Bechtel and his staff at KellerWilliams Realtor are hosting this RED DAY Bicycle Recycle event, and as I understand it are promoting it primarily within their extensive network of contacts, and then generally in the community. One of our CCB members knows Scott and they have had some conversations. This is how CCB knows of RED DAY. Red Day falls on our local Bike to Work Day, Thursday, May 14.
You can find more information at: www.KWChampaignRedDay.com, at KellerWillimas, or their Facebook page.
Thanks for everything all of you are doing to make Champaign County an awesomely Bicycle Friendly Place!
Jeff
Jeff Yockey
President
Champaign County Bikes
217 565-1785
On March 3, 2015, the Chancellor's Capital Review Committee formally approved the 2014 Campus Bike Plan for inclusion in the official Master Planning documents.
Transportation Demand Management (TDM) in Facilities & Services is finalizing the 2014 Campus Bike Plan, a master plan to direct our efforts for future bicycle infrastructure improvements and program development. The official public comment period for the Campus Bike Plan ended in April 2013, but additional feedback is always welcome via the online bicycle feedback form.
The draft 2014 Campus Bike Plan was available for public input during a four-week period, and members of the campus community were encouraged to review the plan and submit their comments and feedback via the online Campus Bicycle Feedback Form.