Projects Updates for theme: all

  1. ISR Wardall

    Associated Project(s): 

    As part of the Housing Lighting Retrofit, 73 T-12 fixtures in ISR Wardall Residence Hall were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 11,511  hours. The simple payback for this project is 2.81 years.

  2. Student Staff Apartments

    Associated Project(s): 

    As part of the Housing Lighting Retrofit, 136 T-12 fixtures in the Student Staff Apartments were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 21,444  hours. The simple payback for this project is 2.81 years.

  3. Evans Hall

    Associated Project(s): 

    As part of the Housing Lighting Retrofit, 500 T-12 fixtures in Evans Residence Hall were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 78,840  hours. The simple payback for this project is 2.81 years.

  4. Busey Hall

    Associated Project(s): 

    As part of the Housing Lighting Retrofit, 391 T-12 fixtures in Busey Residence Hall were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 61,653 hours. The simple payback for this project is 2.81 years.

  5. Taft Hall

    Associated Project(s): 

    As part of the Housing Lighting Retrofit, 111 T-12 fixtures in Taft Residence Hall were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 17,502  hours. The simple payback for this project is 2.81 years.

  6. Van Doren Hall

    Associated Project(s): 

    As part of the Housing Lighting Retrofit, 41 T-12 fixtures in Van Doren Residence Hall were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 6,465  hours. The simple payback for this project is 2.81 years.

  7. Barton Hall

    Associated Project(s): 

    As part of the Housing Lighting Retrofit, 53 T-12 fixtures in Barton Residence Hall were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 8,357  hours. The simple payback for this project is 2.81 years.

  8. Clark Hall

    Associated Project(s): 

    As part of the Housing Lighting Retrofit, 110 T-12 fixtures in Clark Residence Hall Administration Building were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 17,345  hours. The simple payback for this project is 2.81 years.

  9. Lundgren Hall

    Associated Project(s): 

    As part of the Housing Lighting Retrofit, 59 T-12 fixtures in Lundgren Residence Hall were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 9,303  hours. The simple payback for this project is 2.81 years.

  10. Hopkins Hall

    Associated Project(s): 

    As part of the Housing Lighting Retrofit, 153 T-12 fixtures in Hopkins Residence Hall were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 24,125  hours. The simple payback for this project is 2.81 years.

  11. Forbes Hall

    Associated Project(s): 

    As part of the Housing Lighting Retrofit, 638 T-12 fixtures in Forbes Residence Hall were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 100,600  hours. The simple payback for this project is 2.81 years.

  12. Weston Hall

    Associated Project(s): 

    As part of the Housing Lighting Retrofit, 141 T-12 fixtures in Weston Residence Hall were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 22,233 hours. The simple payback for this project is 2.81 years.

  13. Scott Hall

    Associated Project(s): 

    As part of the Housing Lighting Retrofit, 170 T-12 fixtures in Scott Hall were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 26,806 hours. The simple payback for this project is 2.81 years.

  14. Snyder Hall

    Associated Project(s): 

    As part of the Housing Retrofit, 161 T-12 fixtures in Snyder Residence Hall were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 25,386 hours. The simple payback for this project is 2.81 years.

  15. University Press

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 488 T-12 fixtures in the University Press Building were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 76,948 hours. The simple payback for this project is 3.64 years.

  16. Transportation Building

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 547 T-12 fixtures in the Transportation Building were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 86,251 hours. The simple payback for this project is 3.56 years.

  17. Temple Hoyne Buell Hall

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 471 T-12 fixtures in Temple Hoyne Buell Hall were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 74,267 hours. The simple payback for this project is 3.56 years.

  18. Speech and Hearing Clinic

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 47- T-12 fixtures in the Speech and Hearing Clinic were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 74,110 hours. The simple payback for this project is 3.08 years.

  19. Shelford Vivarium Greenhouse

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 335 T-12 fixtures in the Shelford Vivarium Greenhouse were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 52,823 hours. The simple payback for this project is 3.53 years.