You are here

Projects Updates for place: Transportation Building

  1. FY17 ECIP award winners announced

    Occupant Action Category

    % Improvement

    Incentive Award

    1. Foellinger Auditorium 41.0% $61,994
    2. Natural Resources Building 21.0% $38,543
    3. 1207 W. Oregon 19.4% $15,677
    4. Agricultural Engineering Sciences
        Building
    13.6% $12,986

    Energy Advancement Category

    % Improvement

    Incentive Award

    1. Early Child Development
        Laboratory
    25.2% $10,000*
    2. Administrative Information Technology
        Services Building
    24.1% $10,000*
    3. Astronomy Building 23.4% $10,000*
    4. ACES Library, Information &
        Alumni Center
    23.2% $10,000*

     

  2. iWG meeting minutes October 27, 2017

  3. ECBS SWATeam Meeting Minutes

    The Division of Intercollegiate Athletics (DIA) is looking to become more involved with the SWATeams and sustainability on campus. ECBS proposed ideas such as decreasing refrigerator usage, making a climate action plan specifically for DIA, and promoting recycling at tailgates. Illini Lights Out had their first event on September 29, and it was a success. 284 light switches were turned off in 13 different buildings. The Green Labs Coordinator position is slowly making progress, but there is a concern with funding. Updates on the ECIP were made, and there is a push being made for mid-year checkpoints in the future. ECBS also discussed if AFMFA projects could be redefined in order to do more maintenance-based projects. 

    Attached Files: 
  4. Provost Office approves funding for LED Exit Signs

    The Office of the Provost approved $75,000 in one-time funding for the next step in the LED Exit Sign retrofit project.  The funding of $75,000 is for LED Exit Sign lighting replacement, additions, and new building surveys.  Material and labor of $70,000 would be used to replace 343 fixtures in 20 buildings at an average rate of $204/fixture.  An additional $5,000 is proposed to survey 50 campus buildings for exit light counts.  That will provide the input necessary for the next phase, once this phase is completed.

  5. Discussion at Transportation Building about ECIP funds

    Morgan Johnston and Shawna Grady met to discuss the potential uses for the Transportation Building's ECIP funding award ($10,000).  Options included additional recycling bins, LED lamps, power strips, battery recycling containers, and potentially a waste characterization study for the building (if available through ISTC).

  6. KCPA ECIP funds to go towards several improvements

    Krannert Center has identified several projects to tackle with the ECIP award funding: 

    • Recycling Bins and Bags - $5,000 (make in-house recycling efforts more efficient and accessible)
    • TCP Switch for Playhouse - $6,000 (electrical safety issue)
    • Imop -  $5,000 (water conservation)
    • Food Services Dishwashers - $9,750 (energy efficiency, water conservation, chemical usage reduction)
    • Energy efficient washer and dryers (2 each) for Festival Green Room -  $2,250 (energy efficiency, water conservation)
    • Ipad mini’s & Ipad & Secure Mounts for Attendant Access to Calendar and Event Sheets - $2,500  (reduce printed paper)
    • Reconfigure Stairs to Playhouse Pit  - $3,500 (safety issue correction)

    The dollar amounts listed are approximations.  Any additional funds not used for these items would be allocated to expanding the stock of replacement LED bulbs.

  7. Sarthak Prasad Final Report: Independent study with Morgan Johnston ENG 573 (fall 2016)

  8. 2016 Winners Announced!

    The 2016 ECIP award winners were announced last Wednesday, and they will be given plaques at the annual Campus Sustainability Celebration this week, 10/16 from 4-6 at the Alice Campbell Alumni Center.  Here is the letter.

    Congratulations!

    We would like to recognize your unit as a 2016 Energy Conservation Incentive Program (ECIP) award winner during the Campus Sustainability Celebration on Wednesday, October 26 from 4-6 p.m. at the Alice Campbell Alumni Center. For planning purposes, please let us know who will be accepting the award(s) on behalf of your unit by Friday, October 21.

    Sustainability initiatives are at the core of Illinois’ commitment to its land-grant university mission. The Climate Leadership Commitment pledges the Urbana campus to be carbon neutral by 2050, which requires all students, staff, and employees working together to implement a dynamic, multi-disciplinary approach to campus sustainability.

    The ECIP awards began in 2013 as a way to recognize outstanding individual and team efforts that move us closer to reaching our Illinois Climate Action Plan (iCAP) goals. The ECIP honors occupants of campus buildings that have reduced energy at the greatest level from one year to the next. This year more than $177,000 for improvement projects in winning facilities will be provided through the program.

    Everyone researching, learning, and working in these nine buildings is an ECIP winner, and we encourage as many participants to join the celebration as possible.  Hosted by Facilities & Services and the Institute for Sustainability, Energy, and Environment, the Campus Sustainability Celebration will cover the iCAP objectives, celebrate the diverse sustainability community, and recognize 2016 winners. 

    We look forward to you and your employees joining us to celebrate the ECIP winners and their contributions toward campus energy conservation.

    2016 ECIP WINNERS

     Occupant Action Category

     % Improvement

    Incentive Award

    1. Atmospheric Sciences Building

    7.5%

                 $50,324

    2. Krannert Center for the Performing Arts

    4.8%

                   $34,111

    3. Institute of Government & Public Affairs Building

    4.4%

                   $15,083

    4. 1207 West Oregon Street (tie)

    2.9%

                   $10,048

    4. Temple Hoyne Buell Hall (tie)

    2.4%

                  $11,486

     Energy Advancement Category

     % Improvement

     Incentive Award

    1. Davenport Hall

    25.8%

                  $26,335

    2. Ceramics Kiln House

    21.2%

                  $10,000

    3. Transportation Building

    14.0%

                  $10,000

    4. Rehabilitation Education Center

    9.6%

                 $10,000

     

    Helen J. Coleman, LEED AP
    Interim Executive Director

    University of Illinois Urbana-Champaign
    Facilities & Services
    1501 South Oak St.
    Champaign, IL 61820
    Phone: (217) 265-8477
    E-mail: hjcolema@illinois.edu

     

  9. Meeting with F&S officials

    Associated Project(s): 

    Met with the university Facilities and Services officials and LED staff on Wednesday, September 21, 2016, to discuss the progress of LED Campus projects so far. The main focus of the meeting was Exit signs in the buildings. Meeting was hosted by Mogan Johnston, and attended by Ken Buenting, Brian Finet, Steven Bainbridge, and Patty Douglas.

  10. ECBS Objective 4 Subcommittee Meeting Minutes

    The ECBS Objective 4 Subcommittee met Tuesday, February 16 to continue fleshing out the ECBS SWATeam's fourth iCAP objective, which has to do with increasing campus engagement in sustainability.  Discussion continued on ECIP and potential changes for the upcoming year- a major issue is raising awareness of this program and others like it. By the conclusion of the meeting, the focus of the subcommittee shifted to creating and sending recommendations to the iCAP Working Group, such as a Green Labs Initiative proposal as well as continuing Eco-Olympics or initiating a similar program that would serve as dorm resident engagement.  The next meeting is scheduled for Tuesday, February 23.

  11. ECBS Objective 4 Subcommittee Meeting Minutes

    The ECBS Objective 4 Subcommittee held its first meeting on Tuesday, February 9.  Discussion revolved around the issue of tying all existing campus engagement programs (e.g., ECIP, Certified Green Office Program, revolving loan fund, etc.) together into one campus-wide brand.

    Attached Files: 
  12. FY15 ECIP award winners announced

    Occupant Action Category  % Improvement  Incentive Award
    1. Admissions and Records
        Building  
     39.2%  $61,778
    2. Agricultural Bioprocess
        Laboratory 
     25.2%  $34,110
    3. Christopher Hall  24.9%  $18,297
    4. Turner Hall     11.4%  $16,075
     Energy Advancement Category  % Improvement  Incentive Award
    1. David Kinley Hall 39.9%   $33,701
    2. Lincoln Hall 32.0%   $15,961
    3. Early Childhood Development
        Building
    24.2% $10,000
    4. Davenport Hall  19.6%  $10,000

     

  13. FY14 ECIP Winners Announced

    CHAMPAIGN, IL (October 22, 2014) – Eight facilities on the Urbana campus will win funding for facility improvements as recipients of the 2014 Energy Conservation Incentive Program (ECIP) awards on Wednesday, October 22 at 3:00 p.m. in Illini Union 314B as a part of the Illinois Climate Action Plan (iCAP) Forum.

    Last year, the ECIP awarded more than $250K in pre-approved energy conservation projects.

    The list of FY14 winning facilities is attached.

  14. Campus approves an additional $100K for LED Exit Signs

    Associated Project(s): 

    After the successful completion of the recent LED Exit Sign upgrades, the F&S Building Maintenance division has received approval for another round of LED Exit Sign upgrades.  Ken Buenting, Sharon Ball, Ryan Wild, and Morgan Johnston met to discuss the prioritization process for identifying the next buildings to address.  Buildings will be ranked according to student/transient visitor contact hours (if this information can be obtained), results of campus code fire safety reports, and coordination with other projects or funding.

  15. LED Exit Sign projects completed

    Associated Project(s): 

    In support of the Chancellor's commitment to making the University of Illinois an LED Campus, 531 LED way-finding signs have been installed in eight campus buildings: Grainger Library, Animal Science, Roger Adams Lab, Engineering Science Building, Turner Hall, Main Library, Education Building, and the Chem. Life Sciences Lab.

  16. Spurlock ECIP project

    Mike,

    As we discussed on the phone, our Electricians have visited with the folks at Spurlock and secured a preliminary scope of work (see attached). Because of the complex existing lighting system in the building our Electricians will require some assistance from our In-House Engineering staff. I understand that Spurlock has been allotted $22K for this work. I am going to ask Robert to give us an estimate of the Engineering charges and if they exceed 10% of the budget we will discuss scaling back some of the scope with the folks at Spurlock. The AiM project is 2693 and the Engineering estimate work order is 10282137.

    Thanks,

    Thomas Doud

    Construction Superintendent

    Construction Services Division

    University of Illinois, Facilities and Services

    217-244-3686

    Attached Files: 
  17. updated list of LED exit sign buildings

    Associated Project(s): 

    FY07 - 13 buildings

    • 112 - MEB
    • 26 - Altgeld
    • 12 - Noyes
    • 99 - Undergrad
    • 210 - DCL
    • 15 - Engineering Hall
    • 152 - Hydrosystems
    • 67 - Loomis
    • 29 - MEL
    • 34 - MSEB
    • 24 - Newmark
    • 13 - Talbot
    • 42 - Transportation Bldg

    FY08 - 12 buildings

    • HARDING BAND BUILDING #4
    • ILLINI HALL #65
    • OPTICAL PHYSICS BUILDING #165
    • ILLINOIS PROGRAM FOR RESEARCH & HUMANITIES #221
    • ARCHITECTURE BUILDING #50
    • NOBLE HALL #90
    • ART & DESIGN #219
    • MUSIC BUILDING #39
    • FLAGG HALL #89
    • UNIVERSITY HIGH SCHOOL #61
    • ARMORY #6
    • FOELLINGER AUDITORIUM #7

    FY14 – CURRENT PROJECT

    • #324 Grainger Library
    • #174 Engineering Sciences
    • #116 Roger Adams Lab
    • #336 Animal Sciences
    • #197 Turner Hall
    • #370 South Studio #5
    • #371 South Studio #7

    OTHER PROJECTS

    • #339 Temple Buell Hall
  18. update on project progress

    Associated Project(s): 

    Ken Buenting, Sharon Ball, Eva Sweeney, Morgan Johnston, and Ryan Wild met to review progress on the LED Exit Sign work.  Ken reported great progress with four buildings complete and one in progress: Grainger, RAL, Animal Sciences Lab, and the Engineering Sciences Building.  They are in Turner Hall now.  Just over $24K has been spent so far through the contractor.  They will move on to the Main Library and the Education Building next.

    The current implementation process is as follows:

    1. Ryan Wild and Morgan Johnston work with others to identify the priority list of buildings.
    2. Eva Sweeney will review records to ascertain whether the fixtures are connected to an emergency generator or will need battery backup.
    3. Sharon Ball and team will do the initial count of fixtures.
    4. Ken Buenting will direct the hired contractor to replace the existing fixtures and provide data sheets for our records.
    5. Eva Sweeney and Ryan Wild will identify additional signage installation needs.
    6. Ken will direct the F&S electricians to install the additional signs.

    Eva had Ken remove Temple Buell Hall from the list because it is being handled through another project.  Also, through other funding, South studio five and seven were completed.