You are here

Projects Updates for theme: Transportation

  1. Update on Charging Stations

    From: Robert O'Daniell <rodaniell@att.net>
    Sent: Sunday, February 27, 2022 5:05 PM
    To: White, Morgan; Slezak, Paul
    Cc: DeLorenzo, Stacey; Prasad, Sarthak
    Subject: I guess I spoke too soon Re: I’m happy to report

    The ChargePoint locations at B4, D22 and E14 are all down. Disappeared from the ChargePoint app and will not charge. (Discovered Sunday noonish at E14 when I failed to begin charge. Standing beside the charger the App said no chargers nearby) Checked the other locations. All three locations have same message on the screen.

    Robert K. O'Daniell
    Photographer Emeritus-News-Gazette
    PO Box 2085
    Champaign, IL 61825
    217-352-1493

    Attached Files: 
  2. Transportation iCAP Team February Meeting

    The Transportation iCAP team met on Thursday, 2/25/2022 at 4:00 P.M. and discussed the following topics:

    • Scoring for the upcoming walkability audit
    • Questions for an upcoming mode choice survey

    Further details are in attached documents.

    Attached Files: 
  3. Update on Charging Stations

    From: Robert O'Daniell <rodaniell@att.net>
    Sent: Friday, February 25, 2022 1:43 PM
    To: White, Morgan; Slezak, Paul
    Cc: DeLorenzo, Stacey; Prasad, Sarthak
    Subject: I’m happy to report

    The chargers at B4 are back - showing up on the Where to Charge apps again. (Began Feb 24th)

    The damaged screen still not replaced at D22 ( supply chain issue ? )

    On an odd note in the last week or so – I failed in an attempt to charge at E14. Possibly a weather issue and there are indications that others have indeed charged. I have not yet tried again. Possibly a one time issue.

    During that attempt I became aware of some kind of issue with 3G on all three of those charging stations. ATT shut down Feb 22 and Verizon and T-mobile will both shut down 3G by the end of the year. All 3 ChargePoint locations indicate “Illini charging / Off network 1” and a warning message. I did drive by and cars are indeed charging at B4 and at D22 in spite of that message.

    ( images below )
    ——————
    As a retired person I’ve taken on the project of making it easier for people buy and transition to EVs. And to do what I can to improve the infrastructure needed for the EVs.

    Robert K. O'Daniell
    PO Box 2085
    Champaign, IL 61825
    217-493-8129

  4. Walkability audit: Spring 2022, Meeting 5,6

    Associated Project(s): 

    On Feb 17 and 24, Sarthak and Sutapa met to discuss the scoring system of the General Walkability audit. 

    We prepared a comparative list of 2 scoring systems (0-5 scale scores and negative to 5 scale scores). The Transportation dept. group meeting on 24th February has an agenda to finalise our scoring system after discussion.

    We have also prepared a spreadsheet with all the results of the survey and formatted it in a way that has questions on each row and one survey per column of the audit. Instead of prioritizing our larger categories of parameters, we decided to assign priorities to each question as High, Medium and Low with weights of x3, x2 and x1 respectively.

    Map blocks 9, 10, 14, 22, 23 and 27 have no records yet. Part 2 of Data collection for the same will start in the last week of March when the weather gets pleasant to walk around. A call for volunteers has been made in the SPO meeting on February 23rd, 2022.

    Results of Transportation group meeting on 24th February:

    1. Scoring system was discussed and finalized

    • Questions are categorized into High, Medium and Low categories. A few questions are marked as Bonus questions with Low priority.
    • 0-5 scoring scale was chosen to represent the options. Negative points were discontinued.
    • Total addition of weighted scores at this stage was 65 points.

    2. Mass email to be sent out again to MUP students as a 'Call for Volunteers' next week.

    3. Chad and Justin to colour code the categories of the Deficiency reporting surveys in the coming weeks.

     

     

  5. Faculty/Staff Carpool Survey

    The University of Illinois (UIUC) is interested in achieving its Climate Action Plan’s transportation sustainability goals by “reducing single-occupancy vehicle usage” and “promoting the use of electric vehicles” on campus. This survey is designed to evaluate the commuting needs of UIUC faculty and staff, so as to inform future actions on two fronts: (i) feasibility of developing a faculty/staff carpool service, and (ii) expanding electrified vehicle charging infrastructure on campus.

    Survey link: https://survey123.arcgis.com/share/d7c2b2bf267245808ab12570323b5402 

  6. Weekly Update: Uni High Agora Days classes; Maintenance Class

    All, Last week we held our Uni High Agora Days classes from Tues – Fri. It went very well with all the students engaged in learning and tinkering on the bikes. One student even said they’d return to volunteer, which was great. All 3 of the bikes were mostly done by week’s end. We also received some quality donations from a local bike shop and started overhauling those bikes for sale. I’ve also hired a new Program Assistant to help me out off-hours.

    This week I’ll be meeting with the Urbana Parks District to discuss our Maintenance class we’re collaborating on next month and getting more bikes ready for the sales floor. We’ll see how busy we are today with the very warm weather.

    The numbers:

    Visitors: 11
    Sales: $91
    Memberships: 2 for $60

    Thanks!

    Jacob Benjamin
    Campus Bike Center Coordinator

  7. Mode Choice Survey 2022

    Associated Project(s): 

    After discussions internally at F&S (in the Sustainability and Transportation Demand Management departments) and then discussions with iSEE, it was agreed that the F&S TDM department will conduct the Mode Choice Survey in 2022 and every 3 years going forward.

  8. Weekly Update: Build-a-bike, Uni High Agora Days class

    All, Picked up 4 – 5 bikes from Urbana last week which were promptly claimed as B-a-Bs or tagged for shop builds. This week we have our Uni High Agora Days class coming in Tues – Fri. This will reduce our open hours on Wed/Fri to 4 – 6p.

    I’ll be picking up 5 bikes from Champaign Cycle on Tuesday afternoon, too. That should get us towards a good number of bikes on hand.

    The numbers:

    visitors: 10
    Sales: $324
    Bike (refurb): 1 for $180
    Memberships: 3 for $90

    Thanks!

    Jacob Benjamin
    Campus Bike Center Coordinator

  9. Walkability audit: Spring 2022, Meeting 3 & 4

    Associated Project(s): 

    On Feb 3rd and Feb 10th, Sarthak and Sutapa met to transport data from ArcGIS Survey 123 app to an excel spreadsheet. (attached)

    General Walkability study spreadsheet:

    1. Data was cleaned and transposed. Each question is located on a separate row. Each column accounts for 1 survey taken by a volunteer of the study.

    2. A separate sheet was designated for assigning each question with scores on a scale of 1-5.

    3. Using the function index and match, formulas were introduced for each survey answer in the database.

    A group meeting is scheduled in the end of February to finalize the scoring system of the map- blocks. The next step is to calculate averages for each map block and assign an average score out of 5 for each parameter.

     

    Incomplete survey: The Map blocks 9, 10, 14, 22, 23 and 27 have no records yet. When the weather conditions improve in March 2022, another round of data collection is scheduled to be undertaken by volunteers. Details regarding their training sessions will be shared soon.

     

     

  10. Weekly Update: Restocking bikes and parts for sale

    Associated Project(s): 

    All, With the snowstorm last week, we were closed on Wednesday but were able to reopen on Friday. Visitor numbers took a hit with a foot of snow and whiteout conditions (no surprise there). This week I’ll get some bikes from Urbana (snow derailed that plan last week). We’re down to the dregs of steel-rimmed 3 speed schwinns—bikes I’m not exactly comfortable selling in the dead of winter considering their compromised braking/stopping. Our donations of late have all been Walmart-level, unfortunately. We’ve got about 8 bikes on the sales floor as of now.

     

    The numbers:

    Visitors: 16
    Sales: $180
    Memberships: 3 for $90
    Tire/tubes: 4 for $30

    Thanks!

    Jacob Benjamin
    Campus Bike Center Coordinator

  11. Walkability audit: Spring 2022, Meeting 2

    Associated Project(s): 

    On 27th Jan, 2022, Sarthak and Sutapa met to discuss the scores of the general Walkability Questionnaire. The draft of the same was sent to all members involved in the audit. They will get back with suggestions/ corrections by the end of February when there will be another group meeting to finalize the scores.

    We also prepared an excel spreadsheet with each question and scores next to it for analyzing the data- attached.

     

    Attached files:

    1. [DRAFT] Updated scoring system- editable document

    2. [DRAFT] Scoring system and priority map

    3. Spreadsheet of General Walkability Questionnaire

  12. Walkability audit: Spring 2022, Meeting 2

    Associated Project(s): 

    On 27th Jan, 2022, Sarthak and Sutapa met to discuss the scores of the general Walkability Questionnaire. The draft of the same was sent to all members involved in the audit. They will get back with suggestions/ corrections by the end of February when there will be another group meeting to finalize the scores.

    We also prepared an excel spreadsheet with each question and scores next to it for analyzing the data- attached.

     

    Attached files:

    1. [DRAFT] Updated scoring system- editable document

    2. [DRAFT] Scoring system and priority map

    3. Spreadsheet of General Walkability Questionnaire

  13. Weekly Update: more Build-a-Bike available, Uni High Class

    Associated Project(s): 

    All, Surprisingly busy here last week! Sold a bike and if we had more Build-a-Bike frames available, we’d have a quarter dozen or so in-progress. Towards that end I’ll be grabbing some bikes from Urbana this week.

    Our Uni High class is in a couple weeks so we’ll do some internal planning for that event.

    The numbers:

    Visitors: 27
    Sales: $357.50
    Bikes (refurb): 1 for $80
    Memberships: 5 for $150
    Tires/tubes: 3 for $22

    Thanks!

    Jacob Benjamin
    Campus Bike Center Coordinator

  14. Transportation iCAP Team January Meeting

    The Transportation iCAP team met on Thursday, January 27th from 4:00-5:00 P.M. The team discussed progress on the EV Task Force Member Recommendation, the fleet replacement plan recommendation, and two returned recommendations: the Carbon Credit program and the Carpool Survey.

    The team has decided to do further research into what a carpool system would look like at the U of I, and will discuss the matter further with insight from other schools at the next meeting. Progress will hopefully be made on the Fleet Replacement Plan Recommendation, as the team will be meeting with Pete Varney in the Parking Department soon.

     

    Further Information can be found in the attached document.

    Attached Files: 
  15. Weekly Update: Shop reopening this week

    Associated Project(s): 

    All, Last week we were open by appointment only. We logged 6 appointments and sold 1 bike.

    This week we will reopen to our usual M/W/F hours. Staff are eager to get back to work. We’ll have to run some refreshers for folks as I’m sure they’ve forgotten some stuff. We’ll do some inventory and build some bikes while we’re at it. We’ve got a couple other events coming up that we’ll have to prep for this week as well.

    The numbers:

    • Visitors: 6
    • Sale: $231.50
    • Bike: 1 for $200
    • Misc: $31.50

    Thanks!

    Jacob Benjamin
    Campus Bike Center Coordinator

  16. Walkability audit: Spring 2022, Meeting 1

    Associated Project(s): 

    On 20th Jan, 2022, Sarthak and Sutapa met to discuss the plan for the Walkability audit for Spring 2022. A list of goals/ objectives were finalized with timelines attached to them. 

    During the meeting, the priorities of the 7 walk criterions were reconsidered and updated. 'Safety' was put into a 'high priority' category and 'Pedestrian and Vehicular conflicts' was put into the 'low priority' category. The scores of each question of the 'General Walkability survey' were reassesed and finalized. The updated pdf with both these aspects are attached below.

     

     