You are here

Projects Updates for place: Business Instructional Facility (BIF)

  1. Water001 BIF Greywater Meter recommendation - Assessment with comments

    The iCAP Working Group (iWG) met on December 20, 2016, to discuss and start the assessment of SWATeam recommendation, Water001 BIF Greywater Meter. The iWG's official comment on the recommendation was:

    "A permanent real-time water meter should be installed on the greywater piping system in BIF, and the collected data should be made available in the Energy Billing System and through an online dashboard."

    See attached the iWG assessment of Water001 BIF Greywater Meter complete with official comments from all the iWG members.

    See SWATeam recommendation Water001 BIF Greywater Meter here.

  2. KCPA ECIP funds to go towards several improvements

    Krannert Center has identified several projects to tackle with the ECIP award funding: 

    • Recycling Bins and Bags - $5,000 (make in-house recycling efforts more efficient and accessible)
    • TCP Switch for Playhouse - $6,000 (electrical safety issue)
    • Imop -  $5,000 (water conservation)
    • Food Services Dishwashers - $9,750 (energy efficiency, water conservation, chemical usage reduction)
    • Energy efficient washer and dryers (2 each) for Festival Green Room -  $2,250 (energy efficiency, water conservation)
    • Ipad mini’s & Ipad & Secure Mounts for Attendant Access to Calendar and Event Sheets - $2,500  (reduce printed paper)
    • Reconfigure Stairs to Playhouse Pit  - $3,500 (safety issue correction)

    The dollar amounts listed are approximations.  Any additional funds not used for these items would be allocated to expanding the stock of replacement LED bulbs.

  3. Water001 BIF Greywater Meter recommendation - Submittal

    The Water and Stormwater SWATeam submitted a recommendation to the iWG stating, 

    "Monitoring the water usage in the Business Instructional Facility (BIF). Specifically, both the total water use and the amount of water used by the raw water system should be measured and the data made available to the campus community.

    BIF is unique in that it was constructed with a separate raw water system that conveys non-potable water to be used for purposes such as flushing toilets. While the system is in place inside the building, it was never connected to an outside source of non-potable water. Use of non-potable water for purposes such as toilet flushing, landscape irrigation, cooling, etc. is recognized as a sustainable practice (e.g., Asano et al, 2007; EPA, 2012). Data to quantify the impact this could have on water use at UIUC, however, is largely unavailable. Metering the raw water system at BIF would provide data about the temporal total and non-potable water demand at a typical campus class/office building. These data would be valuable to consider whether such systems should be considered in future campus construction and renovation.

    F&S installed a temporary meter to measure the flow to the raw water system and operated this meter for approximately one month (April – May 2016), so this recommendation has already been demonstrated to be feasible. However, because building usage is highly variable over the course of an academic year, we recommend that this should be a permanent installation. We also recommend that the data be made available to the campus community to encourage consideration of such water reuse options."

    See attached the SWATeam recommendation Water001 BIF Greywater Meter complete with comments from all the Water and Stormwater SWATeam.

  4. Urban Legend - debunked

    "As the University of Illinois at Urbana-Champaign considers installing more solar photovoltaic modules on the roofs of buildings, the discussion turns to the type of mounting systems to consider. This discussion often elicits the tale of the modules that were originally installed on the roof of the Business Instructional Facility (BIF) using a ballast-mounted system, that is, a mounting system held down using heavy weights such as concrete blocks. The story goes that a few of the PV modules blew off the roof of the building, and this subsequently led to the modules being installed with a racking system attached to the roof of the building.

    This story is an urban legend..."

    Read file for more information and photos.

     

    Attached Files: 
  5. 2016 Winners Announced!

    The 2016 ECIP award winners were announced last Wednesday, and they will be given plaques at the annual Campus Sustainability Celebration this week, 10/16 from 4-6 at the Alice Campbell Alumni Center.  Here is the letter.

    Congratulations!

    We would like to recognize your unit as a 2016 Energy Conservation Incentive Program (ECIP) award winner during the Campus Sustainability Celebration on Wednesday, October 26 from 4-6 p.m. at the Alice Campbell Alumni Center. For planning purposes, please let us know who will be accepting the award(s) on behalf of your unit by Friday, October 21.

    Sustainability initiatives are at the core of Illinois’ commitment to its land-grant university mission. The Climate Leadership Commitment pledges the Urbana campus to be carbon neutral by 2050, which requires all students, staff, and employees working together to implement a dynamic, multi-disciplinary approach to campus sustainability.

    The ECIP awards began in 2013 as a way to recognize outstanding individual and team efforts that move us closer to reaching our Illinois Climate Action Plan (iCAP) goals. The ECIP honors occupants of campus buildings that have reduced energy at the greatest level from one year to the next. This year more than $177,000 for improvement projects in winning facilities will be provided through the program.

    Everyone researching, learning, and working in these nine buildings is an ECIP winner, and we encourage as many participants to join the celebration as possible.  Hosted by Facilities & Services and the Institute for Sustainability, Energy, and Environment, the Campus Sustainability Celebration will cover the iCAP objectives, celebrate the diverse sustainability community, and recognize 2016 winners. 

    We look forward to you and your employees joining us to celebrate the ECIP winners and their contributions toward campus energy conservation.

    2016 ECIP WINNERS

     Occupant Action Category

     % Improvement

    Incentive Award

    1. Atmospheric Sciences Building

    7.5%

                 $50,324

    2. Krannert Center for the Performing Arts

    4.8%

                   $34,111

    3. Institute of Government & Public Affairs Building

    4.4%

                   $15,083

    4. 1207 West Oregon Street (tie)

    2.9%

                   $10,048

    4. Temple Hoyne Buell Hall (tie)

    2.4%

                  $11,486

     Energy Advancement Category

     % Improvement

     Incentive Award

    1. Davenport Hall

    25.8%

                  $26,335

    2. Ceramics Kiln House

    21.2%

                  $10,000

    3. Transportation Building

    14.0%

                  $10,000

    4. Rehabilitation Education Center

    9.6%

                 $10,000

     

    Helen J. Coleman, LEED AP
    Interim Executive Director

    University of Illinois Urbana-Champaign
    Facilities & Services
    1501 South Oak St.
    Champaign, IL 61820
    Phone: (217) 265-8477
    E-mail: hjcolema@illinois.edu

     

  6. ECBS Objective 4 Subcommittee Meeting Minutes

    The ECBS Objective 4 Subcommittee met Tuesday, February 16 to continue fleshing out the ECBS SWATeam's fourth iCAP objective, which has to do with increasing campus engagement in sustainability.  Discussion continued on ECIP and potential changes for the upcoming year- a major issue is raising awareness of this program and others like it. By the conclusion of the meeting, the focus of the subcommittee shifted to creating and sending recommendations to the iCAP Working Group, such as a Green Labs Initiative proposal as well as continuing Eco-Olympics or initiating a similar program that would serve as dorm resident engagement.  The next meeting is scheduled for Tuesday, February 23.

  7. ECBS Objective 4 Subcommittee Meeting Minutes

    The ECBS Objective 4 Subcommittee held its first meeting on Tuesday, February 9.  Discussion revolved around the issue of tying all existing campus engagement programs (e.g., ECIP, Certified Green Office Program, revolving loan fund, etc.) together into one campus-wide brand.

    Attached Files: 
  8. FY15 ECIP award winners announced

    Occupant Action Category  % Improvement  Incentive Award
    1. Admissions and Records
        Building  
     39.2%  $61,778
    2. Agricultural Bioprocess
        Laboratory 
     25.2%  $34,110
    3. Christopher Hall  24.9%  $18,297
    4. Turner Hall     11.4%  $16,075
     Energy Advancement Category  % Improvement  Incentive Award
    1. David Kinley Hall 39.9%   $33,701
    2. Lincoln Hall 32.0%   $15,961
    3. Early Childhood Development
        Building
    24.2% $10,000
    4. Davenport Hall  19.6%  $10,000

     

  9. Award Letter - Baseline Waste Characterization

    The primary deliverable of this proposed project is to provide a detailed waste characterization assessment for three facilities located throughout the Urbana-Champaign campus of the University of Illinois. Lincoln Avenue Residence Halls (LAR), Business Instructional Facility (BIF), Roger Adams Laboratory(RAL) are facilities that will be characterized.
    This proposal builds upon the initial waste characterizations conducted in the Spring of 2013 for four buildings: Henry Administration Building, Alice Campbell Alumni Center, Swanlund Administration Building, and Illini Union Bookstore.
    The objective of the assessments is to characterize the waste generated from a Lab building, a classroom building and a housing building. The primary goal of the waste stream characterization study is to provide UIUC with an accurate and precise baseline measurement of the solid waste generated at each facility type. ISTC will assist F&S in identifying and implementing practices and technologies that will reduce waste, increase landfill diversion, increase recycling revenues, and decrease waste disposal costs. These efforts will help UIUC to become an example of a sustainable campus, and will provide new learning and teaching opportunities for the university and community at large. The ancillary deliverables are various direct educational programing opportunities both structured as well as passive.

  10. FY14 ECIP Winners Announced

    CHAMPAIGN, IL (October 22, 2014) – Eight facilities on the Urbana campus will win funding for facility improvements as recipients of the 2014 Energy Conservation Incentive Program (ECIP) awards on Wednesday, October 22 at 3:00 p.m. in Illini Union 314B as a part of the Illinois Climate Action Plan (iCAP) Forum.

    Last year, the ECIP awarded more than $250K in pre-approved energy conservation projects.

    The list of FY14 winning facilities is attached.

  11. The Sustainability of the Photovoltaic Solar Panels on the Roof of Business Instructional Facility

    The photovoltaic panels on LEED Platinum certified Business Instructional Facility (BIF) rooftop harvests solar radiation as a clean renewable energy source for the University of Illinois at Urbana-Champaign facility. The solar system has a combined maximum output of 40 kilowatt per hour (kWh), and has an annual production of 60,000 kWh. The system is expected to produce approximately eight percent of the building’s total electricity demand. However, solar panels require unobstructed access to solar radiation for most or all of the day to be effective

    Attached Files: 
  12. Spurlock ECIP project

    Mike,

    As we discussed on the phone, our Electricians have visited with the folks at Spurlock and secured a preliminary scope of work (see attached). Because of the complex existing lighting system in the building our Electricians will require some assistance from our In-House Engineering staff. I understand that Spurlock has been allotted $22K for this work. I am going to ask Robert to give us an estimate of the Engineering charges and if they exceed 10% of the budget we will discuss scaling back some of the scope with the folks at Spurlock. The AiM project is 2693 and the Engineering estimate work order is 10282137.

    Thanks,

    Thomas Doud

    Construction Superintendent

    Construction Services Division

    University of Illinois, Facilities and Services

    217-244-3686

    Attached Files: 
  13. News about Christopher Hall winning

    Saving energy pays off for Christopher Hall

    Clayton Glazik 3/5/2014

    Since we were little our parents have told us to turn off the lights after we leave a room. That is just what the Christopher Hall residents at the University of Illinois did in 2013. By shutting the lights off in rooms not in use, switching their lights to compact fluorescent light (CFL) bulbs, as well as other sustainable practices, the building was able to cut back its energy usage by 30.6% from the previous year.

    The campus Facilities & Services (F&S) hosted a reception at Christopher Hall on February 14 to celebrate the building’s accomplishment in the F&S Energy Conservation Incentive Program (ECIP). A campus-wide sustainability effort, ECIP provides building upgrades to facilities that produce top energy conservation results in energy advancement and occupant action categories. ECIP calculates how much money the buildings are saving in energy reduction and gives it back to the building to pay for upgrades.

    Christopher Hall, which houses the Family Resiliency Center (FRC), the Autism Program (TAP), several classrooms, faculty and staff offices, and a family research home, saved nearly $22,000. According to FRC Director Barbara Fiese, a building committee recommended investing the funds in a bike rack since so many people cycle to work, as well as other items that can further reduce energy usage.

    In 2010, the University of Illinois published a climate action plan that set aggressive timeliness for reducing energy consumption on campus. Currently, there are more than 300 such active projects, which can be tracked at http://icap.sustainability.illinois.edu/projects.

    “At the end of the day, if we really want to meet ICAP goals, we have to do more,” says Al Stratman, F&S executive director. “That is why we came up with ECIP, which mirrors the campus goals.”

    At the award ceremony, faculty and students pledged to continue reducing energy in their lifestyles by taking public transportation, using natural light in their offices rather than electricity, and shopping more at local food markets instead of commercial grocery stores. With their current sustainable practices and these recent pledges, Christopher Hall will continue slashing their energy consumption, making the Illinois campus a greener place.

    (from Family Resiliency Center news http://illinois.edu/lb/article/3493/82438)