Campus Bike Plan progress report FY24
Please see attached the Campus Bike Plan progress report FY24.
Read the Campus Bike Plan progress report FY23
Please see attached the Campus Bike Plan progress report FY24.
Read the Campus Bike Plan progress report FY23
The Transportation iCAP Team met on 4/10/2024 to discuss the final draft of the DESMAN study report, progress on the 2020 Transportation iCAP objectives, and potential 2025 Transportation iCAP goals. Attached is a link to the meeting recording.
Hi all,
We have completed all outdoor bin location proposals. With all the photos it is a large document, so I have placed it on a shared Box. Please let me know if any of these locations need further clarification
In response to your question below of completion by June 30 that is not possible. Also, without knowing all of the locations it is difficult to give you an answer as to what the completion timeframe would be. Below are the two scenarios depending on the proposed locations of the bins.
Installing the bins on existing concrete:
1. Ironworkers can go to the site with the bins/post with two guys and install the anchors and the bins in 2-3 crew hours (4-6 hours total with two guys).
Installing the bins on newly placed concrete:
1. This process will begin with the labor supervisor going to the site and marking the location. 1-2 hours
2. The utility marking crew would then be notified, and they have a 48 hour window to locate utilities. 1-2 hours
3. Laborers and operators go to the site and dig out the spot and place rock. 3-4 crew hours
4. Cement finishers form and pour the concrete and it needs to cure for at least 48 hours. 3-4 crew hours
5. Ironworkers can install the anchors and the bin once concrete has cured. 2-3 crew hours
Depending on how closely the locations are to each other they may prepare 2 or 3 at once and rotate through those with the different steps above. However, that is not always possible.
I hope this helps to see how the two differ in time needed and to see how it really gets involved when the location requires new concrete.
I wanted to reach out & reconnect on the topic of the black, metal outdoor bins. I believe we have 18 identified locations approved by Brent Lewis ready to be installed as soon as the shops are able (locations attached) – these all require concrete poured. We then have ~56 more stored primarily in the Buenting Barn that we have not yet identified locations for, but will very shortly. Some of them will require concrete and others will not. We have WO# 10814481 for this project. Pete is hoping to have the whole process wrapped up by June 30, 2024. I just wanted to put this back up on the radar and get a sense of whether we will be able to get these all installed by summer?
I will be in contact soon regarding the locations of the remaining bins.
Using the #EPASmartWay logo helps differentiate your company from the competition. Be sure to let your customers and stakeholders know that you’re leading the way on clean, sustainable supply chain management. Learn more: epa.gov/smartway
All, Slow week with the bad weather. This week looks better. Friday we’re helping with the Campus Recreation Walking Tour and so will show off our space to some folks that probably wouldn’t visit otherwise—that’ll be fun.
Also have a couple new staff starting this week.
The numbers:
Visitors: 14
Sales: $223.50
Memberships: 2 for $60
Tires/tubes: 4 for $35
Thanks!
Jacob Benjamin
Coordinator -- Campus Bike Center
The Land & Water iCAP team met on Teams from 1-2 PM on Friday, April 5th. Meeting minutes are attached.
RailSplitter Wind Farm provided the March 2024 Buyer's Share amounts by the hour, totaling 3,001.00 Megawatt hours.
The March 2024 Buyer's Share Report is attached below.
The Illinois Climate Action Plan (iCAP) Working Group (iWG) recently approved recommendation Edu009 from the Education iCAP Team to update College of Business course descriptions to reflect the sustainability content.
This recommendation aligns with Objective 6.2 of the iCAP 2020: Establish a comprehensive online repository for courses and academic programs with sustainability content.
The College of Business shared their action plan on completing the approved recommendation (attached).
This will be followed up on in the fall to ensure the proper implementation of the recommendation.
The Education iCAP team met on Teams from 1-2 PM on Thursday, April 4th. Meeting minutes are attached.
All, It’s April! Busier week over here with the warm spell. Tues/Thurs continue to be slower days and the 4 – 6p side of our hours remain more popular—anecdotally. I’ll dig into the numbers and see if that bears out.
We are also trying out new sales tickets for our bikes, with the hopes that it’ll speed up that process as demand at the computer/square station will increase between our checkouts and the Adv. Rec folks.
We received a large donation on Thursday, which we’ll continue to work through this week. Will also facilitate a staff training for a new hire. Plan to tackle some of the abandoned bikes as well.
The numbers:
Visitors: 38
Sales: $727
Bikes (refurb): 2 for $275
Bikes (B-a-B): 1 for $50
Memberships: 4 for $120
Tires/tubes: 2 for $19
Thanks!
Jacob Benjamin
Coordinator -- Campus Bike Center
March 2024 photos of the Florida Orchard Prairie have been added to the box folder.
At Friday's Illini Lights Out event, 4070 light bulbs were shut off that otherwise would have been left on all weekend, saving $619 in energy costs. This also prevented 4.9 metric tons of CO2 equivalent from entering the atmosphere, which is equivalent to the greenhouse gas emissions from 552 gallons of gasoline being consumed. That's a huge impact!
This project name was "Fossil Fuels Divestment" which is a misstatement because the University of Illinois Urbana-Champaign does not have direct authority over the investments at the UI Foundation. To clarify the goal of this objective in the 2020 iCAP, I updated the project name to be "Fossil Fuels Divestment - Support Letter." I also provided more details in the project description, and added the full text from the iCAP 2020 document in the background section of this project page. ~Morgan
All, First week of being open M – F wasn’t blow-the-doors-off-busy. Tuesday was a dud, but Thursday picked up a little. Think it’ll take a little longer to get the word out on our new hours, and of course it’s always weather-dependent to a degree.
We had a visit from Indiana University sustainability folks on Friday, which was good.
This week is business as usual and next week it’ll be April! That undoubtedly will be a busy month.
The numbers:
Visitors: 26
Sales: $934.09
Bikes (refurb): 3 for $540
Bikes (B-a-B): 1 for $50
Memberships: 6 for $180
Tires/tubes: 10 for $65
Thanks!
Jacob Benjamin
Coordinator -- Campus Bike Center
Miriam Keep, Codie Sterner, and Michael McKelvey met to continue discussing how to approach embedding projects from the iCAP Portal on the SSC website.
We discussed several possible ways to represent SSC Projects using the iCAP Portal:
We decided to pursue the 3rd option (multiple semesters of information added to a project). It seems like the simplest approach.
Codie would like it ready to go by summer, when he'll have staff who can work on the data entry. Goal of completion by start of fall semester.
Michael will mock something up for our next iCAP Portal meeting so we can run it by the group and get feedback.
Michael McKelvey, Miriam Keep, and Morgan White met to finalize the discussion of how to structure iCAP Recommendations. We came to an agreement on the structure which we diagrammed online. Recommendations will be patterned after Metrics. If a Recommendation update warrants a Project Update, that will need to be added manually; it will not happen automatically with this approach.
Summary of structure:
Detailed structure:
Additionally, we do not plan to use the iCAP Portal to collect Recommendation feedback - a shared Word Doc on Teams is more conducive to this process. Certain fields in a recommendation will be added to the iCAP Portal Recommendation, and the uploaded document will contain more details, including comments.
I have attached files for the digital sign and the posters. I will get our marketing staff to add the digital sign to our boards in the next couple weeks, and I have asked them to add it to a future issue of Housing Insider. We already talked about the hall posters, but the larger foam board signs you can also bring to me and I will get them delivered to the halls. To cover all the halls we will need 20. I have seen them produced with the a build in fold out stand on the back, which would make it really easy to place in the halls as opposed to having to get a easel for each sign. But we can make either work.
Let me know if you have any questions or thoughts on the design.
BRYAN JOHNSON
Hi Bryan,
Thank you for sending these over! I wanted to follow up with a couple of items:
Thank you,
Daphne
The marketing person who typically orders the poster board signs is out of the office today, but she is expected back tomorrow. She is supposed to get me an answer on how we can get them produced when she returns. Until then, here are updated creatives with the suggestions you provided. Let me know if these look good.
BRYAN JOHNSON