You are here
Home
Recommendations
Recommendation Updates
Recommendation Updates
Search
Theme
- Any -
Energy
Transportation
Land and Water
Zero Waste
Resilience
Reporting Progress
Engagement
Education
Research
Funding
Status
- Any -
Submitted
Transmitted
Assessment Started
Assessment Completed
Successful
Withdrawn
Returned
Supplanted
Denied/Declined
Sort by
Recommendation Title
Update Title
Update Date
Order
Asc
Desc
Recommendation
Update
Update Date
Theme
Status
ECONS001 Conservation Budget
ECBS001 was supplanted by ECBS003
5/17/2016
Energy
Supplanted
ECONS001 Conservation Budget
ECBS SWATeam submitted ECONS001
5/4/2015
Energy
Submitted
ECONS001 Conservation Budget
iWG met to discuss and assess ECONS001
5/21/2015
Energy
Assessment Completed
ECONS002 Illini Lights Out
iWG met to discuss, assess, and approve ECON002
3/30/2016
Energy
Successful
ECONS002 Illini Lights Out
ECBS SWATeam submitted ECONS002
3/4/2016
Energy
Submitted
ECONS003 Conservation Budget
ECBS SWATeam sumbitted ECONS003
5/17/2016
Energy
Submitted
ECONS003 Conservation Budget
iWG met to discuss and assess ECONS003
5/31/2016
Energy
Assessment Completed
ECONS003 Conservation Budget
ECONS003 transmitted to the Office of the Provost
3/6/2017
Energy
Transmitted
ECONS003 Conservation Budget
Interim Provost Wilkin approved ECONS003
7/10/2017
Energy
Successful
ECONS004 Green Labs Coordinator
iWG met to discuss and assess ECONS004
3/27/2017
Energy
Assessment Completed
ECONS004 Green Labs Coordinator
Energy001 was transmitted to Melanie Loots and Jan Novakofski from the VCR's office.
7/15/2017
Energy
Transmitted
ECONS004 Green Labs Coordinator
ECBS SWATeam sumbitted ECONS004
11/29/2016
Energy
Submitted
ECONS005 Illini Lights Out Continuation
ECBS SWATeam submitted ECONS005
4/6/2017
Energy
Submitted
ECONS005 Illini Lights Out Continuation
ECONS005 transmitted to iSEE
7/12/2017
Energy
Transmitted
ECONS005 Illini Lights Out Continuation
iWG met to discuss and assess ECONS005
7/12/2017
Energy
Assessment Completed
ECONS006 Energy Conservation Funding 2017
ECONS006 approved by matthew Tomaszewski
5/11/2018
Energy
Successful
ECONS006 Energy Conservation Funding 2017
ECON006 transmitted to Provost Andreas Cangellaris
4/10/2018
Energy
Transmitted
ECONS006 Energy Conservation Funding 2017
ECBS SWATeam submitted ECONS006
11/27/2017
Energy
Submitted
ECONS006 Energy Conservation Funding 2017
iWG met to discuss and assess ECONS006
3/28/2018
Energy
Assessment Completed
ECONS007 Energy Conservation Funding 2018
ECBS SWATeam sumbitted ECONS007
5/7/2018
Energy
Submitted
ECONS007 Energy Conservation Funding 2018
ECONS007 returned to SWATeam by iWG
9/19/2018
Energy
Returned
eGen001 Wind PPA recommendation
iWG met to discuss and assess eGen001
8/28/2014
Energy
Assessment Completed
eGen001 Wind PPA recommendation
eGen SWATeam submitted eGen001
7/25/2014
Energy
Submitted
eGen001 Wind PPA recommendation
eGen001 transmitted to Facilities and Services
8/28/2014
Energy
Transmitted
eGen002 Utilities Master Plan Review
eGen002 transmitted to Facilites and Services
5/29/2015
Energy
Transmitted
eGen002 Utilities Master Plan Review
eGen SWATeam submitted eGen003
5/4/2015
Energy
Submitted
eGen002 Utilities Master Plan Review
Facilities and Services denied eGen002
6/15/2015
Energy
Denied/Declined
eGen002 Utilities Master Plan Review
iWG met to discuss and assess eGen002
5/28/2015
Energy
Assessment Completed
eGen003 PPA term
eGen SWATeam submitted eGen003
2/29/2016
Energy
Submitted
eGen003 PPA term
iWG met to discuss and assess eGen003
4/6/2016
Energy
Assessment Completed
eGen003 PPA term
eGen003 transmitted to the Sustainability Council
3/6/2017
Energy
Transmitted
eGen003 PPA term
Provost Wilkins approved eGen003
7/10/2017
Energy
Successful
eGen004 Electrification Study
eGen SWATeam submitted eGen004
2/5/2016
Energy
Submitted
eGen004 Electrification Study
iWG returned eGen004 to the SWATeam
12/12/2016
Energy
Returned
eGen005 Rooftop Solar Standards
eGen SWATeam submitted eGen005
2/9/2017
Energy
Submitted
eGen005 Rooftop Solar Standards
iWG met to discuss and assess eGen005
2/23/2017
Energy
Assessment Completed
eGen006 Petascale Offsets
eGen006 transmitted to the Vice Chancellor for Research (VCR).
7/12/2017
Energy
Transmitted
eGen006 Petascale Offsets
eGen SWATeam submitted eGen006
2/9/2017
Energy
Submitted
eGen006 Petascale Offsets
iWG met to discuss and assess eGen006
2/23/2017
Energy
Assessment Completed
eGen007 Solar Farm 2.0
eGen SWATeam submitted eGen007
4/28/2017
Energy
Submitted
eGen007 Solar Farm 2.0
eGen007 transmitted to the Sustainability Council
12/7/2017
Energy
Transmitted
eGen007 Solar Farm 2.0
iWG met to discuss and assess eGen007
10/27/2017
Energy
Assessment Completed
eGen008 Pursue Solar PPA
eGen SWATeam submitted eGen008
5/8/2018
Energy
Submitted
eGen008 Pursue Solar PPA
eGen008 assessment started
5/10/2018
Energy
Assessment Started
eGen009 Campus Geothermal Policy
eGen009 assessment started
6/7/2019
Energy
Assessment Started
eGen009 Campus Geothermal Policy
eGen SWATeam submitted eGen009
5/27/2019
Energy
Submitted
eGen009 Campus Geothermal Policy
Dr. Mohamed Attalla, Executive Director at F&S approved eGen009
8/27/2019
Energy
Successful
eGen009 Campus Geothermal Policy
eGen009 transmitted to Dr. Mohamed Attalla, Director of Facilities & Services.
8/10/2019
Energy
Transmitted
eGen010 Geothermal Feasibility Study
Andy Stumpf responded to eGen010
10/3/2019
Energy
Withdrawn
eGen010 Geothermal Feasibility Study
eGen SWATeam submitted eGen010
5/27/2019
Energy
Submitted
eGen010 Geothermal Feasibility Study
iWG assessed and returned to SWATeam
8/10/2019
Energy
Returned
eGen010 Geothermal Feasibility Study
eGen010 assessment started
5/27/2019
Energy
Assessment Started
Energy001 Anaerobic Digester Feasibility Study
The EnergySWATeam submitted Energy001
4/3/2020
Energy
Submitted
Energy001 Anaerobic Digester Feasibility Study
Energy001 was transmitted to German Bollero (ACES Associate Dean for Research) and Doug Wolters (Director of Operations, Facilities Planning and Management)
11/4/2020
Energy
Transmitted
Energy001 Anaerobic Digester Feasibility Study
ACES approved Energy001
11/13/2020
Energy
Successful
Energy002 Building Envelope
Energy002 transmitted to Mohamed Attalla, Executive Director of Facilities and Services
6/3/2020
Energy
Transmitted
Energy002 Building Envelope
The Energy SWATeam submitted Energy002
4/7/2020
Energy
Submitted
Energy002 Building Envelope
F&S approved Energy002
10/8/2020
Energy
Successful
Energy003 Energy Master Plan
Energy SWATeam submitted Energy003
4/3/2020
Energy
Submitted
Energy003 Energy Master Plan
Energy003 was supplanted by Energy007
4/7/2020
Energy
Supplanted
Energy004 - Energy Conservation Funding
UES approves Energy004
10/22/2021
Energy
Successful
Energy004 - Energy Conservation Funding
Energy004 transmitted to the Sustainability Council
4/28/2021
Energy
Transmitted
Energy004 - Energy Conservation Funding
Energy iCAP Team submitted Energy004
4/3/2020
Energy
Submitted
Energy005 Modeling for Energy Code Compliance
Energy iCAP Team submitted Energy005
2/11/2021
Energy
Submitted
Energy005 Modeling for Energy Code Compliance
F&S approves Energy005
11/2/2024
Energy
Successful
Energy005 Modeling for Energy Code Compliance
Energy005 transmitted to Dr. Mohamed Attalla
4/15/2021
Energy
Transmitted
Energy006 Integrate iCAP Goals into Research/Learning Labs
Energy006 transmitted to Sustainability Council
11/29/2021
Energy
Transmitted
Energy006 Integrate iCAP Goals into Research/Learning Labs
Sustainability Council and Associate Vice Chancellor for Research approve Energy006
11/29/2021
Energy
Successful
Energy006 Integrate iCAP Goals into Research/Learning Labs
Energy iCAP Team submitted Energy006
6/8/2021
Energy
Submitted
Energy007 Implementation of Comprehensive Energy Plan
Energy iCAP Team submitted Energy007
6/8/2021
Energy
Submitted
Energy007 Implementation of Comprehensive Energy Plan
Energy007 transmitted to Sustainability Sub-Council and Sustainability Council
11/29/2021
Energy
Transmitted
Energy007 Implementation of Comprehensive Energy Plan
Sustainability Council, iSEE, and F&S approve Energy007
11/29/2021
Energy
Successful
Energy008 Charging Responsibility for Meeting iCAP Energy Goals
Energy iCAP Team submitted Energy008
2/8/2021
Energy
Submitted
Energy009 MMR Safety and Security
Energy iCAP Team submitted Energy009
2/8/2021
Energy
Submitted
Energy009 MMR Safety and Security
Energy009 declined by iWG
11/14/2022
Energy
Denied/Declined
Energy010 Establishment of a Clean Energy Plan Conference Committee
Energy iCAP Team withdrew Energy010
2/7/2023
Energy
Withdrawn
Energy010 Establishment of a Clean Energy Plan Conference Committee
Energy iCAP Team submitted Energy010
11/30/2022
Energy
Submitted
Energy011 Priority Technologies and Practices for a Clean Energy Plan
Energy iCAP Team submitted Energy011
12/1/2022
Energy
Submitted
Energy011 Priority Technologies and Practices for a Clean Energy Plan
Energy011 transmitted to Associate Vice Chancellor and Executive Director of F&S
4/10/2023
Energy
Transmitted
Energy011 Priority Technologies and Practices for a Clean Energy Plan
F&S approved Energy011
5/5/2023
Energy
Successful
Trans014 Electric Vehicle Task Force Membership
Transportation iCAP team Trans014
12/21/2021
Transportation
Submitted
Trans014 Electric Vehicle Task Force Membership
F&S approved Trans014
4/17/2022
Transportation
Submitted
Trans014 Electric Vehicle Task Force Membership
Trans014 transmitted to Dr. Ehab Kamarah, Associate Vice Chancellor and Executive Director of Facilities & Services
3/29/2022
Transportation
Transmitted
Trans015 Fleet Replacement
Transportation iCAP team Trans015
5/8/2023
Transportation
Submitted
Trans015 Fleet Replacement
Trans015 transmitted to Dr. Ehab Kamarah, Associate Vice Chancellor and Executive Director of Facilities & Services
9/26/2023
Transportation
Transmitted
Trans015 Fleet Replacement
F&S approved Trans015
10/11/2023
Transportation
Successful